PROJECT : VOZA OFFICE

SUBJECT : MEP DESIGN CONCEPT


DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

I DATA
A PARKIR & UTILITY
Area (Semi Gross) 13,729 m2
Total Populasi 458 Person 30 m2/Person
B OFFICE
Office Area (Semi Gross) 1,366 m2/Floor (Average)
Total Office Floor 24 Floor
Total Office Area (Semi Gross) 32,786 m2
Total Populasi 3,525 Person 9.3 m2/Person
Tenancy Zoning 7 - 20th Floor 9 Zone/ Floor
Tenancy Zoning 21 & 22th Floor 5 Zone/ Floor
Tenancy Zoning 23 - 29th Floor 3 Zone/ Floor
C BUILDING
Total Land Area 2,800 m2
Total Build Area (Gross) 56,576 m2
Total Basement 2 Floors
Total Parkir 6 Floors
Total Office 24 Floors
Total Building 32 Floors
Total Height 119.50 m (basement to Roof)

II AIR CONDITIONING & VENTILATION


A AIR CONDITIONING
1 SYSTEM
System VRV
Tenancy Zoning 7 - 20th Floor 10 Zone/Floor (9 tenant + 1 Corridor)
Tenancy Zoning 21 & 22th Floor 6 Zone/Floor (5 tenant + 1 Corridor)
Tenancy Zoning 23 - 29th Floor 4 Zone/Floor (3 tenant + 1 Corridor)
Outdoor Unit Location Every Floor
2 DESIGN TEMPERATURE
- Tenant 24 ± 1 ºC
- Koridor 24 ± 1 ºC
- Main Lobby 24 ± 1 ºC
3 COOLING CAPACITY
- Total Capacity 16,392,900 BTUH 500 Btuh/m2
- VRV Capacity 1,821 PK
1,366 TR
- Per Floor 76 PK 24 Floors
57 TR

MEP DESIGN CONCEPT Page 1 of 33


PROJECT : VOZA OFFICE
SUBJECT : MEP DESIGN CONCEPT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

B VENTILATION SYSTEM
1 DESIGN CRITERIA
- Carpark 6 times Airchange
- Smoke Extract 9 times Airchange
- Toilet 20 times Airchange
- STP 30 times Airchange
- Mechanical Room 20 times Airchange
- Electrical Room 40 times Airchange or Heat Rejection
- Fresh Air 10 CFM/person

III PLUMBING
1 COLD WATER
A SYSTEM
- 3th Top Floor Booster Pump w/ VSD All Pumps
- Rest Floor Gravity
B DESIGN PRESSURE
- Public Area 1.5 - 4.0 Bar
C WATER QUALITY
- Others PDAM 40% Usage
- WC Flush Recycle & Rain Water 60% Usage
C GWT CAPACITY
a Domestic Water
* Parkir & Management 23 M3 50 lt/person/day
* Office 176 M3 50 lt/person/day
TOTAL DOMESTIC WATER 199 M3/day
TOTAL GWT CAPACITY 199 M3 (for 1 day storage)
SPACE REQUIRED (at Basement)
- GWT 100 M2 (2m Water Height, 1m for access)
- Pump Room 50 M2 (3m Height)
b PDAM Water
TOTAL PDAM WATER (40%) 80 M3/day
c Flush Water
TOTAL FLUSH WATER (60%) 119 M3/day
D PUMPS & ROOF TANK
a PDAM Water
- Average Flow Rate 10 M3/hour, Avrg hour = 8 hour
- Transfer Pumps 500 Lpm, peak factor = 3
- Roof Tank 15 M3
SPACE REQUIRED 10 M2 (1.5m Water Height)
b Flush Water
- Average Flow Rate 15 M3/hour, Avrg hour = 8 hour
- Transfer Pumps 800 Lpm, peak factor = 3
- Roof Tank 24 M3
SPACE REQUIRED 16 M2 (1.5m Water Height)

MEP DESIGN CONCEPT Page 2 of 33


PROJECT : VOZA OFFICE
SUBJECT : MEP DESIGN CONCEPT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

2 STP
A SYSTEM
- STP Type Extended Aeration (EA)
- Recycling Sand & Carbon Filter & Ultra Filtration for Flushing
B STP CAPACITY
- Capacity 160 M3 (80% of Domestic Water)
SPACE REQUIRED 140 M2 (with 6M Height)

3 SOAK WELL (SUMUR RESAPAN)


A SYSTEM
- Coverage Roof & Street
- Type Well
B CAPACITY
- Roof Area 1,935 m2
- Volume 77 m3 (1m3/25m2)
- Quantity 20 Unit (size diameter 2x depth 3m)

4 RAIN HARVESTING
A SYSTEM
- Roof Area Coverage 1,935 m2
- Type Sand & Carbon Filtering
B CAPACITY
- Rain Intensity 50 mm/hour
- Flow rate 97 m3/hour
- Treatment Design Base On Flush 119 m3/day
Demand

MEP DESIGN CONCEPT Page 3 of 33


PROJECT : VOZA OFFICE
SUBJECT : MEP DESIGN CONCEPT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

III FIRE FIGHTING


A SYSTEM PROVIDED
- Fire Hydrant 800 m2/ IHB
- Fire Sprinkler Ordinary Hazzard 12 m2/sprinkler (Parking Area)
- Fire Sprinkler Light Hazzard 21 m2/sprinkler (All Area Exclude Parking)
- PFE 200 m2/ PFE
Minimum Pressure 6.9 Bar
Maximum Pressure 12 Bar
Zoning Low & High Zone
Standard Required NFPA 20 Standard
B PUMP SYSTEM
- Electric Pump 1000 gpm 20 Bar
- Diesel Pump 1000 gpm 20 Bar
- Jockey Pump 10 gpm 22 Bar
C SPACE REQUIRED
GWT Fire Water 227 M3 60 minute duration
TOTAL FIRE WATER CAPACITY 227 M3
SPACE REQUIRED (at Semi Basement)
- FIRE GWT 76 M2 (3.0m Water Height, 1m for access)
- Pump Room 50 M2 (3.5m Height)

IV LIFT
A DESIGN PARAMETER
- Waiting Time 25 - 35 Second
- 5% Handling Capacity 10 - 13 %
B LIFT DESIGN
See Lift Configuration (attached)

V ELECTRICAL
A SYSTEM
- PLN Medium Voltage (20 kV)
- User Low Voltage (220 V)
kWH Meter
- Type Electronic with analog counter, Billing System
- Location Centralized at Service Corridor
Riser Power Distribution Busduct
Tenant Power Distribution
- Air Conditioning 60 VA/m2
- Lighting 10 VA/m2
- Socket Outlet 40 VA/m2
Total Capacity 110 VA/m2
B POWER REQUIRED
* Parkir 137 kVA 10 VA/m2
* Office 3,606 kVA 110 VA/m2
TOTAL CAPACITY 3,744 kVA
PLN Connection Rating 4,330 kVA

MEP DESIGN CONCEPT Page 4 of 33


PROJECT : VOZA OFFICE
SUBJECT : MEP DESIGN CONCEPT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

C TRANSFORMER 4,680 kVA (80% effective capacity)


Transformer Selection
- Quantity 2 Set
- Capacity 2,500 kVA
D GENSET
Genset Backup 100%
Genset Load 3,744 kVA
Genset Capacity 4,680 kVA (80% effective capacity)
Genset Selection 1,500 kVA
Genset Quantity 3 Set
E FUEL TANK
Daily Tank 2,900 Liters (3 hours usage)
- Quantity 3 Set
- Capacity 1,000 Liter
Storage Tank 22,000 Liters (8 hours, 3 days usage)
- Quantity 2 Set
- Capacity 11,000 Liter
F LIGHTNING PROTECTION
- Type Electrostatic Non Radioactive + Faraday Cage
- Covered Area 100 m Radius
G SPACE REQUIREMENT
- MV Panel & Transformer 60 m2 (at SB, 3.5M Height)
- LV Panel 90 m2 (at SB, 3.5M Height)
- Genset 180 m2 (at B, 5.5M Height)
- Fuel Tank 30 m2 (at B, 3.5M Height)
- Panel Room 5 m2 (at every floor)
H SHAFT REQUIRED
- ELECTRICAL SHAFT 2000 x 300 mm (from SB to Roof)

MEP DESIGN CONCEPT Page 5 of 33


PROJECT : VOZA OFFICE
SUBJECT : MEP DESIGN CONCEPT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

VI ELECTRONIC
A FIRE ALARM SYSTEM
- System Semi Addressable
- Type Smoke Detector & Heat Detector
- Zone 10 Zone / Floor (9 Tenancy + 1 Public Corridor)
B TELECOMMUNICATION SYSTEM
1 Building Management
- Type PABX / Key Telephone
- Capacity 100 Extension
10 Line (10% of Extension)
2 Office Tenancy
- Type Direct Line
- Capacity 100 /m2 tenant area
Total Line 330 Line
3 Building Total Line 340 Line
C SOUND SYSTEM
- Function Evacuation Paging (Tenant)
Background Music (Public Area)
D CCTV
- Type IP Camera, Digital Storage
- Capacity 2 Month storage duration
- Area Coverage Main Lobby, Car Lift, Public Corridor,
Entrance/Exit Parking, Car Parking
E ACCESS CONTROL
- Type Proximity
- Accessibility Main Lobby & Car Lift
F MATV
- Type Paid TV, Indovision/Cablevision/First Media/Telkomvision
- Service Lobby Lift, Restaurant, Canteen, Floor, Every Floor at shaft
G DATA & INTERNET
- Wifi Public Area
- FO Cable Structure at Shaft for Tenant Request
- Cabling Cat 6 Management Office
H BUILDING AUTOMATION SYSTEM
- Service All Equipment, Public Lighting, Tenant KWH Meter,
Tenant CB
I SPACE REQUIREMENT
- Control Room 30 m2 (at Building Management Floor)
- FCC Room 12 m2 (at GF)
J SHAFT REQUIRED
- ELECTRONIC 1000 x 300 mm (from B3 to Roof inside Panel Room)

MEP DESIGN CONCEPT Page 6 of 33


PROJECT : VOZA OFFICE
SUBJECT : M/E SPACE REQUIREMENT
DATE : 25 JUNE 2014
ISSUED FOR : INFORMATION

EQUIPMENT DIMENSION SPACE REQUIRED


NO SYSTEM Q'TY UNIT LOCATION
L (M) W (M) H (M) Dia (M) L (M) W (M) H (M)

1 GROUND WATER TANK (GWT)


- Domestic Water 389 m3 8.00 10.00 5.00 - 8.00 10.00 6.00 Basement 2 & 1 (2 level)
- Fire Water 284 m3 8.00 15.00 2.50 - 8.00 15.00 3.50 Basement 1

2 ROOF TANK
- Domestic Water 30 m3 4.00 3.00 2.50 6.00 5.00 3.00 Roof (Open Space)

3 PUMP ROOM
Plumbing Pump Room 8.00 5.00 3.00 Basement 2
- Filter Pump 2 set 0.60 0.30 0.40 -
- Sand Filter 1 set - - 1.50 0.60
- Carbon Filter 1 set - - 1.50 0.60
- Water Softener 1 set
- Transfer Pump 2 set 0.75 0.40 0.50 -

Fire Pump Room 8.00 5.00 3.50 Basement 1


- Electric Fire Pump 1 set 2.00 1.20 1.20 - (Minimum by Code)
- Diesel Fire Pump 1 set 2.50 1.20 1.50 -
- Jockey Pump 1 set 0.30 0.30 0.60 -

4 STP & RECYCLING 320 m3/day 20.00 22.00 6.00 - 20.00 22.00 6.00 Basement 2 & below

5 OUTDOOR VRV
- VRV 173 unit 1.20 1.00 1.80 - 30.00 30.00 - Roof (open space)

6 INDOOR UNIT 5 PK 1.20 0.60 0.35 - 1.50 1.20 0.40 Below slab

394083504.xls ME REQUIREMENT Hal. 7 dari 33


PROJECT : VOZA OFFICE
SUBJECT : M/E SPACE REQUIREMENT
DATE : 25 JUNE 2014
ISSUED FOR : INFORMATION

EQUIPMENT DIMENSION SPACE REQUIRED


NO SYSTEM Q'TY UNIT LOCATION
L (M) W (M) H (M) Dia (M) L (M) W (M) H (M)

7 ELECTRICAL
a PLN Sub Station 6,930 kVA 5.00 4.00 3.50 - 7.00 6.00 4.00 Ground Floor Only
b Medium Voltage Panel 4 Cubical 1.00 1.10 2.10 - 6.00 3.00 3.50 Basement 1
c Transformer 3 x 2,000 kVA 2.50 1.50 2.50 - 4.50 10.50 3.50 Basement 1
d Low Voltage Main Panel 12 Cubical 1.00 1.20 2.10 - 14.00 3.00 3.50 Basement 1
e Genset 3 x 2,000 kVA 6.00 2.40 2.40 - 18.00 12.00 5.50 Basement 1 & 2 (2 Level)
f Genset Tenant (Future) 2 x 2,000 kVA 6.00 2.40 2.40 - 12.00 12.00 5.50 Basement 1 & 2 (2 Level)
g Fuel Storage 2 x 16,000 Ltr 10.00 - - 1.70 12.00 6.00 3.00 Basement 1

8 ELECTRONIC
Fire Command Center (FCC) 4.00 3.00 3.00 Ground Floor Only
a Fire Alarm 1 set 0.60 0.30 0.80 - Near Staircase & Fire Lift

Control Room 6.00 5.00 3.00 Basement 1


a PABX 1 set 0.80 0.40 0.80 -
b CCTV 1 set 0.60 0.30 0.80 -
c Data 1 set 0.60 0.30 1.20 -
d Sound System 1 set 0.60 0.40 1.20 -
e MATV 1 set 1.20 0.40 1.20 -
f BMS 1 set 1.20 0.40 1.20 -

9 LIFT (See lift configuration attached)

394083504.xls ME REQUIREMENT Hal. 8 dari 33


PROJECT : VOZA OFFICE
SUBJECT : MEP SHAFT
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

ACH
Room Size Tinggi (m) Shaft Size
(times) Lantai yg Air Flow Air Flow Air Flow Velocity
NO DESCRIPTION Area (m2) Location
Panjang dilayani (CMH) (CFM) (CMS) (m/s) Length Width
Lebar (m) m2/org CFM/ org
(m) (m) (m)

A VAC

1 Fresh Air Shaft (FAS) Typical 100.00 40.00 9.30 15.00 10.00 64,516 37,973 17.92 8.00 2.24 1.50 1.50

2 Exhaust Air Shaft (EAS) Typical Toilet 8.00 6.00 2.50 20.00 10.00 24,000 14,126 6.67 8.00 0.83 0.91 0.91

3 Smoke Extract Shaft (SES) Typical 100.00 40.00 2.90 9.00 1.00 104,400 61,448 29.00 8.00 3.63 1.90 1.90

4 Smoke Free Shaft (SFL) Typical 4.00 4.00 2.90 9.00 10.00 4,176 2,458 1.16 8.00 0.15 0.38 0.38

5 Intake Air Shaft (IAS) Basement 100.00 80.00 3.00 6.00 3.00 432,000 254,266 120.00 8.00 15.00 3.87 3.87

6 Smoke Extract Shaft (SES) Basement 100.00 80.00 3.00 9.00 3.00 648,000 381,398 180.00 8.00 22.50 4.74 4.74

7 Air Conditional Shaft (ACS) Typical All 2.60 13.00 0.20

B PLUMBING

1 Main Shaft 0.20 0.50 0.40

2 Waste Shaft Toilet 0.60 1.50 0.40

C FIRE FIGHTING

1 FCC Room 12.00 3.00 4.00

2 Main Shaft 0.48 1.20 0.40

3 Fire Stairs Shaft 0.40 1.00 0.40

D ELECTRICAL

1 Electrical Panel Room Typical 5.00 2.50 2.00

2 Main Electrical Shaft (ELS) 0.60 2.00 0.30

E ELECTRONIC

1 Electronic Shaft (ECS) 0.60 2.00 0.30


PROJECT : VOZA OFFICE
SUBJECT : ELEVATOR (LOW ZONE & HIGH ZONE)
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

H1 H2 H3 H4 S1 E1
H H H H H H LOW ZONE (GF, L7-L17) HIGH ZONE (GF, L18-L29)
29 ● ● ● ● ● ● Q'ty = 4 Unit Q'ty = 4 Unit
28 ● ● ● ● ● ● Cap = 24 Person Cap = 17 Person
27 ● ● ● ● ● ● Speed = 240 mpm Speed = 360 mpm
26 ● ● ● ● ● ● AWT = 36.06 Second AWT = 34.05 Second
25 ● ● ● ● ● ● HC = 10.20 % HC = 10.16 %
24 ● ● ● ● ● ●
23 ● ● ● ● ● ● PARKING LIFT (B-P6) EXECTV LIFT (GF,L7-L29)
22 ● ● ● ● ● ● Q'ty = 2 Unit Q'ty = 1 Unit
21 ● ● ● ● ● ● Cap = 15 Person Cap = 1500 Kg
20 ● ● ● ● ● ● Speed = 105 mpm Speed = 90 mpm
19 L1 L2 L3 L4 ● ● ● ● ● ● AWT = 47.20 Second AWT = 156.0 Second
18 H H H H ● ● ● ● ● ● HC = 21.25 % HC = 14.78 %
17 ● ● ● ● ● ●
16 ● ● ● ● ● ●
15 ● ● ● ● O O O O ● ●
14 ● ● ● ● ● ●
13 ● ● ● ● ● ●
12 ● ● ● ● O O O O ● ●
11 ● ● ● ● ● ●
10 ● ● ● ● ● ●
9 ● ● ● ● O O O O ● ●
8 ● ● ● ● ● ● P1 P2
7 ● ● ● ● ● ● H H
6 ● ● ● ● O O O O ● ● ●
5 ● ● ● ● ● ● ●
4 ● ● ● ● ● ● ●
3 ● ● ● ● O O O O ● ● ●
2 ● ● ● ● ● ● ●
1 ● ● ● ● ● ● ●
GF ● ● ● ● ● ● ● ● ● F ● F ● ●
SB ● ● ●
P P P P P P P P P
B ● ● ●
P P P

REMARKS :
● = SERVICE FLOOR F = FIREMAN'S SWITCH AWT = AVERAGE WAITING TIME
O = EMERGENCY DOOR (700x1400MM) BY ARCH M = MACHINE ROOM HC = HANDLING CAPACITY (5 MINUTES)
P = PIT LIFT H = OVERHEAD
CO = CENTER OPENING SO = SIDE OPENING

394083504.xls LIFT CONFIG 10 of 33


PROJECT : VOZA OFFICE
SUBJECT : ELEVATOR (LOW ZONE & HIGH ZONE)
DATE : 25 JUNE 2014
PREPARED BY : PT SKEMANUSA CONSULTAMA TEKNIK

LOW ZONE LIFT DATA & DIMENSION HIGH ZONE LIFT DATA & DIMENSION
PIT = 2100 MM PIT = 2100 MM
OVERHEAD = 4700 MM OVERHEAD = 4700 MM
LMR (H) = ROOMLESS LMR (H) = ROOMLESS
HOISTWAY = 2800 x 2500 MM HOISTWAY = 2800 x 2500 MM
CAR DIM. = 1800 x 1600 MM CAR DIM. = 1800 x 1600 MM
CAR HEIGHT = 2300 MM (STD) CAR HEIGHT = 2300 MM (STD)
DOOR SIZE = 1100 x 2100 MM DOOR SIZE = 1100 x 2100 MM
DOOR OPEN = CO DOOR OPEN = CO

PARKING LIFT DATA & DIMENSION SERVICE / FIRE LIFT DATA & DIM
PIT = 1500 MM PIT = 1500 MM
OVERHEAD = 4300 MM OVERHEAD = 4300 MM
LMR (H) = ROOMLESS LMR (H) = ROOMLESS
HOISTWAY = 2200 x 2000 MM HOISTWAY = 3100 x 3100 MM
CAR DIM. = 1600 x 1400 MM CAR DIM. = 2100 x 2500 MM
CAR HEIGHT = 2300 MM (STD) CAR HEIGHT = 2300 MM (STD)
DOOR SIZE = 900 x 2100 MM DOOR SIZE = 1400 x 2100 MM
DOOR OPEN = CO DOOR OPEN = SO

394083504.xls LIFT CONFIG 11 of 33


PROYEK : DEVASA OFFICE
SUBJEK : TRAFFIC ANALYSIS LIFT
TANGGAL : 28 JANUARI 2014
KONSULTAN ME : PT SKEMANUSA CONSULTAMA TEKNIK

TRAVEL LIFT STOP LUAS LUAS LUAS OCCU- JUMLAH LIFT ZONE
ELEVASI ELEVASI
NO BANGUNAN LOW HIGH LOW HIGH GROSS PARKIR SALEABLE PANCY POPU- % OCC LOW HIGH
(M) (M) PARKIR EXEC PARKIR EXEC PARKIR EXEC
ZONE ZONE ZONE ZONE (M2) (M2) (M2) (M2/OR) LASI ZONE ZONE

1 29 4.000 113.50 113.50 113.50 1 1 1,180 901 9.3 97 80% 77 3


2 28 4.000 109.50 109.50 109.50 1 1 1,180 901 9.3 97 80% 77 3
3 27 4.000 105.50 105.50 105.50 1 1 1,180 901 9.3 97 80% 77 3
4 26 4.000 101.50 101.50 101.50 1 1 1,180 901 9.3 97 80% 77 3
5 25 4.000 97.50 97.50 97.50 1 1 1,180 901 9.3 97 80% 77 3
6 24 4.000 93.50 93.50 93.50 1 1 1,180 901 9.3 97 80% 77 3
7 23 4.000 89.50 89.50 89.50 1 1 1,180 901 9.3 97 80% 77 3
8 22 4.000 85.50 85.50 85.50 1 1 1,595 1,279 9.3 138 80% 110 5
9 21 4.000 81.50 81.50 81.50 1 1 1,595 1,279 9.3 138 80% 110 5
10 20 4.000 77.50 77.50 77.50 1 1 1,935 1,620 9.3 174 80% 139 9
11 19 4.000 73.50 73.50 73.50 1 1 1,927 1,611 9.3 173 80% 139 9
12 18 4.000 69.50 69.50 69.50 1 1 1,920 1,604 9.3 172 80% 138 9
13 17 4.000 65.50 65.50 65.50 1 1 1,914 1,599 9.3 172 80% 138 - 9
14 16 4.000 61.50 61.50 61.50 1 1 1,914 1,599 9.3 172 80% 138 - 9
15 15 4.000 57.50 57.50 57.50 1 1 1,914 1,599 9.3 172 80% 138 - 8
16 14 4.000 53.50 53.50 53.50 1 1 1,920 1,604 9.3 172 80% 138 - 9
17 13 4.000 49.50 49.50 49.50 1 1 1,927 1,611 9.3 173 80% 139 - 9
18 12 4.000 45.50 45.50 45.50 1 1 1,935 1,620 9.3 174 80% 139 - 9
19 11 4.000 41.50 41.50 41.50 1 1 1,943 1,627 9.3 175 80% 140 - 9
20 10 4.000 37.50 37.50 37.50 1 1 1,948 1,632 9.3 176 80% 140 - 9
21 9 4.000 33.50 33.50 33.50 1 1 1,950 1,635 9.3 176 80% 141 - 9
22 8 4.000 29.50 29.50 29.50 1 1 1,950 1,635 9.3 176 80% 141 - 9
23 7 4.000 25.50 25.50 25.50 1 1 1,942 1,627 9.3 175 80% 140 - 9
24 6 3.500 22.00 22.00 1 1,974 1,630 30.0 54 80% 43 - - -
25 5 3.000 19.00 19.00 1 1,997 1,653 30.0 55 80% 44 - - -
26 4 3.000 16.00 16.00 1 1,991 1,646 30.0 55 80% 44 - - -
27 3 3.000 13.00 13.00 1 1,991 1,646 30.0 55 80% 44 - - -
28 2 3.000 10.00 10.00 1 1,991 1,646 30.0 55 80% 44 - - -
29 1 3.500 6.50 6.50 6.50 1 1 1,789 742 651 30.0/9.3 95 50% 12 35 - -
30 LANTAI DASAR 6.500 0.00 0.00 0.00 0.00 0.00 1 1 1 1 778 651 9.3 70 0% - - - -
31 SEMI BASEMENT 3.000 -3.00 -3.00 1 2,821 2,431 30.0 81 80% 65 - - -
32 BASEMENT 3.000 -6.00 -6.00 1 2,760 2,335 30.0 78 80% 62 - - -

TOTAL 119.50 28.00 65.50 113.50 113.50 9 13 13 24 56,576 13,729 32,786 3,983 359 1,565 1,178 156
TOTAL PERZONE 28.00 40.00 44.00 113.50

12 of 33
PROYEK : DEVASA OFFICE
SUBJEK : TRAFFIC ANALYSIS LIFT
TANGGAL : 28 JANUARI 2014
KONSULTAN ME : PT SKEMANUSA CONSULTAMA TEKNIK

A LIFT PARKIR B LIFT LOW ZONE C LIFT HIGH ZONE D LIFT EXECUTIVE
POPULASI 359 POPULASI 1,565 POPULASI 1,178 POPULASI 156
JUMLAH LANTAI 9 JUMLAH LANTAI 13 JUMLAH LANTAI 13 JUMLAH LANTAI 24
JUMLAH OPENING 9 JUMLAH OPENING 13 JUMLAH OPENING 13 JUMLAH OPENING 24
TRAVEL TOTAL 28.00 TRAVEL TOTAL 65.50 TRAVEL TOTAL 113.50 TRAVEL TOTAL 113.50
TRAVEL INTERFLOOR 28.00 TRAVEL INTERFLOOR 40.00 TRAVEL INTERFLOOR 44.00 TRAVEL INTERFLOOR 113.50
JUMLAH LIFT 2 JUMLAH LIFT 4 JUMLAH LIFT 4 JUMLAH LIFT 1
KAPASITAS LIFT 15 KAPASITAS LIFT 24 KAPASITAS LIFT 17 KAPASITAS LIFT 15
KECEPATAN LIFT 105 KECEPATAN LIFT 240 KECEPATAN LIFT 360 KECEPATAN LIFT 300
DOOR WIDTH 900 DOOR WIDTH 1100 DOOR WIDTH 1000 DOOR WIDTH 900
WAITING TIME 47.20 WAITING TIME 36.06 WAITING TIME 34.05 WAITING TIME 156.03
5 MIN HANDLING CAP 21.25 5 MIN HANDLING CAP 10.20 5 MIN HANDLING CAP 10.16 5 MIN HANDLING CAP 14.78

13 of 33
PREPARED CHECKED APPROVED
LG Industrial Systems Co., Ltd. LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING Project:
MAIN SPECIFICATION Model:
Ⅰ ONE-WAY EXPRESS Ⅱ ONE-WAY SECTION ◆ 5 Minute Handling
◆ Handling Capacity
EXPRESS
No. of elevators: 2 Bldg:
Rated speed (mpm): 105 Recommended 5 Minute Handling Capacity 12%
Rated Load (person): 15 5 Minute Handling Capacity 21.26%
SLu
SL SE OR No. of stops: 9
SEd
SL (Travel ; m): 28
SEu Running open: Yes
30%
Entrance type: Center OP
Opening (W ; mm): 900 25%

PROJECT: VOZA OFFICE Bldg: OFFICE PARKIR Population (person): 359 5 Minute 20%
MODEL: PENUMPANG Lift No. LP-P-01 & LP-P-02 Floor area (m^2): NA Handling
15% 12.00%
Capacity
( Run : 08-Aug-18 13:17 ) symbol ( unit ) formula result 10%
Recommended 5 Minute
Handling Capacity
No. of elevator(s) n 2 Data for calculation:
5%
Elevator speed V (m/sec) Rated speed / 60 1.75 5 Minute Handling Capacity

No. of passengers r (person) 0.8 x Rated Load 12 0%


No. of expected stops in local service -5%
fL N(1-((N-1)/N)^r) 5.899 N: 7
section

No. of stop(s) in express service section fE 1 0

No. of expected stops in the entire


F fL + fE 5.899
section
Average running distance in local ◆ Average
Average Waiting
Waiting Interval
Interval
S (m) SL / fL 4.746
service section
Local Interval Length SL(m) 28 Recommended Average Waiting Interval 35 (sec)
Express Interval Length SE(m) 0 Average Waiting Interval ###
Average local length ALM(m) 4.75
Average Express length AXL(m) 0.00
Average Local Interval Time ALIT(sec) 5.16 80 (sec)
Total Local Interval Time TLIT(sec) 30.45
Average 70 (sec)
Total Express Interval Time TEIT(sec) 1.40 Waiting
Going down Time GDT(sec) 18.45 Interval 60 (sec)
Total Trip Time TR(sec) 50.30 (sec)
50 (sec)
Door-opening & closing time Td (sec) td x F 16.517 td: 2.8 47 (sec)
40 (sec)
Passenger entrance & exit time Tp (sec) r x tp 27.6 tp: 2.3
30 (sec) Recommended Average
Time loss Tl (sec) tl x (Td + Tp) 4.411 tl: 0.1 Waiting Interval
One round trip time RTT (sec) Tr + Tp + Td + Tl 94.42 20 (sec)
Average waiting interval Tav (sec) RTT / n 47.2 10 (sec)
Average Waiting Interval

5-minute capacity of each elevator's P' (person) 5 x 60 x r / RTT 38.127 Legend:


0 (sec)
no. of floors in local
5-minute capacity of all elevators' P (person) P' x n 76.25 N:
section

accelerated
Floor area Fa (M^2) NA Sa:
(decelerated) dist.

Rental ratio Rr NA tr: running time


◆Evaluation of
◆Evaluation of Traffic Analysis Evaluation
Evaluation
accelerated
Effective floor area of each floor Ef (M^2) NA ta:
(decelerated) time

door -opening &


Area occupied by one person Ao (M^2) NA td: closing time per one
stop

LIFT PARKIR 14 of 33
average entrance &
Floor population Fp (person) NA tp: exit time per
passenger

Total building population Q (person) 358.689 tl: time loss

5-minute handling capacity CC (%) P / Q x 100 21.26

LIFT PARKIR 15 of 33
VOZA OFFICE
PENUMPANG
OFFICE PARKIR

Recommended 5 Minute
Handling Capacity

5 Minute Handling Capacity

Recommended Average
Waiting Interval

Average Waiting Interval

LIFT PARKIR 16 of 33
LIFT PARKIR 17 of 33
PREPARED CHECKED
LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING
MAIN SPECIFICATION
Ⅰ ONE-WAY EXPRESS Ⅱ ONE-WAY SECTION
No. of elevators:
EXPRESS
Rated speed (mpm):
Rated Load (person):
OR SLu
SL SE No. of stops:
SEd
SL (Travel ; m):
SEu Running open:
Entrance type:
Opening (W ; mm):
PROJECT: VOZA OFFICE Bldg: OFFICE LOW ZONE Population (person):

MODEL: PENUMPANG Lift No. LF-LZ-01 s/d 04 Floor area (m^2):


( Run : 08-Aug-18 13:17 ) symbol ( unit ) formula result
No. of elevator(s) n 4 Data for calculation
Elevator speed V (m/sec) Rated speed / 60 4
No. of passengers r (person) 0.8 x Rated Load 19.2
No. of expected stops in local service
fL N(1-((N-1)/N)^r) 9.235 N:
section
No. of stop(s) in express service
fE 1 0
section
No. of expected stops in the entire
F fL + fE 9.235
section
Average running distance in local
S (m) SL / fL 4.331
service section
Local Interval Length SL(m) 40
Express Interval Length SE(m) 25.5
Average local length ALM(m) 4.69
Average Express length AXL(m) 26.86
Average Local Interval Time ALIT(sec) 5.09
Total Local Interval Time TLIT(sec) 41.90
Total Express Interval Time TEIT(sec) 11.41
Going down Time GDT(sec) 21.075
Total Trip Time TR(sec) 74.39
Door-opening & closing time Td (sec) td x F 29.552 td:
Passenger entrance & exit time Tp (sec) r x tp 40.32 tp:
Time loss Tl (sec) tl x (Td + Tp) 6.987 tl:
One round trip time RTT (sec) Tr + Tp + Td + Tl 144.27
Average waiting interval Tav (sec) RTT / n 36.06
5-minute capacity of each elevator's P' (person) 5 x 60 x r / RTT 39.926
Legend:

5-minute capacity of all elevators' P (person) P' x n 159.7 N:

Floor area Fa (M^2) NA Sa:

Rental ratio Rr NA tr:

Effective floor area of each floor Ef (M^2) NA ta:

Area occupied by one person Ao (M^2) NA td:

Floor population Fp (person) NA tp:

LIFT LOW ZONE 18 of 33


Total building population Q (person) 1564.969 tl:

5-minute handling capacity CC (%) P / Q x 100 10.20

LIFT LOW ZONE 19 of 33


APPROVED

4
240
24
13
40
Yes
Center OP
1100
1565
NA

Data for calculation:

11

3.2
2.1
0.1

Legend:
no. of floors in local
section

accelerated
(decelerated) dist.

running time

accelerated
(decelerated) time

door -opening & closing


time per one stop

average entrance & exit


time per passenger

LIFT LOW ZONE 20 of 33


time loss

LIFT LOW ZONE 21 of 33


LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING Project:
Model:
◆ 5 Minute Handling Capacity
Bldg:
Recommended 5 Minute Handling Capacity 11%
5 Minute Handling Capacity 10.20%

30%
25%

5
5 Minute
Minute 20%
Recommended 5
Handling
Handling 15% Minute Handling
Capacity
Capacity 11% Capacity
10% 10% 5 Minute Handling
Capacity
5%
0%
-5%

◆ Average Waiting Interval

Recommended Average Waiting Interval 35 (sec)


Average Waiting Interval 36.06 (sec)

80 (sec)

70 (sec)

Average
Average 60 (sec)
Waiting
Interval
Interval 50 (sec)
(sec)
(sec)
40 (sec)
36 (sec) Recommended Average
30 (sec) Waiting Interval

20 (sec) Average Waiting Interval

10 (sec)

0 (sec)

◆Evaluation of Traffic Analysis Evaluation

LIFT LOW ZONE 22 of 33


LIFT LOW ZONE 23 of 33
VOZA OFFICE
PENUMPANG
OFFICE LOW ZONE

Recommended 5
Minute Handling
Capacity
5 Minute Handling
Capacity

Recommended Average
Waiting Interval

Average Waiting Interval

LIFT LOW ZONE 24 of 33


LIFT LOW ZONE 25 of 33
PREPARED CHECKED
LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING
MAIN SPECIFICATION
Ⅰ ONE-WAY EXPRESS Ⅱ ONE-WAY SECTION
No. of elevators:
EXPRESS
Rated speed (mpm):
Rated Load (person):
OR SLu
SL SE No. of stops:
SEd
SL (Travel ; m):
SEu Running open:
Entrance type:
Opening (W ; mm):
PROJECT: VOZA OFFICE Bldg: OFFICE HIGH ZONE Population (person):
MODEL: PENUMPANG Lift No. LF-HZ-01 s/d 04 Floor area (m^2):
( Run : 08-Aug-18 13:17 ) symbol ( unit ) formula result
No. of elevator(s) n 4 Data for calculation:
Elevator speed V (m/sec) Rated speed / 60 6
No. of passengers r (person) 0.8 x Rated Load 13.6
No. of expected stops in local
fL N(1-((N-1)/N)^r) 7.99 N:
service section
No. of stop(s) in express service
fE 1 0
section
No. of expected stops in the entire
F fL + fE 7.99
section
Average running distance in local
S (m) SL / fL 5.506
service section
Local Interval Length SL(m) 44
Express Interval Length SE(m) 69.5
Average local length ALM(m) 5.97
Average Express length AXL(m) 71.80
Average Local Interval Time ALIT(sec) 5.63
Total Local Interval Time TLIT(sec) 39.39
Total Express Interval Time TEIT(sec) 18.67
Going down Time GDT(sec) 25.6166666667
Total Trip Time TR(sec) 83.67
Door-opening & closing time Td (sec) td x F 23.97 td:
Passenger entrance & exit time Tp (sec) r x tp 28.56 tp:
Time loss Tl (sec) tl x (Td + Tp) 5.253 tl:
One round trip time RTT (sec) Tr + Tp + Td + Tl 136.20
Average waiting interval Tav (sec) RTT / n 34.05
5-minute capacity of each
P' (person) 5 x 60 x r / RTT 29.955 Legend:
elevator's
5-minute capacity of all
P (person) P' x n 119.82 N:
elevators'

Floor area Fa (M^2) NA Sa:

Rental ratio Rr NA tr:

Effective floor area of each floor Ef (M^2) NA ta:

Area occupied by one person Ao (M^2) NA td:

Floor population Fp (person) NA tp:

Total building population Q (person) 1178.313 tl:

5-minute handling capacity CC (%) P / Q x 100 10.17


APPROVED

4
360
17
13
44
Yes
Center OP
1000
1178
NA

Data for calculation:

11

3
2.1
0.1

Legend:
no. of floors in local
section

accelerated
(decelerated) dist.

running time

accelerated
(decelerated) time

door -opening & closing


time per one stop

average entrance & exit


time per passenger

time loss
LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING Project:
Model:
◆ 5 Minute Handling Capacity
Bldg:
Recommended 5 Minute Handling Capacity 11%
5 Minute Handling Capacity 10.17%

30%
25%

5 Minute 20%
Minute Recommended 5
Handling
Handling 15% Minute Handling
Capacity
Capacity 11% Capacity
10% 5 Minute Handling
10% Capacity
5%
0%
-5%

◆ Average Waiting Interval

Recommended Average Waiting Interval 35 (sec)


Average Waiting Interval 34.05 (sec)

80 (sec)

Average
Average 70 (sec)
Waiting
Waiting
Interval
Interval 60 (sec)
(sec)
(sec) 50 (sec)

40 (sec) 35 (sec)
Recommended Average
30 (sec) 34 (sec) Waiting Interval

20 (sec)
Average Waiting Interval
10 (sec)

0 (sec)

◆Evaluation of Traffic Analysis Evaluation


VOZA OFFICE
PENUMPANG
OFFICE HIGH ZONE

Recommended 5
Minute Handling
Capacity
5 Minute Handling
Capacity

ecommended Average
aiting Interval

verage Waiting Interval


PREPARED CHECKED
LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING
MAIN SPECIFICATION
Ⅰ ONE-WAY EXPRESS Ⅱ ONE-WAY SECTION
No. of elevators:
EXPRESS
Rated speed (mpm):
Rated Load (person):
OR SLu
SL SE No. of stops:
SEd
SL (Travel ; m):
SEu Running open:
Entrance type:
Opening (W ; mm):
PROJECT: VOZA OFFICE Bldg: OFFICE EXEC Population (person):
MODEL: PENUMPANG Lift No. LF-EXEC Floor area (m^2):
( Run : 08-Aug-18 13:17 ) symbol ( unit ) formula result
No. of elevator(s) n 1 Data for calculation:
Elevator speed V (m/sec) Rated speed / 60 5
No. of passengers r (person) 0.8 x Rated Load 12
No. of expected stops in local
fL N(1-((N-1)/N)^r) 9.411 N:
service section
No. of stop(s) in express service
fE 1 0
section
No. of expected stops in the entire
F fL + fE 9.411
section
Average running distance in local
S (m) SL / fL 12.06
service section
Local Interval Length SL(m) 113.5
Express Interval Length SE(m) 0
Average local length ALM(m) 12.06
Average Express length AXL(m) 0.00
Average Local Interval Time ALIT(sec) 7.68
Total Local Interval Time TLIT(sec) 72.28
Total Express Interval Time TEIT(sec) 1.40
Going down Time GDT(sec) 28.4
Total Trip Time TR(sec) 102.08
Door-opening & closing time Td (sec) td x F 26.35 td:
Passenger entrance & exit time Tp (sec) r x tp 27.6 tp:
Time loss Tl (sec) tl x (Td + Tp) 5.395 tl:
One round trip time RTT (sec) Tr + Tp + Td + Tl 156.03
Average waiting interval Tav (sec) RTT / n 156.03
5-minute capacity of each
P' (person) 5 x 60 x r / RTT 23.071 Legend:
elevator's
5-minute capacity of all
P (person) P' x n 23.07 N:
elevators'

Floor area Fa (M^2) NA Sa:

Rental ratio Rr NA tr:

Effective floor area of each floor Ef (M^2) NA ta:

Area occupied by one person Ao (M^2) NA td:

Floor population Fp (person) NA tp:

Total building population Q (person) 156 tl:

5-minute handling capacity CC (%) P / Q x 100 14.79


APPROVED

1
300
15
24
113.5
Yes
Center OP
900
156
NA

Data for calculation:

22

2.8
2.3
0.1

Legend:
no. of floors in local
section

accelerated
(decelerated) dist.

running time

accelerated
(decelerated) time

door -opening & closing


time per one stop

average entrance & exit


time per passenger

time loss
LG Industrial Systems Co., Ltd.
LIFT TRAFFIC ANALYSIS FOR OFFICE BUILDING Project:
Model:
◆ 5 Minute Handling Capacity
Bldg:
Recommended 5 Minute Handling Capacity 11%
5 Minute Handling Capacity 14.79%

30%
25%

5 Minute 20%
Minute Recommended 5
Handling
Handling 15% Minute Handling
Capacity 11% 15%
Capacity Capacity
10% 5 Minute Handling
Capacity
5%
0%
-5%

◆ Average Waiting Interval

Recommended Average Waiting Interval 35 (sec)


Average Waiting Interval ###

156 (sec)
80 (sec)

Average
Average 70 (sec)
Waiting
Waiting
Interval
Interval 60 (sec)
(sec)
(sec) 50 (sec)

40 (sec) 35 (sec)
Recommended Average
30 (sec) Waiting Interval
20 (sec)
Average Waiting Interval
10 (sec)

0 (sec)

◆Evaluation of Traffic Analysis Evaluation


VOZA OFFICE
PENUMPANG
OFFICE EXEC

Recommended 5
Minute Handling
Capacity
5 Minute Handling
Capacity

Recommended Average
Waiting Interval

Average Waiting Interval