Вы находитесь на странице: 1из 1

S UI N ORTHERN G AS QA D EPARTMENT

P IPELINES L IMITED
D AILY P ROGRESS R EPORT – QA P ROJECTS QA-FM-01 / 02 / 02-01-06

F ROM : E XEC .E NGINEER T O: G ENERAL M ANAGER


(QUALITY ASSURANCE) (QUALITY ASSURANCE)
R EF : QA / PHN / 16/06/02 D ATE : 03-06-2016
P ROJECT / L INE : LNG II L OOP LINE , PHOOL NAGAR TO MP 59.9
MP F ROM : TO:
C HAINAGE F ROM (CH): TO:
R EPORT FOR 02-06-
T OTAL L ENGTH : 63.5 KMS D ATE : 2016
SR.
A CTIVITY T ODAY T O D ATE % AGE
# C OMPLETED
1. ROW C LEANING ( FT.) 0 193389 93%
2. P IPE S TRINGING ( NOS. + FT.) (100)(4001.6) (4451)(178822.32) 86%
3. M AIN L INE (117)(4906.88) (4026)(161546.56) 78%
J OINTS & P IPE W ELDED (JOINT NOS. +
I.
FT.)
II . R ADIOGRAPHED (NOS.)
III . R EPAIRS (NOS.)
IV . R EPAIRS R ECTIFIED (NOS.)
4. T IE I NS
I. J OINTS (NOS.)
II . R ADIOGRAPHED (NOS.)
III . R EPAIRS (NOS.)
IV . R EPAIRS R ECTIFIED (NOS.)
5. F ABRICATION
I. J OINTS (NOS.)
II . R ADIOGRAPHED (NOS.)
III . R EPAIRS (NOS.)
IV . R EPAIRS R ECTIFIED (NOS.)
6. A IR T ESTING (FT.)
7. S LEEVING – J OINTS S LEEVED (NOS.) 93 2908
8. T RENCHING (FT.) 5097 110034 53%
9. L OWERING – IN (FT.) 4297 102825 49%
10. B ACKFILLING (FT.) 4395 79514 38%
11. Y O Y O T EST
12. H YDROSTATIC T ESTING
13. T RENCHING W T . P RECASTED (NOS.)
14. RCC S LABS P RECASTED (NOS.)
R EMARKS : ROW IS IN PROGRESS

C OMPUTER , S CANNER , P RINTER REQUIRED

_______
__________________________
E XEC .
E NGINEER (QA) MOR KHUNDA CAMP

Quality is never an accident; it is always a result of high intentions, intellectual directions& intelligent decisions