Академический Документы
Профессиональный Документы
Культура Документы
18 caiuree'a21
t f81FO C BIlC 10f8C
S 18e: )i 8C uay
Wa Oni; 18" N-""
Eur Ing AD Barley, geotechnical specialist
and the quay behind (Photograph I). Delivery of a pump was arranged u" twI
to dewater behind the piles after high tide to reduce the quantity of
water retained which was itself accelerating failure. A slight tear ~ ~tg
appeared in the top of the sheet piles at the final downstream limit of
failure.
Arrangements were made to bl ing heavy chains to the site to provide
external restraint to the sheet pile wall and prevent the failure pro-
gressing. This was particularly critical in the upstream direction
towards the location of the existing crane. Excessive settlement was
observed over a large area of the concrete paving (up to approximately
500mm) extending some 15m 'in shore'rom the sheet pile wall settle-
I hg 'op:
Photograph t.
ment and a further 30 m in an upstream direction from the initial wall Wall failure after
failure zone. six days.
The situation was monitored over the weekend when the first failure
of the 1.5 m square reinforced concrete service duct was observed. ABOVE:
Failure was by a combination of vertical settlement and outward col- Photograph 2.
lapse into the void formed behind the sheet pile wall. Overall view of
Two sets of chains and tie rods were provided the following week wall failure after
and fixed from the two bollards in the failed capping beam to two about two weeks.
exposed pile caps some 30m behind the quay. Plant was then mobilised i ~
to drive a line of sheet piles normal to the quay in an effort to prevent LEFP. Photograph
the failure progressing closer to the crane (Photograph 2). 3.Severed anchor
Investigation to establish factors contributing towards the wall fail- tendons after wall
ure commenced by removal of a number of complete anchor head units failure.
from the sheet pile in-pans in the area where the collapse had started.
(Photograph 3). downstream return which appeared to restrict failure from progress-
Access to the outside of the wall to inspect all exposed anchor heads ing downstream. The basic construction technique adopted involved:
was provided by the contractors vessel while, during the low tide peri- ~Progressive back filling from the embankment crest towards the line
od, safe access to the inner void allowed a detailed study of all exposed of the new quay.
anchors, the inner steel work, and the reinforced concrete components. ~Driving pairs of H piles for the inner crane rail support. (These
would provide some retention of the backfill).
The structure and consbuctlon techniques ~Driving sheet piles.
The structure was designed to provide a 15m deep shipping berth com- ~Positioning horizontal RSJ beams at 3m centres, spanning between
plete with crane rail and service duct, and is consistent with those com- outer H pile and the sheet piles, seated on brackets and welded to steel-
monly utilised (Figure 1). The 142m length of sheet piles, complete work. The service duct was eventually seated on these beams and the
with heavy reinforced concrete capping beam, provided the quay edge underside fill, but during construction these beams stiffened the com-
and supported the outer crane rail; while pairs of driven 'H'iles, posite structure, to allow high level backfilling prior to anchor con-
complete with reinforced concrete beam, supported the inner crane struction.
rail. In between was located the rectangular reinforced concrete ser- ~Fixing of twin reinforced concrete waling behind sheet piles imme-
vice duct, and a thin reinforced concrete slab covered the entire quay diately above anchor level.
area. Lateral restraint was provided by a combination of a row of ~Backfilling to waling level (RSJ beams provided sheet pile restraint
ground anchors installed three metres below quay level, the toe fixity until anchors stressed).
of the driven sheet piles, the pairs of driven H piles and the general ~Constructing and stressing anchors including testing of 5% to 1.5 x
stiffness of the composite structure. working load.
Construction commenced in Autumn 1968 and was completed by ~Finishing backfill, constructing service duct, R C beams and crane
Autumn 1969. The original site consisted of a paved sloping river rails etc.
embankment, and the new sheet pile line was driven some 25m out ~Dredging to 6.8m below original bed level with final exposed face of
from the original crest, with an upstream and downstream return. sheet piles 15m high above dredge.
The returns were restrained by use of tie rods and anchor beams
positioned in the fill, and the corners by use of diagonal ties. At a later Htstoryof ground anchors and assochted cofyuslon ttrtttectton
date the quay wall line was extended downstream so, at the time of col- systems Inite UK 1965-1970' I
lapse, only the upstream return was exposed. It was in fact the buried ground or rock anchors have been used in a few engineering
'lthough
Rgms 2:Section through anchor head and summary of locaeon of ohund failures (wsakeot link).
~j I P(;7,,PIr
p.
-„,e
There were indications that the original calculations based on the occurrence of corrosion, where some cracking in the corrosion protec-
relevant BS document 'Earth Retaining Structures'CP2) were satis- tion may have taken place, could not be eliminated.
factory in establishing the required waling load to be provided by the The anchor system and associated corrosion protection provided
ground anchors. However, analysis of potential mechanisms and during this early period of anchor introduction in the UK were either
external loading conditions which could have resulted in increase in consistent with, or in advance of, the State-of-the-Art in the UK at that
the required anchor load during the life of the structure could not be time (1968). Investigation revealed that attention was paid to the pro-
ignored, viz: tection of all components, and it is only during the continual develop-
~The dredge depth appeared to have been increased by 6.8m during the ment over the intermediate 20 year period that the shortcomings in cer-
construction period but after the anchors were originally loaded; tain protective mediums then used have been realised.
~temporary tie beams installed below the service duct during con- It cannot be fully established whether anchor failure during week
struction could have failed due to weld joint corrosion, or due to over- beginning 26 February 1990 was solely due to corrosion of certain
loading as a consequence of backfill settlement and subsequent service anchor components, or whether load increase in the anchors caused by
duct loading; failure of other structural components or by increased pressure on the
~failure or partial failure of the flap valves and/or limitation in free wall, also contributed. However, it is inevitable that failure due to cor-
drainage of the backfill material; rosion would eventually have taken place.
~overloading of the quay due to storage of scrap metal (which had Subsequent to failure, the quay wall was reconstructed and
been observed); and restrained by the use of a tie rod system which was easily facilitated in
~slab settlement (due to above) resulting in excessive local drainage of the open site. However, the existing length of wall upstream of the fail-
surface water. (High rainfall run-off being coincident with extreme ure was stabilised by the installation of an additional row of ground
tidal range at time of failure). anchors, fully protected against corrosion by the double plastic protec-
Despite the above potential contributions to anchor overloading tion system. The collapse and inspection demonstrated that the provi-
and/or load fluctuation, there are no indications that failure within the sion of a high quality corrosion protection, in which at least one
fixed anchor had taken place. However, such conditions may have con- proven barrier must exist to protect all steel components when in situ,
tributed to the failures of the anchor tendons and other components and this barrier must outlive the intended lifespan of the structure.
which were observed. Analysis identified three main areas where some
failures occurred, either solely due to corrosion, or due to load increase References
in the anchor tendon identifying the weakest component: 1. Ground Engineering Conference, ICE London 197a
2. The Consulting Engineer, May 197a
~the failure of the epoxy resin coating over the external anchorhead; 3. Littlejohn, GS, and Bruce, DA, 1977. 'Rock anchors state of the art/ Foundation
~the inadequacy of the underhead grouting; Engineering Publications.
~a weakness at the junction between the underhead grouting and the 4. Barley, AD, 1988. 'Ten thousand anchors in rock.'round Engineering (Sept-Nov, 1988).
upper free length protection. 5. Liaison: British Ropes (Bridon Wire), Somerset Wire (Allied Steel), Plasticables Ltd.
Johnson (k Nephew, Professor GS Littlejohn
Where tendon failures within the anchor free length occurred, they 6. Barley, AD, and Clarke, S, 1997. 'The Performance of a twenty-one year old anchor
probably resulted from a combination of overloading and angular devi- protection system in a marine environment.'round Anchor Conference, ICE London,
ation due to change in geometry during wall failure, although the Mareinforced concreteh 1997.
IWI iisl
Ground Engineering welcomes papers on geotechnics, geo-environmental
I. sinai
IQCJ
engineering and engineering geology.
Papers should be topical, practically orientated and preferably of
international interest. Case studies describing innovative geotechnical work are
particularly encouraged. All original papers are refereed. Authors should aim
for a maximum overall length of no more than 3500 words, although shorter
papers are particularly welcome.
Ground Engineering aims to publish papers within six months of receipt
offering authors rapid and widespread dissemination of information
throughout the world's geotechnical community.
Prospective authors should contact: Paul Wheeler.
Tel: +44 171505 6647;
Fax: +44 171 505 6642;
e-mail:paulw@construct.emap.co.uk