C AROIL DAILY STATMENT

Date: 11-mars-18
Client : ENI CONGO S.A. Rig : DP3
Contract : 5000117901/219 - Révision nr 01
au contrat 50001179/212
Daily Statment: Address : B.P. 706
6 Effective date of contract : May 1st, 2015
DDR 125-126 Avenue Général de Gaulle
Pointe-Noire Field : Loango
République du Congo Well : DP 3 - P619
Rate A = Operating rate - Workover
Rate B = Stand-By Rate - Workover
Rate C = Moving Rate - Workover

OPERATIONS A B C
FROM TO TIME
Continu to kill well in reverse circulation, total volume pumped 306 BBLS without any return at surface. Close tubingand squeeze thru annulus 10 bbls of
00:00 03:30 3.5 FSW at 2 BPM-50 PSI. Close casing and squeeze thru tubing 45 bbls of FSW at 0.9 BPM - 1750 PSI. Meanwhile Caroil crew N/U BOP manual and HCR 3.5
valves, manual & hydraulic killing valves side, ongoing. Fill up Koomey oil tank.
03:30 07:00 3.5 Flow check: well stable. Meanwhile Halliburton mud engineer prepare Baracarb viscous pill. 3.5
07:00 08:00 1.0 Crewchange, open work permit and held PJSM. 1.0
08:00 12:30 4.5 Air Liquide teal fix fire firefighting system. 4.5
12:30 13:30 1.0 Pump 2 m3 of LCM vis pill (85 sec), displace same w/ 19 m3 of filtered FSW, no pressure increase notice. 1.0
13:30 14:30 1.0 Wait soacking time. 1.0
Perform attempt of forward circulation at 5 bpm w/ FSW: after 10.5 m3 notice pumping pressure increase to 200 psi, continue to pump till 24 m3, pressure
14:30 15:00 0.5 0.5
stable (TBG pressure 0 psi).
15:00 15:30 0.5 Perform static flow check: wait 15 min, pump at 5.5 bpm, pressure increase to 200 psi after 3 m3. 0.5
15:30 16:30 1.0 Line up TBGin and pump at 1.2 bpm / 1700 psi 4 m3 of FSW. B/O Halliburton forward pumping line. 1.0
16:30 18:30 2.0 PJSM. Close TRSV. Breda remove 3-1/8" 5k x 2" weco Xover flange from swab valve, re-install tree cap and installed BPV type B. 2.0
18:30 19:30 1.0 Noticed gas flowing (without pressure) from well thru XMT, investigate same: gas coming from well. 1.0
19:30 20:30 1.0 Night crew change & JSM. 1.0
Breda installed back 3-1/8" 5k x 2" weco Xover flange on swab valve. Halliburton installed back pumping line to Xover flange, pressure test same at 2500
20:30 23:00 2.5 2.5
PSI.
23:00 24:00 1.0 Bullhead CSGin at 3.3 BPM-100 PSI, total volume pumped 235 BBLS. 1.0

EXTRA : NIGHT PUSHER 1

24.0 0.0
Total = 24.0
24.0 0.0