Вы находитесь на странице: 1из 1

Highlights of RPMC Project Facilitation Meeting / Problem Solving Session

April 27, 2018

Project / Location Cost Discussion and Agreements


nd
Cebu: 2 District

ROW – Widening of Natalio Bacalso Avenue P 1.5 Million - ROW Negotiation Ongoing
Start: June 15, 2015 - Delayed; it tool Cebu Capitol assessor’s office to issue
Completion: December 29, 2016 permit after one year
Status (Feb. 2018): 80.18% Accomplishment - At present, construction works on-going