STF PALONG TIMUR REV.00 RUN ALL BS 24.03.

2018 Classic Schedule Layout 05-May-18 03:24 PM


Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 300.0d 155.0d -95.0d 02-Oct-17 08:00 22-Sep-18 08:00 78.21% 38.66%
AM A AM
Milestone 300.0d 0.0d -95.0d 02-Oct-17 08:00 AM A
22-Sep-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -95.0d 22-Sep-18 08:00 AM22-Sep-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%

Documentation 32.0d 0.0d 02-Oct-17 08:00 AM A


07-Nov-17 05:00 PM A 100% 100%
Preparation & Submission 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1000 Preparation of Performance Bond 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1010 Preparation of Insurance Policies / Public Liability / Workmen's Compensation
14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1020 Preparation & Submission of Levy of CIDB 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1030 Site Registration of JKKP (DOSH) 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1040 Submission Copy of SPAN Certificate 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1050 Preparation & Submission of Lithography Expenses 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1060 Preparation & Submission of PQP / Method Statements 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
A1070 Preparation of Works (Contractor Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1080 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1090 Preparation of Works (General Obligation, Project Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1100 Preparation of Works (Authorities Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
A1110 Preparation of Works (Environmental Protection & Enhancement) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
Civil & Structure Works 180.0d 91.0d -48.0d 06-Dec-17 08:00 AM08-Jul-18
A 05:00 PM 94.17% 25.4%

Preliminary Works 22.0d 0.0d 11-Dec-17 08:00 AM30-Jan-18


A 05:00 PM A 100% 100%
Setting Up of Site 12.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
A1120 Site measurement & site survey 12.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
Earthwork 12.0d 0.0d 22-Dec-17 08:00 AM30-Jan-18
A 05:00 PM A 100% 100%
A1130 Site clearance & excavation works 12.0d 0.0d 22-Dec-17 08:00 AM30-Jan-18
A 05:00 PM A 100% 100%
Water Retaining Structure 155.0d 66.0d -23.0d 06-Dec-17 08:00 AM09-Jun-18
A 05:00 PM 86.73% 48.94%
Wash Water Collection & Sludge Balancing Tank 155.0d 66.0d -23.0d 06-Dec-17 08:00 AM09-Jun-18
A 05:00 PM 86.73% 48.94%
Substructure 53.0d 0.0d 06-Dec-17 08:00 AM10-Mar-18
A 05:00 PM A 100% 100%
A1140 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM06-Mar-18
A 05:00 PM A 100% 100%
A1150 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM06-Mar-18
A 05:00 PM A 100% 100%
A1160 Concreting work 5.0d 0.0d 03-Feb-18 08:00 AM 10-Mar-18
A 05:00 PM A 100% 100%
Wall & Top Slab 86.0d 60.0d -23.0d 22-Feb-18 08:00 AM 02-Jun-18
A 05:00 PM 91.67% 20%

Page 1 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 Classic Schedule Layout 05-May-18 03:24 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1170 Frame 24.0d 24.0d -23.0d 22-Feb-18 08:00 AM 21-Apr-18


A 05:00 PM 100% 50%
A1180 External finishes 18.0d 18.0d -23.0d 22-Apr-18 08:00 AM 13-May-18 05:00 PM 100% 0%
A1190 Internal finishes 18.0d 18.0d -23.0d 14-May-18 08:00 AM02-Jun-18 05:00 PM 72.22% 0%
Backfilling & Compaction 18.0d 18.0d -23.0d 14-May-18 08:00 AM02-Jun-18 05:00 PM 72.22% 0%
A1210 Backfill, level & compact 18.0d 18.0d -23.0d 14-May-18 08:00 AM02-Jun-18 05:00 PM 72.22% 0%
Testing 6.0d 6.0d -23.0d 03-Jun-18 08:00 AM 09-Jun-18 05:00 PM 0% 0%
A1200 Cleaning & Water Tighness Testing 6.0d 6.0d -23.0d 03-Jun-18 08:00 AM 09-Jun-18 05:00 PM 0% 0%
Platform Structure 180.0d 91.0d -78.0d 06-Dec-17 08:00 AM08-Jul-18
A 05:00 PM 96.22% 13.33%
Dewatering Container (Geotube) 180.0d 91.0d -78.0d 06-Dec-17 08:00 AM08-Jul-18
A 05:00 PM 96.22% 13.33%
Substructure (Drain & Slab) 120.0d 31.0d -78.0d 06-Dec-17 08:00 AM29-Apr-18
A 05:00 PM 100% 27.37%
A1220 Install reinforcement 26.0d 26.0d -78.0d 06-Dec-17 08:00 AM23-Apr-18
A 05:00 PM 100% 30%
A1230 Install formwork 26.0d 26.0d -78.0d 10-Dec-17 08:00 AM23-Apr-18
A 05:00 PM 100% 30%
A1240 Concreting work 5.0d 5.0d -78.0d 24-Apr-18 08:00 AM 29-Apr-18 05:00 PM 100% 0%
Ramp 24.0d 24.0d -78.0d 30-Apr-18 08:00 AM 28-May-18 05:00 PM 100% 0%
A1250 Formwork, reinforcement, concrete & cover 24.0d 24.0d -78.0d 30-Apr-18 08:00 AM 28-May-18 05:00 PM 100% 0%
Geotube 36.0d 36.0d -78.0d 29-May-18 08:00 AM08-Jul-18 05:00 PM 86.11% 0%
A1260 Preparation & installation 36.0d 36.0d -78.0d 29-May-18 08:00 AM08-Jul-18 05:00 PM 86.11% 0%
Building 180.0d 91.0d -48.0d 06-Dec-17 08:00 AM08-Jul-18
A 05:00 PM 97.54% 7.54%
Polymer Plant 180.0d 91.0d -48.0d 06-Dec-17 08:00 AM08-Jul-18
A 05:00 PM 97.54% 7.54%
Substructure (Footing, Stump, Ground Beam & Slab) 120.0d 31.0d -48.0d 06-Dec-17 08:00 AM29-Apr-18
A 05:00 PM 100% 27.37%
A1270 Install reinforcement 26.0d 26.0d -48.0d 06-Dec-17 08:00 AM23-Apr-18
A 05:00 PM 100% 30%
A1280 Install formwork 26.0d 26.0d -48.0d 10-Dec-17 08:00 AM23-Apr-18
A 05:00 PM 100% 30%
A1290 Concreting work 5.0d 5.0d -48.0d 24-Apr-18 08:00 AM 29-Apr-18 05:00 PM 100% 0%
Frame (Upper Beam & Column) 24.0d 24.0d -48.0d 30-Apr-18 08:00 AM 28-May-18 05:00 PM 100% 0%
A1300 Scaffold, stagging, formwork, reinforcement, t-prox, soffit & concrete 24.0d 24.0d -48.0d 30-Apr-18 08:00 AM 28-May-18 05:00 PM 100% 0%
Ramp & Drain 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1310 Excavation, levelling, formwork, reinforcement & concrete 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Roof 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1320 Install roof truss & covering 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Wall 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1330 Scaffold, stagging, formwork, reinforcement & concrete 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Accessories 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1340 Install frame, doors, windows, roller shutter & lockset 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%

Page 2 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 Classic Schedule Layout 05-May-18 03:24 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

External Finishes 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1350 External plastering & painting 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Internal Floor & Wall Finishes 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 18.0d -48.0d 29-May-18 08:00 AM17-Jun-18 05:00 PM 100% 0%
Ceiling Finishes 18.0d 18.0d -48.0d 18-Jun-18 08:00 AM 08-Jul-18 05:00 PM 72.22% 0%
A1370 Install frame, ceiling & painting 18.0d 18.0d -48.0d 18-Jun-18 08:00 AM 08-Jul-18 05:00 PM 72.22% 0%
Pipeworks 155.0d 78.0d -35.0d 20-Dec-17 08:00 AM23-Jun-18
A 05:00 PM 98.89% 12%

Procurement 24.0d 24.0d -35.0d 20-Dec-17 08:00 AM21-Apr-18


A 05:00 PM 100% 60%
A1380 To procure & deliver Pipes to site 24.0d 24.0d -35.0d 20-Dec-17 08:00 AM21-Apr-18
A 05:00 PM 100% 60%
Installation 48.0d 48.0d -35.0d 22-Apr-18 08:00 AM 16-Jun-18 05:00 PM 100% 0%
A1390 Excavation & backfilling works 24.0d 24.0d -35.0d 22-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1400 Pipe laying & jointing 24.0d 24.0d -35.0d 22-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1410 Connection to existing Chamber / Pipes 24.0d 24.0d -35.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
A1420 Miscellaneous works 18.0d 18.0d -29.0d 21-May-18 08:00 AM09-Jun-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -35.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%
A1430 Cleaning & testing works 6.0d 6.0d -35.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%
Mechanical Works 233.0d 132.0d -72.0d 22-Nov-17 08:00 AM25-Aug-18
A 05:00 PM 78.04% 36.71%

Drawing & Material Approval 24.0d 0.0d 22-Nov-17 08:00 AM19-Dec-17


A 05:00 PM A 100% 100%
A1440 Submission of Drawing / Material for approval 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
A1450 Review & approval for Drawing / Material 12.0d 0.0d 06-Dec-17 08:00 AM19-Dec-17
A 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 209.0d 120.0d -71.0d 06-Dec-17 08:00 AM11-Aug-18
A 05:00 PM 60.86% 40%
Procurement 102.0d 102.0d -71.0d 06-Dec-17 08:00 AM21-Jul-18
A 05:00 PM 76.79% 60%
A1460 Horizontal Screw Pump, Subermisble Supernatant Pump 72.0d 72.0d -71.0d 06-Dec-17 08:00 AM16-Jun-18
A 05:00 PM 100% 60%
A1470 FAT Wash Water Recovery Pumpset 6.0d 6.0d -71.0d 05-Mar-18 08:00 AM23-Jun-18
A 05:00 PM 100% 60%
A1480 Pipes, Fittings & Valves 30.0d 30.0d -71.0d 05-Mar-18 08:00 AM21-Jul-18
A 05:00 PM 56.67% 60%
A1490 Submersible Mixer 30.0d 30.0d -71.0d 05-Mar-18 08:00 AM21-Jul-18
A 05:00 PM 56.67% 60%
A1500 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d -71.0d 05-Mar-18 08:00 AM21-Jul-18
A 05:00 PM 56.67% 60%
Installation 42.0d 42.0d -71.0d 24-Jun-18 08:00 AM 11-Aug-18 05:00 PM 13.1% 0%
A1510 Construction of Horizontal Screw Pump Pit 24.0d 24.0d -71.0d 24-Jun-18 08:00 AM 21-Jul-18 05:00 PM 45.83% 0%
A1520 Horizontal Screw Pump, Subermisble Supernatant Pump 18.0d 18.0d -71.0d 22-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1530 Pipes, Fittings & Valves 18.0d 18.0d -71.0d 22-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1540 Submersible Mixer 12.0d 12.0d -71.0d 22-Jul-18 08:00 AM 04-Aug-18 05:00 PM 0% 0%

Page 3 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 Classic Schedule Layout 05-May-18 03:24 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -71.0d 22-Jul-18 08:00 AM 04-Aug-18 05:00 PM 0% 0%
Existing Sedimentation Tank 197.0d 108.0d -65.0d 06-Dec-17 08:00 AM28-Jul-18
A 05:00 PM 89.62% 39.13%
Procurement 60.0d 60.0d -41.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1560 Submersible Sludge Pump 60.0d 60.0d -65.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1570 Pipes, Fittings & Valves 30.0d 30.0d -11.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
Installation 48.0d 48.0d -65.0d 03-Jun-18 08:00 AM 28-Jul-18 05:00 PM 60.42% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -65.0d 03-Jun-18 08:00 AM 30-Jun-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -65.0d 01-Jul-18 08:00 AM 28-Jul-18 05:00 PM 20.83% 0%
Polymer Plant 221.0d 132.0d -89.0d 06-Dec-17 08:00 AM25-Aug-18
A 05:00 PM 70.5% 25.86%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -29.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -89.0d 06-Dec-17 08:00 AM02-Jun-18
A 05:00 PM 100% 60%
A1620 Crane / Lifting Equipment 30.0d 30.0d 1.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d 1.0d 06-Dec-17 08:00 AM28-Apr-18
A 05:00 PM 100% 60%
Fabrication 36.0d 36.0d -65.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 85.29% 0%
A1640 Mixing & Service Tank 36.0d 36.0d -89.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 80.56% 0%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -89.0d 03-Jun-18 08:00 AM 14-Jul-18 05:00 PM 80.56% 0%
A1660 Local Control Panel 30.0d 30.0d -59.0d 03-Jun-18 08:00 AM 07-Jul-18 05:00 PM 96.67% 0%
Installation 36.0d 36.0d -89.0d 15-Jul-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -89.0d 15-Jul-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
A1700 Local Control Panel 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -89.0d 12-Aug-18 08:00 AM 25-Aug-18 05:00 PM 0% 0%
Pipeworks 155.0d 78.0d -18.0d 20-Dec-17 08:00 AM23-Jun-18
A 05:00 PM 98.39% 18.46%
Procurement 24.0d 24.0d -5.0d 20-Dec-17 08:00 AM21-Apr-18
A 05:00 PM 100% 60%
A1730 To procure & deliver Pipes to site 24.0d 24.0d -5.0d 20-Dec-17 08:00 AM21-Apr-18
A 05:00 PM 100% 60%
Installation 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
A1740 Excavation & backfilling works 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
A1750 Pipe laying & jointing 24.0d 24.0d -29.0d 21-May-18 08:00 AM16-Jun-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -18.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%

Page 4 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 Classic Schedule Layout 05-May-18 03:24 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1760 Cleaning & testing works 6.0d 6.0d -18.0d 17-Jun-18 08:00 AM 23-Jun-18 05:00 PM 83.33% 0%
Miscellaneous Works 177.0d 100.0d -57.0d 20-Dec-17 08:00 AM18-Jul-18
A 05:00 PM 90.22% 46.88%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM11-Jan-18
A 05:00 PM A 100% 100%
Procurement 61.0d 61.0d -57.0d 13-Jan-18 08:00 AM 0
A3-Jun-18 05:00 PM 98.77% 60%
A1780 Booster Pump 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1790 Air Compressor Set 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d -57.0d 13-Jan-18 08:00 AM 2
A8-Apr-18 05:00 PM 100% 60%
A1810 Portable Water jet 12.0d 12.0d -57.0d 13-Jan-18 08:00 AM 0
A7-Apr-18 05:00 PM 100% 60%
A1820 Penstock & Valves 60.0d 60.0d -57.0d 13-Jan-18 08:00 AM 0
A2-Jun-18 05:00 PM 98.33% 60%
A1830 FAT Penstock / Valves 1.0d 1.0d -57.0d 26-Mar-18 08:00 AM03-Jun-18
A 05:00 PM 0% 60%
Installation 70.0d 70.0d -57.0d 29-Apr-18 08:00 AM 18-Jul-18 05:00 PM 54.55% 0%
A1840 Booster Pump Set 18.0d 18.0d -35.0d 29-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1850 Air Compressor Set 18.0d 18.0d -35.0d 29-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1860 Penstock / Valves 30.0d 30.0d -57.0d 14-Jun-18 08:00 AM 18-Jul-18 05:00 PM 0% 0%
Electrical Works 251.0d 138.0d -95.0d 08-Nov-17 08:00 AM01-Sep-18
A 05:00 PM 52.82% 41.05%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM05-Dec-17


A 05:00 PM A 100% 100%
A1870 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM21-Nov-17
A 05:00 PM A 100% 100%
A1880 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
Switchboard / MCC Panel 201.0d 100.0d -57.0d 22-Nov-17 08:00 AM18-Jul-18
A 05:00 PM 80% 44.35%
A1890 Procurement & fabrication of Panel 84.0d 84.0d -95.0d 22-Nov-17 08:00 AM30-Jun-18
A 05:00 PM 100% 60%
A1900 FAT Electrical Control & Swicthboards 1.0d 1.0d -57.0d 27-Mar-18 08:00 AM04-Jun-18
A 05:00 PM 0% 60%
A1910 Installation works 30.0d 30.0d -57.0d 14-Jun-18 08:00 AM 18-Jul-18 05:00 PM 0% 0%
Submain Cabling Works for MCC-SDP-Palong 155.0d 54.0d -95.0d 05-Mar-18 08:00 AM01-Sep-18
A 05:00 PM 38.64% 26.67%
A1920 Procurement & delivery of Cable 24.0d 24.0d -95.0d 05-Mar-18 08:00 AM28-Jul-18
A 05:00 PM 70.83% 60%
A1930 Installation & cabling works 30.0d 30.0d -95.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 0% 0%
Distribution & Earthing System 155.0d 54.0d -95.0d 05-Mar-18 08:00 AM01-Sep-18
A 05:00 PM 38.64% 26.67%
A1940 Procurement & delivery 24.0d 24.0d -95.0d 05-Mar-18 08:00 AM28-Jul-18
A 05:00 PM 70.83% 60%
A1950 Installation & cabling works 30.0d 30.0d -95.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 0% 0%
Compound Lighting System 155.0d 54.0d -95.0d 05-Mar-18 08:00 AM01-Sep-18
A 05:00 PM 38.64% 26.67%
A1960 Procurement & delivery 24.0d 24.0d -95.0d 05-Mar-18 08:00 AM28-Jul-18
A 05:00 PM 70.83% 60%
A1970 Installation & cabling works 30.0d 30.0d -95.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 0% 0%

Page 5 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 24.03.2018 Classic Schedule Layout 05-May-18 03:24 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Relocation of Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18


A 05:00 PM A 0% 100%
A1980 To relocate existing Cable 30.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18
A 05:00 PM A 0% 100%
Miscellaneous Works 30.0d 30.0d -95.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 0% 0%
A1990 Any other neccessary works 30.0d 30.0d -95.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 0% 0%
Instrumentation Works 227.0d 114.0d -73.0d 08-Nov-17 08:00 AM04-Aug-18
A 05:00 PM 83.72% 54.24%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM05-Dec-17


A 05:00 PM A 100% 100%
A2000 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM21-Nov-17
A 05:00 PM A 100% 100%
A2010 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM05-Dec-17
A 05:00 PM A 100% 100%
Procurement & Fabrication 84.0d 84.0d -73.0d 22-Nov-17 08:00 AM30-Jun-18
A 05:00 PM 98.82% 60.47%
A2020 To procure & fabricate Instrument Panel 84.0d 84.0d -73.0d 22-Nov-17 08:00 AM30-Jun-18
A 05:00 PM 100% 60%
A2030 FAT 1.0d 0.0d 27-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 0% 100%
Installation 30.0d 30.0d -73.0d 01-Jul-18 08:00 AM 04-Aug-18 05:00 PM 0% 0%
A2040 Installation & signal cabling works 30.0d 30.0d -73.0d 01-Jul-18 08:00 AM 04-Aug-18 05:00 PM 0% 0%
Infrastructure Works 24.0d 24.0d -78.0d 16-Jul-18 08:00 AM 12-Aug-18 05:00 PM 0% 0%

Roadworks 24.0d 24.0d -78.0d 16-Jul-18 08:00 AM 12-Aug-18 05:00 PM 0% 0%


A2050 Site clearance, levelling & compaction 18.0d 18.0d -78.0d 16-Jul-18 08:00 AM 05-Aug-18 05:00 PM 0% 0%
A2060 Lay of crusher-run & premix 24.0d 24.0d -78.0d 16-Jul-18 08:00 AM 12-Aug-18 05:00 PM 0% 0%
Site Handover Work 17.0d 17.0d -95.0d 02-Sep-18 08:00 AM20-Sep-18 05:00 PM 0% 0%

Training, Testing, Commissioning & Maintenance 17.0d 17.0d -95.0d 02-Sep-18 08:00 AM20-Sep-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -95.0d 02-Sep-18 08:00 AM15-Sep-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -95.0d 02-Sep-18 08:00 AM08-Sep-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -95.0d 09-Sep-18 08:00 AM11-Sep-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -95.0d 12-Sep-18 08:00 AM19-Sep-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -95.0d 20-Sep-18 08:00 AM20-Sep-18 05:00 PM 0% 0%

Page 6 of 6 TASK filter: All Activities