Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
FOR
MOBIL PRODUCING NIGERIA UNLIMITED (MPNU)
ENGINEERING REPORT
COMPOSITE REPAIR ON 2” INSTRUMENT GAS LINE AT
UTUE PRODUCTION PLATFORM
1|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
EXECUTIVE SUMMARY
This repair was carried out on a 2” instrument gas line at KP Main Deck at UTUE Production
Platform to stop the leak and reinforce the structure.
Based on the extent of the defect, the repair was designed in accordance to ISO 24817 standards,
which resulted in six layers of FormashieldTM material of an overall repair thickness of
0.437inches. The repair was completed from start to finish in two day.
The pipe was mechanically prepared and cleaned with acetone solvent. The leaked area was filled
with proprietary epoxy putty, coated with PPR primer, then the four layers of Formashield TM
material was applied to the entire repair zone for effective repair.
The pipe was then coated with a corrosion and UV-resistant paint as a finish coat over the repair
as stipulated by the ISO 24817 Standards.
2|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
Table of content
1. INTRODUCTION.....................................................................................................4
1.1 Project Team...................................................................................................4
1.2 Mobilization....................................................................................................4
1.3 Execution........................................................................................................4
1.4 Demobilization...............................................................................................4
1.5 Challenges Encountered................................................................................4
2. Pipe Defect..........................................................................................................4
3. Equipment and Materials....................................................................................5
4. Engineering Design..............................................................................................5
5. Conclusion...........................................................................................................6
6. Attachement.......................................................................................................6
3|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
1 INTRODUCTION
Engineering Automation Technology Limited was called upon to repair a 2” instrument gas line
at KP Main Deck at UTUE Production Platform. Scoping was carried out which detected that the
pipe has a leak point. Engineering design was done and composite repair was carried out
using FormashieldTM material based on client’s specification.
1.2 Mobilization:
Personnel and materials were mobilized through Qua Iboe Terminal (QIT) on 13th
February, 2018.
4|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
1.4 Demobilization:
2 Pipe Defect
The defect being repaired contained 0.154 inches of external wall loss and 0 inches of
assumed end-of-life internal wall loss for a total assumed wall loss of 100%, the total affected
length, considering all defects, is determined as 0.1 inches.
xvi. Acetone
xix. Pencil Durometer Tester
4 Engineering Design
Engineering design was done based on defect and engineering information and the result is attached.
5 Conclusion
The line was repaired and allowed to cure for the 24 hours. Personnel were demobilized to
base in good condition.
6 Attachemnt
I. Sample of photos
II. Engineering Design
III. QC verification sheet
6|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
Fig 1. Disjointed fire water line before Repair Fig 2. After surface prep
7|Page
DOCUMENT TITLE: DOC. NO:
Project Engineering Report (PER) EATL/MPN/ENGRP/024/16
8|Page