Вы находитесь на странице: 1из 2

Commissioning Check List E

Restricted
ANSI 32R
CL-E130S Reverse Power
Protection(ST)
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Project Code

System: Protection/ Synchronization and Metering (Generator)

Component: CHA10-U08-F01 – generator protection

Page: 1 of 2 Appendices:

No. Activity (Items not applicable to be marked N/A) Remarks Confirmed

1. Technical data: See device coversheet

Secondary injection checklist CL-E230 available 

2. Primary tests

Measurement and Setting of Reverse Power (in case of redundant


protection for both relays)

- Prepare provision to open the Generator Circuit Breaker manually (in case of
malfunctioning protection)

- Set Reverse Power Pickup P> at -0,5%

- Set Time Delay long at 45s

- Adjust Reactive Power output to approx. Q= 0 MVAr

- Close ST Control Valves (action by ST-Commissioning)

- Record minimum Reverse Power P0 measured by the protection relay.

P0 = [MW]

- Confirm Pickup of Reverse power Protection

- Increase active power of turbine (action by ST- Commissioning)

- Adjust reverse power setting according to calculation (by ST


commissioning) of 1CSD440963

.P>set = [MW]

P>set = [%]
-Adjust reverse power long time delay setting to original value

tlong = 10 [s]

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
CL-E130S Reverse Power Protection (ST)
Primary Injection Tests

Commissioning Checklist E System: Protection/ Synchronization and Metering (Generator)


Component: CHA10-U08-F01 – generator protection

Page: 2 of 2

No. Activity (all activities are part of electrical commissioning and start-up) Remarks Confirmed

Testing Reverse Power Protection

-Close ST Control Valves (action by ST-Commissioning) 

-Observe Reverse Power Trip Long time (opening of GCB) 

-Resynchronize turbine to grid

-Confirm correct tripping of both reverse power protections with closed stop
valve (short time delay initiated by turbine trip). 

3. Evaluation

- Attach active/reactive power records from I&C system

4. Remarks:
......................................................................................................................................................................................... 1

.......................................................................................................................................................................................... 2

......................................................................................................................................................................................... 3

Com. dep.: ........................................................ Name: .......................................................................

Date:. ...................................................................... Signature: .............................................................

Transmittal, reproduction, dissemination and/or editing of this document as well as utilization


of its content and communication thereof to others without express authorization are prohibited.
Project Site Execution Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.

Вам также может понравиться