0 оценок0% нашли этот документ полезным (0 голосов)
25 просмотров26 страниц
The document provides cost estimates for two alternatives to upgrade the HVAC system for Building 400:
Alternative 2 involves installing water-to-water heat pumps and would cost an estimated total of $4,319,980. This includes well drilling, piping, installing 15 heat pumps, retrofitting existing air handling units, replacing VAV reheat coils, and control system upgrades.
Alternative 3 involves installing central geothermal chillers and would cost an estimated total of $3,809,677. This option replaces the heat pumps with chillers but otherwise involves similar well drilling, piping, air handling unit, and control system work.
The document provides cost estimates for two alternatives to upgrade the HVAC system for Building 400:
Alternative 2 involves installing water-to-water heat pumps and would cost an estimated total of $4,319,980. This includes well drilling, piping, installing 15 heat pumps, retrofitting existing air handling units, replacing VAV reheat coils, and control system upgrades.
Alternative 3 involves installing central geothermal chillers and would cost an estimated total of $3,809,677. This option replaces the heat pumps with chillers but otherwise involves similar well drilling, piping, air handling unit, and control system work.
The document provides cost estimates for two alternatives to upgrade the HVAC system for Building 400:
Alternative 2 involves installing water-to-water heat pumps and would cost an estimated total of $4,319,980. This includes well drilling, piping, installing 15 heat pumps, retrofitting existing air handling units, replacing VAV reheat coils, and control system upgrades.
Alternative 3 involves installing central geothermal chillers and would cost an estimated total of $3,809,677. This option replaces the heat pumps with chillers but otherwise involves similar well drilling, piping, air handling unit, and control system work.
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 54,582 LF $ 10 $ 545,820 4.33-in bore 3 Thermal Bentonite Grout 2,300 BAG $ 30 $ 69,000 4 Geothermal Piping 115,022 LF $ 5.80 $ 667,129 Means 33 51 13.10 1040 5 Facility Piping 789 LF $ 29.50 $ 23,276 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 15 EA $ 20,000 $ 300,000 Vendor pricing 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 272 EA $ 4,792 $ 1,303,424 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 0 EA $ 391 $ - Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 29 DAY $ 1,882 $ 54,584 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 29 DAY $ 1,618 $ 46,908 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 125 PTS $ 800 $ 100,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 121,936 $ 60,968 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 509,933 Subtotal $ 3,909,484 Bonding (1.5%) $ 58,642 Permitting (0.5%) $ 19,547 Design (6%) $ 234,569 Construction Management (1.5%) $ 58,642 Project Management (1%) $ 39,095 TOTAL $ 4,319,980
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 54,582 LF $ 10 $ 545,820 4.33-in bore 3 Thermal Bentonite Grout 2,300 BAG $ 30 $ 69,000 4 Geothermal Piping 115,022 LF $ 5.80 $ 667,129 Means 33 51 13.10 1040 5 Facility Piping 789 LF $ 29.50 $ 23,276 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 0 LS $ 104,000 $ - 7 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 8 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 9 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 272 EA $ 4,792 $ 1,303,424 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 0 EA $ 391 $ - Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 14 DAY $ 1,882 $ 26,351 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 14 DAY $ 1,618 $ 22,645 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 35 PTS $ 800 $ 28,000 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,440 $ 34,720 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 443,442 Subtotal $ 3,399,720 Bonding (1.5%) $ 50,996 Permitting (0.5%) $ 16,999 Design (6%) $ 203,983 Construction Management (1.5%) $ 50,996 Project Management (1%) $ 33,997 TOTAL $ 3,756,691
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 1 of 26
Budget Estimate (Building 400)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 18,538 LF $ 10 $ 185,383 4.33-in bore 3 Thermal Bentonite Grout 800 BAG $ 30 $ 24,000 4 Geothermal Piping 39,330 LF $ 5.80 $ 228,116 Means 33 51 13.10 1040 5 Facility Piping 789 LF $ 29.50 $ 23,276 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 12 LS $ 20,000 $ 240,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 11 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 26 DAY $ 1,882 $ 48,937 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 26 DAY $ 1,618 $ 42,055 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 107 PTS $ 800 $ 85,600 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 118,773 $ 59,386 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 180,326 Subtotal $ 1,382,503 Bonding (1.5%) $ 20,738 Permitting (0.5%) $ 6,913 Design (6%) $ 82,950 Construction Management (1.5%) $ 20,738 Project Management (1%) $ 13,825 TOTAL $ 1,527,666
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 21,298 LF $ 10 $ 212,976 4.33-in bore 3 Thermal Bentonite Grout 900 BAG $ 30 $ 27,000 4 Geothermal Piping 45,125 LF $ 6 $ 261,725 Means 33 51 13.10 1040 5 New Chiller 0 LS $ 104,000 $ - 6 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 14 DAY $ 1,882 $ 26,351 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 14 DAY $ 1,618 $ 22,645 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 35 PTS $ 800 $ 28,000 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,440 $ 34,720 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 121,625 Subtotal $ 932,455 Bonding (1.5%) $ 13,987 Permitting (0.5%) $ 4,662 Design (6%) $ 55,947 Construction Management (1.5%) $ 13,987 Project Management (1%) $ 9,325 TOTAL $ 1,030,363
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 2 of 26
Budget Estimate (Building 401)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,117 LF $ 10 $ 341,172 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 72,046 LF $ 5.80 $ 417,867 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 10 EA $ 20,000 $ 200,000 Vendor pricing 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 110 EA $ 4,792 $ 527,120 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 199 EA $ 391 $ 77,710 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 24 DAY $ 1,882 $ 45,173 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 24 DAY $ 1,618 $ 38,820 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 95 PTS $ 800 $ 76,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 104,437 $ 52,219 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 310,364 Subtotal $ 2,379,456 Bonding (1.5%) $ 35,692 Permitting (0.5%) $ 11,897 Design (6%) $ 142,767 Construction Management (1.5%) $ 35,692 Project Management (1%) $ 23,795 TOTAL $ 2,629,299
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,117 LF $ 10 $ 341,172 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 72,046 LF $ 5.80 $ 417,867 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 0 LS $ 104,000 $ - 7 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 8 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 9 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 110 EA $ 4,792 $ 527,120 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 199 EA $ 391 $ 77,710 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 14 DAY $ 1,882 $ 26,351 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 14 DAY $ 1,618 $ 22,645 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 35 PTS $ 800 $ 28,000 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,440 $ 34,720 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 266,410 Subtotal $ 2,042,476 Bonding (1.5%) $ 30,637 Permitting (0.5%) $ 10,212 Design (6%) $ 122,549 Construction Management (1.5%) $ 30,637 Project Management (1%) $ 20,425 TOTAL $ 2,256,936
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 3 of 26
Budget Estimate (Building 401)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 16,654 LF $ 10 $ 166,536 4.33-in bore 3 Thermal Bentonite Grout 700 BAG $ 30 $ 21,000 4 Geothermal Piping 35,373 LF $ 5.80 $ 205,161 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 8 LS $ 20,000 $ 160,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 11 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 22 DAY $ 1,882 $ 41,408 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 22 DAY $ 1,618 $ 35,585 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 83 PTS $ 800 $ 66,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 104,774 $ 52,387 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 155,470 Subtotal $ 1,191,938 Bonding (1.5%) $ 17,879 Permitting (0.5%) $ 5,960 Design (6%) $ 71,516 Construction Management (1.5%) $ 17,879 Project Management (1%) $ 11,919 TOTAL $ 1,317,092
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 15,041 LF $ 10 $ 150,408 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 31,986 LF $ 6 $ 185,517 Means 33 51 13.10 1040 5 New Chiller 0 LS $ 104,000 $ - 6 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 14 DAY $ 1,882 $ 26,351 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 14 DAY $ 1,618 $ 22,645 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 35 PTS $ 800 $ 28,000 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,440 $ 34,720 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 99,458 Subtotal $ 762,513 Bonding (1.5%) $ 11,438 Permitting (0.5%) $ 3,813 Design (6%) $ 45,751 Construction Management (1.5%) $ 11,438 Project Management (1%) $ 7,625 TOTAL $ 842,577
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 4 of 26
Budget Estimate (Building 402)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,137 LF $ 10 $ 341,370 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 72,088 LF $ 5.80 $ 418,109 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 10 EA $ 20,000 $ 200,000 Vendor pricing 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 133 EA $ 4,792 $ 637,336 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 252 EA $ 391 $ 98,406 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 24 DAY $ 1,882 $ 45,173 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 24 DAY $ 1,618 $ 38,820 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 95 PTS $ 800 $ 76,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 104,437 $ 52,219 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 330,067 Subtotal $ 2,530,510 Bonding (1.5%) $ 37,958 Permitting (0.5%) $ 12,653 Design (6%) $ 151,831 Construction Management (1.5%) $ 37,958 Project Management (1%) $ 25,305 TOTAL $ 2,796,214
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,137 LF $ 10 $ 341,370 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 72,088 LF $ 5.80 $ 418,109 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 83,500 $ 83,500 Means 23 64 19.10 1160, 100 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 9 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 133 EA $ 4,792 $ 637,336 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 252 EA $ 391 $ 98,406 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 19 DAY $ 1,882 $ 35,762 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 19 DAY $ 1,618 $ 30,733 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 42 PTS $ 800 $ 33,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 86,939 $ 43,469 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 302,294 Subtotal $ 2,317,590 Bonding (1.5%) $ 34,764 Permitting (0.5%) $ 11,588 Design (6%) $ 139,055 Construction Management (1.5%) $ 34,764 Project Management (1%) $ 23,176 TOTAL $ 2,560,937
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 5 of 26
Budget Estimate (Building 402)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 10,327 LF $ 10 $ 103,270 4.33-in bore 3 Thermal Bentonite Grout 400 BAG $ 30 $ 12,000 4 Geothermal Piping 22,087 LF $ 5.80 $ 128,103 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 5 LS $ 20,000 $ 100,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 11 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 19 DAY $ 1,882 $ 35,762 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 19 DAY $ 1,618 $ 30,733 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 65 PTS $ 800 $ 52,000 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 94,275 $ 47,137 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 119,549 Subtotal $ 916,545 Bonding (1.5%) $ 13,748 Permitting (0.5%) $ 4,583 Design (6%) $ 54,993 Construction Management (1.5%) $ 13,748 Project Management (1%) $ 9,165 TOTAL $ 1,012,782
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 14,872 LF $ 10 $ 148,716 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 31,630 LF $ 6 $ 183,456 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 83,500 $ 83,500 Means 23 64 19.10 1160, 100 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 19 DAY $ 1,882 $ 35,762 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 19 DAY $ 1,618 $ 30,733 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 42 PTS $ 800 $ 33,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 86,939 $ 43,469 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 115,077 Subtotal $ 882,257 Bonding (1.5%) $ 13,234 Permitting (0.5%) $ 4,411 Design (6%) $ 52,935 Construction Management (1.5%) $ 13,234 Project Management (1%) $ 8,823 TOTAL $ 974,894
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 6 of 26
Budget Estimate (Building 403)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 31,000 LF $ 10 $ 310,000 4.33-in bore 3 Thermal Bentonite Grout 1,300 BAG $ 30 $ 39,000 4 Geothermal Piping 65,500 LF $ 5.80 $ 379,900 Means 33 51 13.10 1040 5 Facility Piping 685 LF $ 29.50 $ 20,208 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 10 EA $ 20,000 $ 200,000 Vendor pricing 7 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 8 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 181 EA $ 4,792 $ 867,352 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 251 EA $ 391 $ 98,016 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 20 DAY $ 1,882 $ 37,644 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 20 DAY $ 1,618 $ 32,350 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 85 PTS $ 800 $ 68,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 90,438 $ 45,219 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 341,720 Subtotal $ 2,619,852 Bonding (1.5%) $ 39,298 Permitting (0.5%) $ 13,099 Design (6%) $ 157,191 Construction Management (1.5%) $ 39,298 Project Management (1%) $ 26,199 TOTAL $ 2,894,937
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 31,000 LF $ 10 $ 310,000 4.33-in bore 3 Thermal Bentonite Grout 1,300 BAG $ 30 $ 39,000 4 Geothermal Piping 65,500 LF $ 5.80 $ 379,900 Means 33 51 13.10 1040 5 Facility Piping 685 LF $ 29.50 $ 20,208 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 0 LS $ 104,000 $ - 7 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 8 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 9 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 181 EA $ 4,792 $ 867,352 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 251 EA $ 391 $ 98,016 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 10 DAY $ 1,882 $ 18,822 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 10 DAY $ 1,618 $ 16,175 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 25 PTS $ 800 $ 20,000 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 55,441 $ 27,721 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 297,766 Subtotal $ 2,282,873 Bonding (1.5%) $ 34,243 Permitting (0.5%) $ 11,414 Design (6%) $ 136,972 Construction Management (1.5%) $ 34,243 Project Management (1%) $ 22,829 TOTAL $ 2,522,574
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 7 of 26
Budget Estimate (Building 403)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 8,257 LF $ 10 $ 82,573 4.33-in bore 3 Thermal Bentonite Grout 300 BAG $ 30 $ 9,000 4 Geothermal Piping 17,740 LF $ 5.80 $ 102,894 Means 33 51 13.10 1040 5 Facility Piping 685 LF $ 29.50 $ 20,208 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 8 LS $ 20,000 $ 160,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 11 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 18 DAY $ 1,882 $ 33,880 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 18 DAY $ 1,618 $ 29,115 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 73 PTS $ 800 $ 58,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 90,775 $ 45,388 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 113,832 Subtotal $ 872,712 Bonding (1.5%) $ 13,091 Permitting (0.5%) $ 4,364 Design (6%) $ 52,363 Construction Management (1.5%) $ 13,091 Project Management (1%) $ 8,727 TOTAL $ 964,347
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 13,696 LF $ 10 $ 136,955 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 29,161 LF $ 6 $ 169,131 Means 33 51 13.10 1040 5 New Chiller 0 LS $ 104,000 $ - 6 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 7 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 10 DAY $ 1,882 $ 18,822 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 10 DAY $ 1,618 $ 16,175 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 25 PTS $ 800 $ 20,000 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 55,441 $ 27,721 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 85,083 Subtotal $ 652,301 Bonding (1.5%) $ 9,785 Permitting (0.5%) $ 3,262 Design (6%) $ 39,138 Construction Management (1.5%) $ 9,785 Project Management (1%) $ 6,523 TOTAL $ 720,792
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 8 of 26
Budget Estimate (Building 404)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 23,742 LF $ 10 $ 237,420 4.33-in bore 3 Thermal Bentonite Grout 1,000 BAG $ 30 $ 30,000 4 Geothermal Piping 50,258 LF $ 5.80 $ 291,498 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 7 EA $ 20,000 $ 140,000 Vendor pricing 7 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 8 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 137 EA $ 4,792 $ 656,504 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 208 EA $ 391 $ 81,224 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 17 DAY $ 1,882 $ 31,997 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 17 DAY $ 1,618 $ 27,498 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 67 PTS $ 800 $ 53,600 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 79,939 $ 39,970 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 268,802 Subtotal $ 2,060,816 Bonding (1.5%) $ 30,912 Permitting (0.5%) $ 10,304 Design (6%) $ 123,649 Construction Management (1.5%) $ 30,912 Project Management (1%) $ 20,608 TOTAL $ 2,277,202
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 23,742 LF $ 10 $ 237,420 4.33-in bore 3 Thermal Bentonite Grout 1,000 BAG $ 30 $ 30,000 4 Geothermal Piping 50,258 LF $ 5.80 $ 291,498 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 9 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 137 EA $ 4,792 $ 656,504 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 208 EA $ 391 $ 81,224 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 15 DAY $ 1,882 $ 28,233 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 15 DAY $ 1,618 $ 24,263 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 32 PTS $ 800 $ 25,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 72,940 $ 36,470 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 258,152 Subtotal $ 1,979,167 Bonding (1.5%) $ 29,688 Permitting (0.5%) $ 9,896 Design (6%) $ 118,750 Construction Management (1.5%) $ 29,688 Project Management (1%) $ 19,792 TOTAL $ 2,186,979
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 9 of 26
Budget Estimate (Building 404)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 11,433 LF $ 10 $ 114,327 4.33-in bore 3 Thermal Bentonite Grout 500 BAG $ 30 $ 15,000 4 Geothermal Piping 24,409 LF $ 5.80 $ 141,571 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 7 LS $ 20,000 $ 140,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 11 AHU HHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 17 DAY $ 1,882 $ 31,997 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 17 DAY $ 1,618 $ 27,498 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 67 PTS $ 800 $ 53,600 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 87,275 $ 43,638 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 121,037 Subtotal $ 927,951 Bonding (1.5%) $ 13,919 Permitting (0.5%) $ 4,640 Design (6%) $ 55,677 Construction Management (1.5%) $ 13,919 Project Management (1%) $ 9,280 TOTAL $ 1,025,386
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 10,926 LF $ 10 $ 109,263 4.33-in bore 3 Thermal Bentonite Grout 500 BAG $ 30 $ 15,000 4 Geothermal Piping 23,345 LF $ 6 $ 135,402 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 5 EA $ 5,500 $ 27,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 15 DAY $ 1,882 $ 28,233 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 15 DAY $ 1,618 $ 24,263 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 5 EA $ 5,000 $ 25,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 32 PTS $ 800 $ 25,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 72,940 $ 36,470 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 5 LS $ 8,000 $ 40,000 source Contingency (15%) $ 95,201 Subtotal $ 729,876 Bonding (1.5%) $ 10,948 Permitting (0.5%) $ 3,649 Design (6%) $ 43,793 Construction Management (1.5%) $ 10,948 Project Management (1%) $ 7,299 TOTAL $ 806,513
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 10 of 26
Budget Estimate (Building 406)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,792 LF $ 10 $ 347,920 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 73,463 LF $ 5.80 $ 426,087 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 10 EA $ 20,000 $ 200,000 Vendor pricing 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 70 EA $ 4,792 $ 335,440 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 221 EA $ 391 $ 86,301 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 24 DAY $ 1,882 $ 45,173 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 24 DAY $ 1,618 $ 38,820 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 95 PTS $ 800 $ 76,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 104,437 $ 52,219 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 285,146 Subtotal $ 2,186,116 Bonding (1.5%) $ 32,792 Permitting (0.5%) $ 10,931 Design (6%) $ 131,167 Construction Management (1.5%) $ 32,792 Project Management (1%) $ 21,861 TOTAL $ 2,415,658
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 34,792 LF $ 10 $ 347,920 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 73,463 LF $ 5.80 $ 426,087 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 94,500 $ 94,500 Means 23 64 19.10 1180, 125 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 9 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 70 EA $ 4,792 $ 335,440 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 221 EA $ 391 $ 86,301 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 19 DAY $ 1,882 $ 35,762 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 19 DAY $ 1,618 $ 30,733 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 42 PTS $ 800 $ 33,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 86,939 $ 43,469 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 259,023 Subtotal $ 1,985,846 Bonding (1.5%) $ 29,788 Permitting (0.5%) $ 9,929 Design (6%) $ 119,151 Construction Management (1.5%) $ 29,788 Project Management (1%) $ 19,858 TOTAL $ 2,194,360
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 11 of 26
Budget Estimate (Building 406)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 10,017 LF $ 10 $ 100,168 4.33-in bore 3 Thermal Bentonite Grout 400 BAG $ 30 $ 12,000 4 Geothermal Piping 21,435 LF $ 5.80 $ 124,325 Means 33 51 13.10 1040 5 Facility Piping 765 LF $ 29.50 $ 22,568 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 6 LS $ 20,000 $ 120,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 11 AHU HHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 20 DAY $ 1,882 $ 37,644 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 20 DAY $ 1,618 $ 32,350 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 71 PTS $ 800 $ 56,800 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 97,774 $ 48,887 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 123,025 Subtotal $ 943,190 Bonding (1.5%) $ 14,148 Permitting (0.5%) $ 4,716 Design (6%) $ 56,591 Construction Management (1.5%) $ 14,148 Project Management (1%) $ 9,432 TOTAL $ 1,042,224
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 14,287 LF $ 10 $ 142,870 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 30,403 LF $ 6 $ 176,336 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 94,500 $ 94,500 Means 23 64 19.10 1180, 125 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 7 EA $ 5,500 $ 38,500 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 19 DAY $ 1,882 $ 35,762 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 19 DAY $ 1,618 $ 30,733 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 7 EA $ 5,000 $ 35,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 42 PTS $ 800 $ 33,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 86,939 $ 43,469 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 7 LS $ 8,000 $ 56,000 source Contingency (15%) $ 114,782 Subtotal $ 879,996 Bonding (1.5%) $ 13,200 Permitting (0.5%) $ 4,400 Design (6%) $ 52,800 Construction Management (1.5%) $ 13,200 Project Management (1%) $ 8,800 TOTAL $ 972,395
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 12 of 26
Budget Estimate (Building 407)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 37,539 LF $ 10 $ 375,390 4.33-in bore 3 Thermal Bentonite Grout 1,600 BAG $ 30 $ 48,000 4 Geothermal Piping 79,232 LF $ 5.80 $ 459,545 Means 33 51 13.10 1040 5 Facility Piping 581 LF $ 29.50 $ 17,140 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 10 EA $ 20,000 $ 200,000 Vendor pricing 7 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 8 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 0 EA $ 4,792 $ - currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 244 EA $ 391 $ 95,282 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 14 DAY $ 1,882 $ 26,351 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 14 DAY $ 1,618 $ 22,645 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 70 PTS $ 800 $ 56,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,440 $ 34,720 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 216,527 Subtotal $ 1,660,044 Bonding (1.5%) $ 24,901 Permitting (0.5%) $ 8,300 Design (6%) $ 99,603 Construction Management (1.5%) $ 24,901 Project Management (1%) $ 16,600 TOTAL $ 1,834,349
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 37,539 LF $ 10 $ 375,390 4.33-in bore 3 Thermal Bentonite Grout 1,600 BAG $ 30 $ 48,000 4 Geothermal Piping 79,232 LF $ 5.80 $ 459,545 Means 33 51 13.10 1040 5 Facility Piping 581 LF $ 29.50 $ 17,140 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 9 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 0 EA $ 4,792 $ - currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 244 EA $ 391 $ 95,282 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 9 DAY $ 1,882 $ 16,940 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 9 DAY $ 1,618 $ 14,558 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 17 PTS $ 800 $ 13,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 51,942 $ 25,971 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 192,355 Subtotal $ 1,474,724 Bonding (1.5%) $ 22,121 Permitting (0.5%) $ 7,374 Design (6%) $ 88,483 Construction Management (1.5%) $ 22,121 Project Management (1%) $ 14,747 TOTAL $ 1,629,570
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 13 of 26
Budget Estimate (Building 407)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 11,174 LF $ 10 $ 111,737 4.33-in bore 3 Thermal Bentonite Grout 500 BAG $ 30 $ 15,000 4 Geothermal Piping 23,865 LF $ 5.80 $ 138,415 Means 33 51 13.10 1040 5 Facility Piping 581 LF $ 29.50 $ 17,140 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 8 LS $ 20,000 $ 160,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 11 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 12 DAY $ 1,882 $ 22,586 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 12 DAY $ 1,618 $ 19,410 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 58 PTS $ 800 $ 46,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 69,777 $ 34,888 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 106,650 Subtotal $ 817,650 Bonding (1.5%) $ 12,265 Permitting (0.5%) $ 4,088 Design (6%) $ 49,059 Construction Management (1.5%) $ 12,265 Project Management (1%) $ 8,177 TOTAL $ 903,503
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 15,098 LF $ 10 $ 150,984 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 32,107 LF $ 6 $ 186,219 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 9 DAY $ 1,882 $ 16,940 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 9 DAY $ 1,618 $ 14,558 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 17 PTS $ 800 $ 13,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 51,942 $ 25,971 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 94,682 Subtotal $ 725,897 Bonding (1.5%) $ 10,888 Permitting (0.5%) $ 3,629 Design (6%) $ 43,554 Construction Management (1.5%) $ 10,888 Project Management (1%) $ 7,259 TOTAL $ 802,116
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 14 of 26
Budget Estimate (Building 408)
Alternative 2 - Water to Water HeatPump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 36,270 LF $ 10 $ 362,700 4.33-in bore 3 Thermal Bentonite Grout 1,500 BAG $ 30 $ 45,000 4 Geothermal Piping 76,567 LF $ 5.80 $ 444,089 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 13 EA $ 20,000 $ 260,000 Vendor pricing 7 AHU CHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs 8 AHU HHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 74 EA $ 4,792 $ 354,608 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 230 EA $ 391 $ 89,815 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 25 DAY $ 1,882 $ 47,055 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 25 DAY $ 1,618 $ 40,438 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 6 EA $ 5,000 $ 30,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 108 PTS $ 800 $ 86,400 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 107,937 $ 53,968 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 6 LS $ 8,000 $ 48,000 source Contingency (15%) $ 301,556 Subtotal $ 2,311,933 Bonding (1.5%) $ 34,679 Permitting (0.5%) $ 11,560 Design (6%) $ 138,716 Construction Management (1.5%) $ 34,679 Project Management (1%) $ 23,119 TOTAL $ 2,554,686
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 36,270 LF $ 10 $ 362,700 4.33-in bore 3 Thermal Bentonite Grout 1,500 BAG $ 30 $ 45,000 4 Geothermal Piping 76,567 LF $ 5.80 $ 444,089 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs 9 AHU HHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 74 EA $ 4,792 $ 354,608 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 230 EA $ 391 $ 89,815 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 17 DAY $ 1,882 $ 31,997 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 17 DAY $ 1,618 $ 27,498 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 6 EA $ 5,000 $ 30,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 37 PTS $ 800 $ 29,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 79,939 $ 39,970 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 6 LS $ 8,000 $ 48,000 source Contingency (15%) $ 263,862 Subtotal $ 2,022,942 Bonding (1.5%) $ 30,344 Permitting (0.5%) $ 10,115 Design (6%) $ 121,377 Construction Management (1.5%) $ 30,344 Project Management (1%) $ 20,229 TOTAL $ 2,235,351
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 15 of 26
Budget Estimate (Building 408)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 11,133 LF $ 10 $ 111,333 4.33-in bore 3 Thermal Bentonite Grout 500 BAG $ 30 $ 15,000 4 Geothermal Piping 23,780 LF $ 5.80 $ 137,923 Means 33 51 13.10 1040 5 Facility Piping 741 LF $ 29.50 $ 21,860 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 8 LS $ 20,000 $ 160,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs 11 AHU HHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 20 DAY $ 1,882 $ 37,644 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 20 DAY $ 1,618 $ 32,350 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 6 EA $ 5,000 $ 30,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 78 PTS $ 800 $ 62,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 97,774 $ 48,887 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 6 LS $ 8,000 $ 48,000 source Contingency (15%) $ 130,323 Subtotal $ 999,143 Bonding (1.5%) $ 14,987 Permitting (0.5%) $ 4,996 Design (6%) $ 59,949 Construction Management (1.5%) $ 14,987 Project Management (1%) $ 9,991 TOTAL $ 1,104,053
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 14,134 LF $ 10 $ 141,336 4.33-in bore 3 Thermal Bentonite Grout 600 BAG $ 30 $ 18,000 4 Geothermal Piping 30,081 LF $ 6 $ 174,467 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 107,500 $ 107,500 Means 23 64 19.10 1200, 145 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 6 EA $ 5,500 $ 33,000 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 17 DAY $ 1,882 $ 31,997 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 17 DAY $ 1,618 $ 27,498 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 6 EA $ 5,000 $ 30,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 37 PTS $ 800 $ 29,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 79,939 $ 39,970 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 6 LS $ 8,000 $ 48,000 source Contingency (15%) $ 111,272 Subtotal $ 853,084 Bonding (1.5%) $ 12,796 Permitting (0.5%) $ 4,265 Design (6%) $ 51,185 Construction Management (1.5%) $ 12,796 Project Management (1%) $ 8,531 TOTAL $ 942,658
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 16 of 26
Budget Estimate (Building 424)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 21,384 LF $ 10 $ 213,840 4.33-in bore 3 Thermal Bentonite Grout 900 BAG $ 30 $ 27,000 4 Geothermal Piping 45,306 LF $ 5.80 $ 262,777 Means 33 51 13.10 1040 5 Facility Piping 567 LF $ 29.50 $ 16,727 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 7 EA $ 20,000 $ 140,000 Vendor pricing 7 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 8 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 9 EA $ 4,792 $ 43,128 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 3 EA $ 391 $ 1,172 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 12 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 13 Mechanical Installation 11 DAY $ 1,882 $ 20,704 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 11 DAY $ 1,618 $ 17,793 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 16 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 52 PTS $ 800 $ 41,600 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 58,941 $ 29,470 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 138,398 Subtotal $ 1,061,053 Bonding (1.5%) $ 15,916 Permitting (0.5%) $ 5,305 Design (6%) $ 63,663 Construction Management (1.5%) $ 15,916 Project Management (1%) $ 10,611 TOTAL $ 1,172,463
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 21,384 LF $ 10 $ 213,840 4.33-in bore 3 Thermal Bentonite Grout 900 BAG $ 30 $ 27,000 4 Geothermal Piping 45,306 LF $ 5.80 $ 262,777 Means 33 51 13.10 1040 5 Facility Piping 567 LF $ 29.50 $ 16,727 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS $ 73,500 $ 73,500 MEANS 23 64 19.10 1140, 85 TON CHILLER 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 9 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 9 EA $ 4,792 $ 43,128 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 3 EA $ 391 $ 1,172 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 9 DAY $ 1,882 $ 16,940 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 9 DAY $ 1,618 $ 14,558 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 18 Control Points 17 PTS $ 800 $ 13,600 temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 51,942 $ 25,971 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 122,648 Subtotal $ 940,304 Bonding (1.5%) $ 14,105 Permitting (0.5%) $ 4,702 Design (6%) $ 56,418 Construction Management (1.5%) $ 14,105 Project Management (1%) $ 9,403 TOTAL $ 1,039,036
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 17 of 26
Budget Estimate (Building 424)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 7,094 LF $ 10 $ 70,936 4.33-in bore 3 Thermal Bentonite Grout 300 BAG $ 30 $ 9,000 4 Geothermal Piping 15,296 LF $ 5.80 $ 88,720 Means 33 51 13.10 1040 5 Facility Piping 567 LF $ 29.50 $ 16,727 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 5 LS $ 20,000 $ 100,000 Vendor pricing 7 Boiler 1 LS $ 27,100 $ 27,100 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 140 LF $ 7.45 $ 1,043 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 1 LS $ 1,500 $ 1,500 ROM 10 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 11 AHU HHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 12 General Site Work and Excavation 15 DAY $ 1,467 $ 22,009 3 week POP, Means Crew B-12E 13 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 14 Mechanical Installation 9 DAY $ 1,882 $ 16,940 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 9 DAY $ 1,618 $ 14,558 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 17 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 40 PTS $ 800 $ 32,000 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 59,278 $ 29,639 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 78,591.23 Subtotal $ 602,533 Bonding (1.5%) $ 9,038 Permitting (0.5%) $ 3,013 Design (6%) $ 36,152 Construction Management (1.5%) $ 9,038 Project Management (1%) $ 6,025 TOTAL $ 665,799
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 1 LS $ 10,000 $ 10,000 Historical 2 Geothermal Well Drilling 10,452 LF $ 10 $ 104,517 4.33-in bore 3 Thermal Bentonite Grout 400 BAG $ 30 $ 12,000 4 Geothermal Piping 22,349 LF $ 6 $ 129,622 Means 33 51 13.10 1040 5 New Chiller 1 LS $ 73,500 $ 73,500 MEANS 23 64 19.10 1140, 85 TON CHILLER 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 7 AHU CHW Coil Retrofits 2 EA $ 5,500 $ 11,000 Number of AHUs 8 General Site Work and Excavation 10 DAY $ 1,467 $ 14,672 2 week POP, Means Crew B-12E 9 Equipment Crane 3 DAY $ 1,924 $ 5,772 Means Crew B-12A 10 Mechanical Installation 9 DAY $ 1,882 $ 16,940 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 9 DAY $ 1,618 $ 14,558 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 1 LS $ 30,000 $ 30,000 Historical 13 Economizing and Outside Air Function 2 EA $ 5,000 $ 10,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU (OA 14 Control Points 17 PTS $ 800 $ 13,600 temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 51,942 $ 25,971 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 16 Demolition 2 LS $ 8,000 $ 16,000 source Contingency (15%) $ 73,223 Subtotal $ 561,374 Bonding (1.5%) $ 8,421 Permitting (0.5%) $ 2,807 Design (6%) $ 33,682 Construction Management (1.5%) $ 8,421 Project Management (1%) $ 5,614 TOTAL $ 620,318
\\PLD2-FS1\Project\Projects\GABEL\Gabel-Tomah VAMC-3617147319\4.0_Deliverables\4.4_Calcs-Analysis\Calculations\Tomah VA Cost Estimate Rev1.xlsxTomah VA Cost Estimate Rev1.xlsx Page 18 of 26
Budget Estimate Summary (Buildings 400, 407, and 408)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 128,391 LF $ 10 $ 1,283,910 4.33-in bore 3 Thermal Bentonite Grout 5,400 BAG $ 30 $ 162,000 4 Geothermal Piping 270,821 LF $ 5.80 $ 1,570,762 Means 33 51 13.10 1040 5 Facility Piping 2,111 LF $ 29.50 $ 62,275 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 38 EA $ 20,000 $ 760,000 Vendor pricing 7 AHU CHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs 8 AHU HHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Reheat Coils Demolition/Replacement 346 EA $ 4,792 $ 1,658,032 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 474 EA $ 391 $ 185,097 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 12 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 13 Mechanical Installation 68 DAY $ 1,882 $ 127,990 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 68 DAY $ 1,618 $ 109,990 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 16 Economizing and Outside Air Function 15 EA $ 5,000 $ 75,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 303 PTS $ 800 $ 242,400 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 299,312 $ 149,656 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 15 LS $ 8,000 $ 120,000 source Contingency (15%) $ 1,028,017 Subtotal $ 7,881,461 Bonding (1.5%) $ 118,222 Permitting (0.5%) $ 39,407 Design (6%) $ 472,888 Construction Management (1.5%) $ 118,222 Project Management (1%) $ 78,815 TOTAL $ 8,709,015
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 128,391 LF $ 10 $ 1,283,910 4.33-in bore 3 Thermal Bentonite Grout 5,400 BAG $ 30 $ 162,000 4 Geothermal Piping 270,821 LF $ 5.80 $ 1,570,762 Means 33 51 13.10 1040 5 Facility Piping 2,111 LF $ 29.50 $ 62,275 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 2 LS Varies $ 215,000 Means 23 64 19.10, Various Sizes 7 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 8 AHU CHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs 9 AHU HHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 346 EA $ 4,792 $ 1,658,032 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 474 EA $ 391 $ 185,097 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 40 DAY $ 1,882 $ 75,288 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 40 DAY $ 1,618 $ 64,700 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 15 EA $ 5,000 $ 75,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 18 Control Points 89 PTS $ 800 $ 71,200 (OA temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 201,321 $ 100,660 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 15 LS $ 8,000 $ 120,000 source Contingency (15%) $ 899,659 Subtotal $ 6,897,386 Bonding (1.5%) $ 103,461 Permitting (0.5%) $ 34,487 Design (6%) $ 413,843 Construction Management (1.5%) $ 103,461 Project Management (1%) $ 68,974 TOTAL $ 7,621,612 Budget Estimate Summary (Buildings 400, 407, and 408)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 40,845 LF $ 10 $ 408,452 4.33-in bore 3 Thermal Bentonite Grout 1,800 BAG $ 30 $ 54,000 4 Geothermal Piping 86,975 LF $ 5.80 $ 504,455 Means 33 51 13.10 1040 5 Facility Piping 2,111 LF $ 29.50 $ 62,275 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 28 LS $ 20,000 $ 560,000 Vendor pricing 7 Boiler 3 LS $ 27,100 $ 81,300 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 420 LF $ 7.45 $ 3,129 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 3 LS $ 1,500 $ 4,500 ROM 10 AHU CHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs 11 AHU HHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs 12 General Site Work and Excavation 45 DAY $ 1,467 $ 66,026 3 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 58 DAY $ 1,882 $ 109,168 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 58 DAY $ 1,618 $ 93,815 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 15 EA $ 5,000 $ 75,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 243 PTS $ 800 $ 194,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 286,324 $ 143,162 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 15 LS $ 8,000 $ 120,000 source Contingency (15%) $ 417,299 Subtotal $ 3,199,296 Bonding (1.5%) $ 47,989 Permitting (0.5%) $ 15,996 Design (6%) $ 191,958 Construction Management (1.5%) $ 47,989 Project Management (1%) $ 31,993 TOTAL $ 3,535,222
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 50,530 LF $ 10 $ 505,296 4.33-in bore 3 Thermal Bentonite Grout 2,100 BAG $ 30 $ 63,000 4 Geothermal Piping 107,312 LF $ 6 $ 622,411 Means 33 51 13.10 1040 5 New Chiller 2 LS Varies $ 215,000 Means 23 64 19.10, Various Sizes 6 Chiller Condensing Pipe Retrofits 1 EA $ 7,470 $ 7,470 Means D3030 130 1010 7 AHU CHW Coil Retrofits 15 EA $ 5,500 $ 82,500 Number of AHUs 8 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 9 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 10 Mechanical Installation 40 DAY $ 1,882 $ 75,288 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 40 DAY $ 1,618 $ 64,700 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 13 Economizing and Outside Air Function 15 EA $ 5,000 $ 75,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 89 $ 800 14 Control Points PTS $ 71,200 (OA temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 201,321 $ 100,660 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 15 $ 8,000 16 Demolition LS $ 120,000 source Contingency (15%) $ 327,579 Subtotal $ 2,511,436 Bonding (1.5%) $ 37,672 Permitting (0.5%) $ 12,557 Design (6%) $ 150,686 Construction Management (1.5%) $ 37,672 Project Management (1%) $ 25,114 TOTAL $ 2,775,137 Budget Estimate Summary (Buildings 401, 402, and 403)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 99254.2 LF $ 10 $ 992,542 4.33-in bore 3 Thermal Bentonite Grout 4100 BAG $ 30 $ 123,000 4 Geothermal Piping 209633.82 LF $ 5.80 $ 1,215,876 Means 33 51 13.10 1040 5 Facility Piping 2215 LF $ 29.50 $ 65,343 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 30 EA $ 20,000 $ 600,000 Vendor pricing 7 AHU CHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs 8 AHU HHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 424 9 VAV Reheat Coils Demolition/Replacement EA $ 4,792 $ 2,031,808 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 702 EA $ 391 $ 274,131 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 12 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 13 Mechanical Installation 68 DAY $ 1,882 $ 127,990 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 68 DAY $ 1,618 $ 109,990 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 16 Economizing and Outside Air Function 19 EA $ 5,000 $ 95,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 275 PTS $ 800 $ 220,000 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 299,312 $ 149,656 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 19 LS $ 8,000 $ 152,000 source Contingency (15%) $ 982,150 Subtotal $ 7,529,819 Bonding (1.5%) $ 112,947 Permitting (0.5%) $ 37,649 Design (6%) $ 451,789 Construction Management (1.5%) $ 112,947 Project Management (1%) $ 75,298 TOTAL $ 8,320,450
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 99,254 LF $ 10 $ 992,542 4.33-in bore 3 Thermal Bentonite Grout 4,100 BAG $ 30 $ 123,000 4 Geothermal Piping 209,634 LF $ 5.80 $ 1,215,876 Means 33 51 13.10 1040 5 Facility Piping 2,215 LF $ 29.50 $ 65,343 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 1 LS Varies $ 83,500 Means 23 64 19.10, Various Sizes 7 Chiller Condensing Pipe Retrofits 2 EA $ 7,470 $ 14,940 Means D3030 130 1010 8 AHU CHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs 9 AHU HHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 424 EA $ 4,792 $ 2,031,808 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 702 EA $ 391 $ 274,131 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 43 DAY $ 1,882 $ 80,935 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 43 DAY $ 1,618 $ 69,553 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 19 EA $ 5,000 $ 95,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 18 Control Points 102 PTS $ 800 $ 81,600 (OA temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 211,820 $ 105,910 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 19 LS $ 8,000 $ 152,000 source Contingency (15%) $ 866,470 Subtotal $ 6,642,940 Bonding (1.5%) $ 99,644 Permitting (0.5%) $ 33,215 Design (6%) $ 398,576 Construction Management (1.5%) $ 99,644 Project Management (1%) $ 66,429 TOTAL $ 7,340,448 Budget Estimate Summary (Buildings 401, 402, and 403)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 35,238 LF $ 10 $ 352,379 4.33-in bore 3 Thermal Bentonite Grout 1,400 BAG $ 30 $ 42,000 4 Geothermal Piping 75,200 LF $ 5.80 $ 436,158 Means 33 51 13.10 1040 5 Facility Piping 2,215 LF $ 29.50 $ 65,343 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 21 LS $ 20,000 $ 420,000 Vendor pricing 7 Boiler 3 LS $ 27,100 $ 81,300 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 420 LF $ 7.45 $ 3,129 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 3 LS $ 1,500 $ 4,500 ROM 10 AHU CHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs 11 AHU HHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs 12 General Site Work and Excavation 45 DAY $ 1,467 $ 66,026 3 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 59 DAY $ 1,882 $ 111,050 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 59 DAY $ 1,618 $ 95,433 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 19 EA $ 5,000 $ 95,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 221 PTS $ 800 $ 176,800 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 289,824 $ 144,912 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 19 LS $ 8,000 $ 152,000 source Contingency (15%) $ 388,852 Subtotal $ 2,981,195 Bonding (1.5%) $ 44,718 Permitting (0.5%) $ 14,906 Design (6%) $ 178,872 Construction Management (1.5%) $ 44,718 Project Management (1%) $ 29,812 TOTAL $ 3,294,221
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 43,608 LF $ 10 $ 436,079 4.33-in bore 3 Thermal Bentonite Grout 1,800 BAG $ 30 $ 54,000 4 Geothermal Piping 92,777 LF $ 6 $ 538,104 Means 33 51 13.10 1040 5 New Chiller 1 LS Varies $ 83,500 Means 23 64 19.10, Various Sizes 6 Chiller Condensing Pipe Retrofits 2 EA $ 7,470 $ 14,940 Means D3030 130 1010 7 AHU CHW Coil Retrofits 19 EA $ 5,500 $ 104,500 Number of AHUs 8 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 9 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 10 Mechanical Installation 43 DAY $ 1,882 $ 80,935 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 43 DAY $ 1,618 $ 69,553 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 13 Economizing and Outside Air Function 19 EA $ 5,000 $ 95,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 102 $ 800 14 Control Points PTS $ 81,600 (OA temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 211,820 $ 105,910 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 $ 8,000 16 Demolition LS $ 152,000 source Contingency (15%) $ 299,618 Subtotal $ 2,297,071 Bonding (1.5%) $ 34,456 Permitting (0.5%) $ 11,485 Design (6%) $ 137,824 Construction Management (1.5%) $ 34,456 Project Management (1%) $ 22,971 TOTAL $ 2,538,263 Budget Estimate Summary (Buildings 404, 406, and 424)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 79918 LF $ 10 $ 799,180 4.33-in bore 3 Thermal Bentonite Grout 3300 BAG $ 30 $ 99,000 4 Geothermal Piping 169027.8 LF $ 5.80 $ 980,361 Means 33 51 13.10 1040 5 Facility Piping 2073 LF $ 29.50 $ 61,154 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 24 EA $ 20,000 $ 480,000 Vendor pricing 7 AHU CHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs 8 AHU HHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 216 9 VAV Reheat Coils Demolition/Replacement EA $ 4,792 $ 1,035,072 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 432 EA $ 391 $ 168,696 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 12 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 13 Mechanical Installation 52 DAY $ 1,882 $ 97,874 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 52 DAY $ 1,618 $ 84,110 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 16 Economizing and Outside Air Function 14 EA $ 5,000 $ 70,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 214 PTS $ 800 $ 171,200 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 243,317 $ 121,659 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 14 LS $ 8,000 $ 112,000 source Contingency (15%) $ 692,346 Subtotal $ 5,307,984 Bonding (1.5%) $ 79,620 Permitting (0.5%) $ 26,540 Design (6%) $ 318,479 Construction Management (1.5%) $ 79,620 Project Management (1%) $ 53,080 TOTAL $ 5,865,323
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 79,918 LF $ 10 $ 799,180 4.33-in bore 3 Thermal Bentonite Grout 3,300 BAG $ 30 $ 99,000 4 Geothermal Piping 169,028 LF $ 5.80 $ 980,361 Means 33 51 13.10 1040 5 Facility Piping 2,073 LF $ 29.50 $ 61,154 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 3 LS Varies $ 275,500 Means 23 64 19.10, Various Sizes 7 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ - Means D3030 130 1010 8 AHU CHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs 9 AHU HHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 216 EA $ 4,792 $ 1,035,072 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 432 EA $ 391 $ 168,696 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 43 DAY $ 1,882 $ 80,935 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 43 DAY $ 1,618 $ 69,553 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 14 EA $ 5,000 $ 70,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 18 Control Points 91 PTS $ 800 $ 72,800 (OA temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 211,820 $ 105,910 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 14 LS $ 8,000 $ 112,000 source Contingency (15%) $ 639,824 Subtotal $ 4,905,317 Bonding (1.5%) $ 73,580 Permitting (0.5%) $ 24,527 Design (6%) $ 294,319 Construction Management (1.5%) $ 73,580 Project Management (1%) $ 49,053 TOTAL $ 5,420,375 Budget Estimate Summary (Buildings 404, 406, and 424)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 28,543 LF $ 10 $ 285,431 4.33-in bore 3 Thermal Bentonite Grout 1,200 BAG $ 30 $ 36,000 4 Geothermal Piping 61,141 LF $ 5.80 $ 354,615 Means 33 51 13.10 1040 5 Facility Piping 2,073 LF $ 29.50 $ 61,154 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 18 LS $ 20,000 $ 360,000 Vendor pricing 7 Boiler 3 LS $ 27,100 $ 81,300 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 420 LF $ 7.45 $ 3,129 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 3 LS $ 1,500 $ 4,500 ROM 10 AHU CHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs 11 AHU HHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs 12 General Site Work and Excavation 45 DAY $ 1,467 $ 66,026 3 week POP, Means Crew B-12E 13 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 14 Mechanical Installation 46 DAY $ 1,882 $ 86,581 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 46 DAY $ 1,618 $ 74,405 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 17 Economizing and Outside Air Function 14 EA $ 5,000 $ 70,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 178 PTS $ 800 $ 142,400 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 244,328 $ 122,164 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 14 LS $ 8,000 $ 112,000 source Contingency (15%) $ 322,653 Subtotal $ 2,473,673 Bonding (1.5%) $ 37,105 Permitting (0.5%) $ 12,368 Design (6%) $ 148,420 Construction Management (1.5%) $ 37,105 Project Management (1%) $ 24,737 TOTAL $ 2,733,409
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 3 LS $ 10,000 $ 30,000 Historical 2 Geothermal Well Drilling 35,665 LF $ 10 $ 356,650 4.33-in bore 3 Thermal Bentonite Grout 1,500 BAG $ 30 $ 45,000 4 Geothermal Piping 76,097 LF $ 6 $ 441,360 Means 33 51 13.10 1040 5 New Chiller 3 LS Varies $ 275,500 Means 23 64 19.10, Various Sizes 6 Chiller Condensing Pipe Retrofits 0 EA $ 7,470 $ -Means D3030 130 1010 7 AHU CHW Coil Retrofits 14 EA $ 5,500 $ 77,000 Number of AHUs 8 General Site Work and Excavation 30 DAY $ 1,467 $ 44,017 2 week POP, Means Crew B-12E 9 Equipment Crane 9 DAY $ 1,924 $ 17,316 Means Crew B-12A 10 Mechanical Installation 43 DAY $ 1,882 $ 80,935 2 days per AHU and 5 days per chiller, Means Crew R-18 11 Electrical Installation 43 DAY $ 1,618 $ 69,553 2 days per AHU and 5 days per chiller, Means Crew Q-2 12 Programming Existing BMS 3 LS $ 30,000 $ 90,000 Historical 13 Economizing and Outside Air Function 14 EA $ 5,000 $ 70,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 91 $ 800 14 Control Points PTS $ 72,800 (OA temp/humidity, OA damper control, 3 TBD) 15 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 211,820 $ 105,910 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 14 $ 8,000 16 Demolition LS $ 112,000 source Contingency (15%) $ 283,206 Subtotal $ 2,171,246 Bonding (1.5%) $ 32,569 Permitting (0.5%) $ 10,856 Design (6%) $ 130,275 Construction Management (1.5%) $ 32,569 Project Management (1%) $ 21,712 TOTAL $ 2,399,226 Budget Estimate Summary (All Buildings)
Alternative 2 - Water to Water Heat Pump
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 9 LS $ 10,000 $ 90,000 Historical 2 Geothermal Well Drilling 307,563 LF $ 10 $ 3,075,632 4.33-in bore 3 Thermal Bentonite Grout 12,800 BAG $ 30 $ 384,000 4 Geothermal Piping 649,483 LF $ 5.80 $ 3,767,000 Means 33 51 13.10 1040 5 Facility Piping 6,399 LF $ 29.50 $ 188,771 Means 22 11 13.44 0610 (Includes CV Reheat) 6 20 Ton Water to Water HP 92 EA $ 20,000 $ 1,840,000 Vendor pricing 7 AHU CHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs 8 AHU HHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 9 VAV Terminal Replacement, Hot Water Reheat 986 EA $ 4,792 $ 4,724,912 currently exist, Means 23 05 05.10 3800 10 Convectors Demolition/Replacement 1608 EA $ 391 $ 627,924 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 11 General Site Work and Excavation 90 DAY $ 1,467 $ 132,052 2 week POP, Means Crew B-12E 12 Equipment Crane 27 DAY $ 1,924 $ 51,947 Means Crew B-12A 13 Mechanical Installation 188 DAY $ 1,882 $ 353,854 1 day per heat pump and 2 per AHU, Means Crew R-18 14 Electrical Installation 188 DAY $ 1,618 $ 304,090 1 day per heat pump and 2 per AHU, Means Crew Q-2 15 Programming Existing BMS 9 LS $ 30,000 $ 270,000 Historical 16 Economizing and Outside Air Function 48 EA $ 5,000 $ 240,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 17 Control Points 792 PTS $ 800 $ 633,600 TBD) 18 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 841,942 $ 420,971 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 19 Demolition 48 LS $ 8,000 $ 384,000 source Contingency (15%) $ 2,702,513 Subtotal $ 20,719,264 Bonding (1.5%) $ 310,789 Permitting (0.5%) $ 103,596 Design (6%) $ 1,243,156 Construction Management (1.5%) $ 310,789 Project Management (1%) $ 207,193 TOTAL $ 22,894,787
Alternative 3 - Central Geothermal Chillers
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 9 LS $ 10,000 $ 90,000 Historical 2 Geothermal Well Drilling 307,563 LF $ 10 $ 3,075,632 4.33-in bore 3 Thermal Bentonite Grout 12,800 BAG $ 30 $ 384,000 4 Geothermal Piping 649,483 LF $ 5.80 $ 3,767,000 Means 33 51 13.10 1040 5 Facility Piping 6,399 LF $ 29.50 $ 188,771 Means 22 11 13.44 0610 (Includes CV Reheat) 6 New Chiller 6 LS Varies $ 574,000 Means 23 64 19.10, Various Sizes 7 Chiller Condensing Pipe Retrofits 3 EA $ 7,470 $ 22,410 Means D3030 130 1010 8 AHU CHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs 9 AHU HHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs Means D3040 134 1010, VAV Terminal 1250 CFM, Assume power lines 10 VAV Reheat Coils Demolition/Replacement 986 EA $ 4,792 $ 4,724,912 currently exist, Means 23 05 05.10 3800 11 Convectors Demolition/Replacement 1608 EA $ 391 $ 627,924 Means 23 82 33.10 2226, 21"H x 36"L, Means 23 05 05.10 2976 12 General Site Work and Excavation 90 DAY $ 1,467 $ 132,052 2 week POP, Means Crew B-12E 13 Equipment Crane 27 DAY $ 1,924 $ 51,947 Means Crew B-12A 14 Mechanical Installation 126 DAY $ 1,882 $ 237,157 2 days per AHU and 5 days per chiller, Means Crew R-18 15 Electrical Installation 126 DAY $ 1,618 $ 203,805 2 days per AHU and 5 days per chiller, Means Crew Q-2 16 Programming Existing BMS 9 LS $ 30,000 $ 270,000 Historical 17 Economizing and Outside Air Function 48 EA $ 5,000 $ 240,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 18 Control Points 282 PTS $ 800 $ 225,600 (OA temp/humidity, OA damper control, 3 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 624,961 $ 312,480 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 48 LS $ 8,000 $ 384,000 source Contingency (15%) $ 2,405,953 Subtotal $ 18,445,642 Bonding (1.5%) $ 276,685 Permitting (0.5%) $ 92,228 Design (6%) $ 1,106,739 Construction Management (1.5%) $ 276,685 Project Management (1%) $ 184,456 TOTAL $ 20,382,435 Budget Estimate Summary (All Buildings)
Alternative 4 - Water to Water Heat Pump with Auxiliary Boiler
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 9 LS $ 10,000 $ 90,000 Historical 2 Geothermal Well Drilling 104,626 LF $ 10 $ 1,046,262 4.33-in bore 3 Thermal Bentonite Grout 4,400 BAG $ 30 $ 132,000 4 Geothermal Piping 223,315 LF $ 5.80 $ 1,295,227 Means 33 51 13.10 1040 5 Facility Piping 6,399 LF $ 29.50 $ 188,771 Means 22 11 13.44 0610 6 20 Ton Water to Water HP 67 LS $ 20,000 $ 1,340,000 Vendor pricing 7 Boiler 9 LS $ 27,100 $ 243,900 Means 23 52 23.20 3300, 1530 MBH Gas Fired Boiler Assumes utility brings gas to road outside of facility, 1-in SDR 11 Means 8 Natural Gas Piping 1,260 LF $ 7.45 $ 9,387 33 51 Means 13.10 1040 9 Gas Meter, Regulator, and Other Appurtenances 9 LS $ 1,500 $ 13,500 ROM 10 AHU CHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs 11 AHU HHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs 12 General Site Work and Excavation 135 DAY $ 1,467 $ 198,077 3 week POP, Means Crew B-12E 13 Equipment Crane 27 DAY $ 1,924 $ 51,947 Means Crew B-12A 14 Mechanical Installation 163 DAY $ 1,882 $ 306,799 2 days per heat pump and AHU, Means Crew R-18 15 Electrical Installation 163 DAY $ 1,618 $ 263,653 2 days per heat pump and AHU, Means Crew Q-2 16 Programming Existing BMS 9 LS $ 30,000 $ 270,000 Historical 17 Economizing and Outside Air Function 48 EA $ 5,000 $ 240,000 Damper control motors 6 pts per heat pump (EWT, LWT, COMP Status, Pump Status, Run Status, O/I Control), 5 pts per AHU (OA temp/humidity, OA damper control, 3 18 Control Points 642 PTS $ 800 $ 513,600 TBD) 19 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 820,475 $ 410,238 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 20 Demolition 48 LS $ 8,000 $ 384,000 source Contingency (15%) $ 1,128,804 Subtotal $ 8,654,164 Bonding (1.5%) $ 129,812 Permitting (0.5%) $ 43,271 Design (6%) $ 519,250 Construction Management (1.5%) $ 129,812 Project Management (1%) $ 86,542 TOTAL $ 9,562,851
Alternative 5 - Central Geothermal Chillers (Cooling Only)
Item Description Quantity UOM Unit Cost Extended Price Notes/Assumptions 1 Mobilization/Demobilization 9 LS $ 10,000 $ 90,000 Historical 2 Geothermal Well Drilling 129,803 LF $ 10 $ 1,298,025 4.33-in bore 3 Thermal Bentonite Grout 5,400 BAG $ 30 $ 162,000 4 Geothermal Piping 276,185 LF $ 6 $ 1,601,874 Means 33 51 13.10 1040 9 New Chiller 6 LS Varies $ 574,000 Means 23 64 19.10, Various Sizes 10 Chiller Condensing Pipe Retrofits 3 EA $ 7,470 $ 22,410 Means D3030 130 1010 11 AHU CHW Coil Retrofits 48 EA $ 5,500 $ 264,000 Number of AHUs 16 General Site Work and Excavation 90 DAY $ 1,467 $ 132,052 2 week POP, Means Crew B-12E 17 Equipment Crane 27 DAY $ 1,924 $ 51,947 Means Crew B-12A 18 Mechanical Installation 126 DAY $ 1,882 $ 237,157 2 days per AHU and 5 days per chiller, Means Crew R-18 19 Electrical Installation 126 DAY $ 1,618 $ 203,805 2 days per AHU and 5 days per chiller, Means Crew Q-2 20 Programming Existing BMS 9 LS $ 30,000 $ 270,000 Historical 21 Economizing and Outside Air Function 48 EA $ 5,000 $ 240,000 Damper control motors 7 pts per chiller (EWT, LWT, Status, O/I Control, 3 TBD), 5 pts per AHU 282 $ 800 22 Control Points PTS $ 225,600 (OA temp/humidity, OA damper control, 3 TBD) 23 Miscellaneous Materials, Equipment, and Appurtenances 50% % $ 624,961 $ 312,480 Percent of crew costs Remove/dispose of CHW coils, remove unused piping and conduit back to 48 $ 8,000 24 Demolition LS $ 384,000 source Contingency (15%) $ 910,403 Subtotal $ 6,979,753 Bonding (1.5%) $ 104,696 Permitting (0.5%) $ 34,899 Design (6%) $ 418,785 Construction Management (1.5%) $ 104,696 Project Management (1%) $ 69,798 TOTAL $ 7,712,627