Construction of RCC Pavement between Shed No-6 & 7

Unit Price Total Price


Measurement Quantity In figures In Figures (BDT)
Item No Description of Item Unit (BDT)

Dismantling of reinforced cement


concrete work such as roof, floor,
1 beam, column, lintel, sunshade etc. Cum 675
including removing the debris to a safe
distance.

Dismantling brick masonry in ground


floor in cement mortar of any
proportion including removing debris
2 Cum 33
to a safe distance and scaffolding etc.
complete (Debris and the released
bricks to be carried by head lead).

Dismantling cement concrete of all


proportion including removing the
3 Cum 12
debris to a safe distance and
scaffolding as per direction.

Labour for taking out brick on edge


4 pavement in herring bone bond (HBB) Sqm 2773
soling etc. complete.

Labour for taking out brick flat soling


5 Sqm 2825
and stacking as per direction.

Picking up old road surface including


6 Cum 5
collecting and stacking the same at site.

Labour for taking out MS channel,


bracing of sizes from jetty under
7 Kg 5040
structure including cutting bolts and
nuts etc. as required and directed.

Labour for cutting RS joists by hacksaw


8 Nos 28
or gas cutter as per direction (Big size).

Earth work in excavation of foundation


trenches for ordinary soil mixed with
set cement, scrap iron, broken glass
9 Cum 4060
etc. up to required depth including
cutting & removing debris to a safe
distance as per direction.
Sand filling in yard with fine dry sand
crated from outside including
spreading, watering, leveling and
10 Cum 1850
compacting with vibro-compactor in
229mm layers etc. as per direction (For
compacted measurement).

Labour for breaking 63mm-38mm sizes


11 CC or RCC including stacking at site.

a (63mm~38mm) size. Cum 701


Labour for breaking 38mm-25mm sizes
b brick, bricks bats, jhama bats including Cum 591
stacking at site.

Labour for providing compacted sub-


base with 2.83cum broken concrete
chips (38mm~63mm) mixed with
0.62cum sand including local handling
i.e, mixing sand and concrete chips,
spreading uniformly on road/ yard
12 surface to proper grade, comber/ Cum 701
slope, watering and rolling with
(8~10)Ton roller for proper compaction
as per direction of Engineer excluding
cost of concrete chips but including
cost of sand etc. complete (For
compacted volume).

Providing compacted sub base with


(25mm~38mm) size jhama brick chips
and sand (FM= 0.80) in proportion of
(2:1) as per specification including local
handling i.e mixing sand and jhama
chips in a stack yard or road/ yard side
land and spreading uniformly on road/
13 Cum 590
yard bed to proper grade,
camber/slope, rolling properly with
(8~10)Ton road roller for compaction as
per direction of the Engineer excluding
cost of jhama brick chips but including
sand etc. complete (Measurement will
be given for compacted volume).
Providing compacted sub base with
(25mm~38mm) size jhama brick chips
and sand (FM= 0.80) in proportion of
(2:1) as per specification including local
handling i.e mixing sand and jhama
chips in a stack yard or road/ yard side
land and spreading uniformly on road/
14 yard bed to proper grade, Cum 150
camber/slope, rolling properly with
(8~10)Ton road roller for proper
compaction as per direction of the
Engineer including cost of jhama brick
chips and sand etc. all complete
(Measurement will be given for
compacted volume).

Providing compacted sub base with


(25mm~38mm) size Sylhet stone chips
and sand (FM- 0.80) in proportion of
(2:1) including local handling i.e. mixing
of sand and stone chips in a stack yard
or road/ yard bed to proper grade,
15 camber/slope, rolling properly with Cum 440
(8~10)Ton road roller for proper
compaction as per direction of the
Engineer including cost of stone chips
and sand etc. all complete
(Measurement will be given for
compacted volume).

Single layer brick soling (76mm thick)


with 1st class well burnt brick including
preparation of bed as necessary, filling
and packing brick joints properly with
16 Sqm 8840
local sand with necessary cushion of
sand below, supplying and laying of all
materials etc. complete. as per
direction.

Supplying and laying 0.20mm thick


polythin paper (with 150mm lapping)
17 below RCC and CC work etc. including Sqm 3025
cutting to proper sizes etc. as per
direction.
RCC work in pavement 305mm thick
(excluding MS reinforcement) in
proportion of (1:1½:3) with cement
(OPC), sand (50% Sylhet sand + 50%
local coarse sand) and 19mm down
18 Sqm 2900
Sylhet crushed stone chips including
shuttering, mixing, pouring, using
vibrator, surface finishing, 28 days
curing etc. complete as per design,
drawing and direction of Engineer.

Reinforced cement concrete (RCC)


work (excluding MS reinforcement) in
proportion of (1:1½:3) with cement
(OPC), sand (50% local + 50% Sylhet)
(FM= 1.8) and Sylhet crushed stone
chips (19mm down) in pavement,
19 Cum 150
check wall, drain, column, beam, roof
slab, stairs, lintel, sunshade, bracing
etc. including centering, shuttering,
scaffolding and curing for 28 days
complete as per direction in ground
floor or height up to 4.88m.

Supplying and fitting fixing MS


deformed bar reinforcement of
required sizes (minimum yield strength,
fy= 60,000 psi) including fabrication,
20 Kg 152000
bending, binding with wire, erection,
hooking etc. complete as per design
and direction (No measurement for
over lapping/ lapping).

Supplying and fitting fixing of 25mm


dia MS cap having length up to 260mm
for dowel bars (excluding cost of dowel
21 bar) including filling the gap with Nos 360
bitumen/ grease etc. painting half
portion of dowel bar etc. for expansion
joint as per direction and design.

Extra rate of painting over dowel bars


or MS plain bars fitted and fixed as
concrete pavement connector with two
coats anti-corrosive epoxy paint after
22 Nos 3120
necessary preparation of surface, then
lubricated with oil/ grease and finally
placed firmly in proper position
complete.
Supply and fitting fixing 25mm thick
cork sheet for provision of RCC
23 expansion joints including cost of all Sqm 110
materials and labour etc. as per
direction.

Filling up expansion joints of concrete


24 pavement or bridge with bitumen and Rm 350
sand as per direction.

Filling up construction joints of


concrete pavement with sand and
25 bitumen mixture as per direction Rm 700
including necessary cleaning of the
joints etc. complete.

Cement concrete in foundation, floor


etc. in proportion of (1:2:4) with
cement, local coarse sand and 19mm
26 down jhama khoa including ramming, Cum 25
shuttering, curing etc. complete as per
direction (3days curing for foundation
and 21 days for floor).

Earth filling in plinth or side of trenches


with earth/ sandy soil available at site
with necessary head lead including
27 Cum 5
leveling, dressing, watering, ramming
etc. in 150mm layers complete as per
direction.

1st class brick work with cement


mortar in proportion of (1:4) with
28 cement and sand in foundation and Cum 15
plinth including curing etc. complete as
per direction.

13mm thick cement and sand plaster


(1:3) in floor including neat cement
29 Sqm 100
finishing, curing etc. complete as per
direction.

Taking out old plaster from wall surface


30 including racking out joints, removing Sqm 80
debris etc. complete as per direction.

Supplying and fitting fixing of 102mm


dia GI pipe including necessary small
fittings i.e, GI plain nipple, GI hex
nipple, GI jum nuts, GI plugs, GI sockets
31 and laying the pipes on the top of the Rm 200
khoa consolidation layer, thread
cutting, jute or lead wool packing
complete as per direction (Excluding
big fitting).
Labour for taking out RCC slab of
standard sizes from existing drain and
32 replacing the same after cleaning and Cum 5
repairing the drain as per direction
(Excluding repairing cost).

Taking out rubbishes mixed with silt,


khoa, brick bats, stone chips etc. from
33 Cum 30
the bed of the drain including stacking
the same as per direction.

MS work in ties and angles fitted and


fixed including cost of cutting into
34 proper sizes but excluding cost of Kg 170
welding, nuts, bolts etc. as per
direction.

MS work such as base plate, clamp etc.


including cutting to proper sizes and
35 fitting-fixing in position as per direction Kg 750
(Excluding welding, making holes, nuts,
bolts, rivets etc).

Welding charges to MS works such as


36 MS pipes, MS angles, MS flat bars etc. Rm 70
as per direction.

Spreading and thorough consolidation


of road metal including carrying the
metal from road side stack, hand
packing and consolidating the same
37 Cum 5
with (8~10)Ton roller true to camber
and level including protecting the
edges, watering and blinding with
loamy soil etc. complete.

Carriage of materials such as sand,


debris, brick bats etc. including loading,
38 unloading, local carriage and carriage
to a selected place by truck, push cart
etc. as per direction.

a Up to 2(two) km by truck. Cum 4910

Carriage of heavy girders, RS joists,


trusses, bundle of CI sheet, wooden
39 fender etc. including loading, unloading
and carriage to a selected places etc. as
per direction.

a Up to 2(two) km by truck. Ton 6


Carriage of materials which are
measured in tons such as cement,
bundle less CI sheet, MS angle, MS
40 pipe, GI pipe etc. including loading,
unloading and stacking as per
direction.

a Up to 2(two) km by truck. Ton 4

Carriage of glass, released doors,


windows, pipes and other same
41 materials etc. including loading,
unloading and carriage to a selected
places etc. as per direction.

a Up to 2(two) km by small truck. Trip 1

Cleaning and dressing the site before


and after work inluding leveling,
dressing, widding out grass, up-rooting
42 trees up to 150mm dia., cutting Item 1
jungles, bailing out water, removing all
refuges etc. to a safe distance as per
direction.