Commissioning Check List E

Restricted
ANSI 87G/ 87M/ 87T/ 87L
CL-E125.1 Differential protection
(2-leg)
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Plant Code

System: Protection/ Synchronization and Metering (Generator)

Component: CHA10-U08-F01 – generator protection

Page: 1 of 2 Appendices:

No. Activity (Items not applicable to be marked N/A) Remarks Confirmed

1. Technical data: See device coversheet

Secondary injection checklist CL-E225.1 available 


Primary tests
2. - 3 phase short circuit outside differential zone.
- The Generator Circuit Breaker is blocked for ON command.
- The Generator is in service with manual excitation, set point 0A.
- Residual current check of measured values from CT to generator
protection
- Increase the current and do the CT and diff currents readings
according to Siprotec manual.
Side 1 Side 2
Rated Current IN[A]
Phase Current L1 Ipri[A]
Phase Current L2 Ipri[A]
Phase Current L3 Ipri[A]
L1
L2
L3
IL1pri/IN
IL2pri/IN
IL3pri/IN
DIFF Current L1 [IDiff/IN]
Restraint Current L1 [IRest/IN]
DIFF Current L2 [IDiff/IN]
Restraint Current L2 [IRest/IN]
DIFF Current L3 [IDiff/IN]
Restraint Current L3 [IRest/IN]
- Differential trip. Swap wires on CT secondary side. The diff
protection trip GCB and Turbine.
- Remove 3-phase short circuit.
Trip current ……………..A

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Power Plant: Panama Colon CL-E125.1 Differential Protection (2-leg)
Primary Injection Tests

Commissioning Checklist E System: Protection/ Synchronization and Metering (Generator)


Component: CHA10-U08-F01 – generator protection

Page: 2 of 2

No. Activity (all activities are part of electrical commissioning and start-up) Remarks Confirmed

3. Evaluation

- No measurement monitoring functions respond 


- Correct current phase angles 
- Diff protection stable 
(Diff Currents approx. 0 , Restraint Currents approx. 2xIpri/IN)
- Tests carried out with short circuit / on load (delete as appropriate)

4. Remarks:
.......................................................................................................................................................................................... 1

Department: ........................................................ Name: .......................................................................

Date:. ...................................................................... Signature: .............................................................

Siemens AG . Power Generation (PG) Construction and Commissioning


This document is subject to the handling restrictions set forth on the title page.

Вам также может понравиться