Вы находитесь на странице: 1из 6

∠PR口「CИ ttaⅣ OFttFttSttEⅣ G五百″ C″ TttCFrSπ 躍 動臣s五 Ⅳ 冒E

CONS蜜 びCπ aⅣ θFttθ ttC“ rttИ R鍋 蘭21//KE■ EttS24」 ⅣrπOttGs 『

ル .【 ル′S彎 0,″ rの α″″ル .FXS′暉 滋″ .Dの


"″ ",MEng,P力
αりCJガ E″ gブ 4θ θr″g Dυ α tttι t Sθ q″ α鍋飢 α″ Cα ttο ′ ぅちSθ αrα ηg
た し物ルθだノ
“ “
の Prα ε θ
″われr ακグ五acttκ たα′Cο κsグ げ Zな物″θ
な乃′S′θ
θ′Cθ 履″κ′
わ′
"″

ABSTRACT: The 27hMay 2006 earthquake has reduced some parts of Jogja and Klaten into rubbles. The
aftermathreconstructionof the housings is confrontedwithvarious localfactors, i.e :1/financial constraints,
2/ the need of durability and earthquake resistance, 3/ the requirement of short construction time, 4/ the pres-
ervation of environment and 5/ the manifestation of the local community self-help. In cooperation with World
Hope International and Lembaga Harapan Sejahtera, PT Berkah Pertama Mandiri (BPM) has successfully
pioneered the construction of l4 (fourteen) units of low-cost earthquake-resistant housings in Grundotempel,
Desa Monggang, kelurahan Srihardono, l@camatan Pundong, Kabupaten Bantul, Jogja. High-Strength Light-
weight Steel Frames with Zincalume Coatings produced by PT Bluescope Lysaght Indonesia hwe beenfabri-
cated and installed. Regarding the five requirements (ocal factors), the construction of the housings has in-
deed demonstrated the competetiveness of the price, the strength and durability of the structure, the very short
construction time (2 days / unit), the active involvement of the local people, and the recycling of the rubbles.

Keywords: Earthquake-Resistant, Lightweight-Steel, Low-Cost, Recycling, Local-Involvement.

INTRODUCTION The reconstruction for Jogja-Klaten earthquake


which has killed more than 5.000 people and flatten-
Natural disasters (earthquake, tsunami, volcanic ned down more than 200.000 housings has to con-
eruption,etc) have successively hit various parts of front at least five local factors, i.e:
lndonesia. Starting with Aceh earthquake and Tsu- 1. Financial constraints and resourcing
nami in 2004, they struck Nias in April 2005. And 2. The need of strength and durability assurance
very recently, they also got Jogja-Klaten regions on of the new structures against possible future
27th May 2006. ln all those disasters, death toll were earthquakes.
high and property losses were huge. For each case, 3. The requirement of short construction time.
the reconstruction approach has its own characteris- 4. The preservation of physical environments.
tics related to its local socio-economic conditions,i.e 5. The need of conducive atmosphere to the
: reconstruction approach for Aceh should be differ- spirit of local community self-help.
ent from ones for Nias, Jogja,etc. ln its effort to meet the peviously mentioned fac-
tors, PT BPM has successfully constructed a housing
model with the following characteristics.
ANALYSIS OF THE SITUATIONS 1. It consists of a house frame (spot foundations,
structural frames, and trusses and roofing
From various field observations, especially in the vi- sheets) which is strong, durable, and quick to
cinity of Bantul and Klaten, the following facts have construct.
been found among the collapsed and the badly dam- 2. The construction encourages local people to
aged residential housings : participate and thus transfer of technology is
l. Those which were collapsed or badly dam- expected to happen.
aged are basically non-engineered buildings. 3. The non structural works are left to the local
2. Among the rubbles, recycleable materials people to suit their needs, flavours and mate-
like bricks, door-leaves, window-leaves, etc rial availability.
are abundant.
3. Human resources, i.e the house owners, are
abundantly available.
HIGH-STRENGTH LIGHT-WEIGHT STEEL (HSLWS) horizontal force which is easily provided
partly by the passive resistance of the soil,
To enable a speedy construction, steel is the an- and partly by the friction of the foundation
swer. Compared to the heavy concrete, steel is much base.
lighter thus attracts much smaller earthquake load 7. The 2.8 meter column of C75.75 profile has
but yet strong and ductile meaning a significant in- 0.8 kN buckling capacity (according to the
crease ofearthquake resistance. Steel is undoubtedly same test conducted by PT Bluescope Steel
superior to either timber or bamboo. The last two Lysaght) based on fixed-free standing ele-
materials mentioned are just not suitable especially ment assumption According to a the same
for the local environment when the need of them is test, if noggings are supplied, the buckling
so excessive. capacity could increase to 2.5 kN. Since the
The light-weight steel used in the construction real total column load is no more than 73 kg
has a teniile strength of 550 MPa or 5.500 kglcm2 (0.73 kN), the column system is undoubtedly
(compared with 300 MPa for the conventional steel). far from instability conditions.
Because of its small thickness (i.e 0,4-1.0 mm) but 8. The key factor for the overall stability of the
high strength, this material is called High Strength structure is the installation of diagonal brac-
Light-Weight Steel (HSLWS) ings at two diametrical corners.(See Fig-2)
To protect this steel, a metal alloy of 55Yo Al +
43.5% Zinc + 1.5% Silicon called ZincalumeR pro- SPECIFICATION OF MATERIALS AND EQUIPMENTS
duced by PT Bluescope Steel is used. The composi-
tion is believed to be optimum based on the exten- ln July 2006, sponsored by World Hope Intema-
sive study by Betlehem Steel USA. Just to mention tional and Lembaga Harapan Sejahtera, PT BPM
some, different compositions like Galvanized Steel Constructed 14 (fourteen) units of low-cost Earth-
(Zinc+O,2Yo Al), GalFan (Zinc+SYo Al) and Alumin- quake proof houses in Grudotempel, Desa Mong-
ized Steel (Al+10% Si) are also available in the mar- gang, Kelurahan Srihardono , Kecamatan Pundong,
ket. The oxidized Al in Zincalume will protect the Kabupaten Bantul, Jogiakarta. The general specifica-
core steel against further corrosion while the zinc tion of the materials is as follows:
will sacrifice it-self to protect the edge of the steel 1. The Umpak was made of concrete with a 40
cut or the scratch.(See Fig-l) cm C75.75 stump halfway immersed. The ten
umpak have a size of 30cm x 30cm x 30cm.
EARTHQUAKE-RESISTAIYT HOUSINGS 2. The strap-beam (elevation +/- 0.00) and the
ring beam (elevation +2.80) are made of C-
More stringent than its predecessor, the recent 75.75 profile (75mm height and 0.75mm
lndonesian Earthquake Code for Buildings (SNI-03- thickness). The length were 7.20 meter and
1726-2002) bases itself on a 500 year return period. 4.80 meter
According to the new code, the housings in Pun- 3. The coloumns (C75.75 x 2.8 m) were spaced
dong, Bantul is exempted from all the clauses within every 1.20 meter.
because of its single story with no more than ten 4- Noggings of 1.2m long C75.75 are installed
people inhabiting. Inspite of that, principles of earth- horizontally in the middle of every panel.
quake-resistant design are applied. They include: 5. Four trusses (Smartruss*; of 4.8m span and
1. Self-weight must be kept minimum by the 300 slope were made of CiS.lS and piaced on
use of HSLWS. top of the ring beam every 2.4 meter.
2. The dead load which consists of roofsheets, 6. Purlins were placed on top of the trusses and
trusses, and halfivay columns is amounted to spaced every 110 cm while the ceiling-
411 kg. battens were installed every 160 cm under-
3. Live load is assumed to be 320 kg which is neath.
equivalent to 5 kg/m2 or to be the weight of 7. The roofsheet was made of the same materi-
5 workers working on top. als(Zincalume-coated) with an effective
4. With l0 columns standing around, each col- width of 760 mm and length of 3.65 m.
umn will (on average) support 41 kg dead length. The sheet was of Custom-Orb cross-
load or 73 kg dead load + live load. section with a thickness of 0.35mm.
5. Based on the Code, theMaximum Base Shear 8. Roof ridge was made of 626mm width x
is found to be : 0.35mm thick forming an angle of 1200 in
V:0.5 x Wt:0.5 x 4l I kg: 206kg the centre.
6. Each column is supported by a spot- 9. A pair of roof grills were installed vertically
foundation ("Umpak") of 30 cm (Length) x to provide air ventilation.
30 cm (Width) x 30 cm (Height). With the 10. Shap-Bracings were installed at two diamet-
base shear distributed evenly among the ten rical corners of the structure. To tighten up
"umpak", each umpak has to resist 21 kg of the bracings, tensioners were used.
10. Install the six column at both ends of the
Table 1. Steel Brace Specification structure. These columns should fix the end
Minimum basic Type of Steel Brace trusses and keep them vertical.
Working loads, kN Strap-Brace Speed-Brace 11. Place the secondary columfls among the
Steel Tension,End
main six columns with its bottoms going into
Fixing,Wrap Around 35-5 5kN 5.5kN the strap-beam while its tops going into the
Splice Capacity ring beams.
Brace to intermediate 055N O.45kN 12. Install the noggings (stiffeners) by consider-
Truss Fixing Capacity
40xl.0
ing the positions and sizes of the windows
Dimensions (mm) 25xl.0
and doors.
Nail-size requirements 10-16x16 10-16x16*
* Wafer/ Hex tck selfdrilling screw
13. Place the four trusses on top of the ring
beams and temporarily shore them. Secure
their supports on top of the main columns by
All the cquipments and tools needed for the con―
using L-brackets.
struction include:
14. Four Purlins spaced at 110 cm are installed
1.Hand― held drill with reverse rotation to work on each side of the slopes and secured by
with self― tapplng screw system
shoe-brackets-
2. Cutting wheel or scissors tQ cut.
15. Install the two ceiling battens just under the
3. Other standard tools like roll¨ meter, leveler,
bottom chords of the trusses at 1.6 m inter-
cable,sting,ctc.
vals. (See Fig. 5)
16. Stiffen the four corners by diagonal bracings
FABRICAT10N PROCESS screwed on the comer ring beams.
17. Attac,h four pairs of diagonal bracings at the
ne choice Of 4.80m x 7.2Clm slze hollsing was
comer panels using strap plates. Use tension-
bascd on the minimuln/basic need ofa family of4-
ers to tighten up the diagonal bracings.
6.The l.2 m module was takcn in line with the 18. Install the roofsheets and its ridges.
available standard sレ es of materials IIll the IIlarket_
l9.Install the ventilation grills at both ends of
The slope ofthe roofwas taken 30° to provide good
the strucfure
circulation of fに sh〔 壼 which is most crllcial for
20. Add some anchors to the panels which are to
metal roo■
be covered by brickwalls (See Fig.6 & Fig.7)
h fab五 cation process of this low― coSt earth―
quakc resistant housings can be described as fbllows.
CONCLUSIONS
1.■ e locJ people prepareぬ e ten holes for the
ullnpak foundation.The hole size is approxl―
Regarding the five requirements (local factors), the
mately 40 cm x 40 cln x 30 cln,and spaced at
construction of the housings has indeed demon-
a dislレ nce of2.4 1netcr.
strated the competetiveness of the price, the strength
2. The hole base is then compacted and layered
and durabilrty of the structure, the very short con-
with 5-10 cln Sand.
struction time (2 days lunit), the active involvement
3.The ten``Ump〔 よ"are put into their holes and
of the local people, and the recycling of the rubbles.
可 uSted fOr theむ vOttcd alld hO五 zontal posi―

mttPlP雷 電臨謝織ギ背器 ACKNOWLEDGEMENT


above are done together with the local people。
We express our sincere gratitude to :
(See Fig-3) 1. World Hope International and Lembaga
4. Proflles are cut into eleIInents according the
Harapan Sejahter4 who have given financial
prcparcd cutting list. .
support.
■ e four ullits ofTruss are then assembled ac―
5。

cording to lhe prepared working sheet.


2. Mr.Gary Newby @T Bluescope-Lysaght),
who has given many technical supports.
6.The strap― bealns arc notched every 2:4 m and
3. Mr. kosa Wahyudi,ST,MT (PT Bluescope
then placed on top of the `ulnpak'. ■ e
Lysaght Indonesia), with whom structural ef-
smmps Ofthe `umpak' should stand and go
ficiency matters have been discussed.
through the notchcs。 (SCe Fig… 4)
7.Colums arc thcn attached to the`llmpak'by
4. Mr. Sumamo and his fellow neighbours in
Grundotempel-Pundong-Bantul, who have
spccial boxing systeln, positioned and ad…
justed for their plumbness to both directions,
demonstrated their enthusiasms about the
project.
8.Check thc right angle ofthe structure by tcm―
porarily shoring the follr colu― s at thc cor…
ners.
9. hstall thc■ ■g bealns with downward position
REFERENCES
Dttid Trisnohad」 antO,2006.Coatcd Flat Steel,Product lntro‐
ductions and Applications as building SolutiOns..

SN1 03-1726-2002, 2002. Tata― Cara Perencanaan Ketahanan


Gempa Untuk Ruinah dan Gcdung.

APPENDⅨ

Figure la Anti-corrosion Mechanism


Figure lb Sacrificial Reaction as an Anti-
corrosion Mechanism
Figure2 Strap-Bracings and Tensioners
Figure 3 Community Self-help Demonstrated
during the Project Construction
Figure 4 : Umpak foundation,its stump and the
boxed C75.75 Column
Figure 5 The Frames and Trusses Erected
Figure 6 Brick-Walling and Ventilation-Grill
Figure 7 The Reinstallation of Doors and Win-
dows

│ヽ OFOSi
trir
'.. 't' I .,,

illenrngkap
LI:1,.,.,iイ に ハl llM= 'I' ,:r: .it,
│ナ i..
[iloktrorr yang
rlik:pas olch
L t:r,
lirrc, sclrirri;qir
Borc;rk:;t lr:lrrlr rl.rlrrrlLt lclrilr k;rtotlik (.)
ti;rtr rrr:lr1r,r:[,rl rlarr lr:bih srrlit

´
(11okti oll1ly・ n brlrr:irkr; i
,,.
[..ritir-;rtr Iitlt: Reaksi Sacrificial′
Ar o ',:., Pengo「 banan Diri
: :! :, i. ll I Y., i! t t:,1

Fig. la. Anti-corrosion Mechanism Fig. lb. Sacrificial Reaction as an Anti-


corrosion Mechanism

Fig. 2. Strap-Bracing and Tensioners Fig. 3. Community Self-help Demonstrated


during the Prgject Construction

鰈辟 勒


環 │

彦¶
〆 ・

=﹁﹁∃

Fig。 4.Umpak fomdation,itssmp andthe Fig. 5. The Frames and Trusses Erected
boxed C 75。 75 Colllmn
i

Fig. 6. Brick-Walling and Ventilation-Grills Fig.7. Reinstallation of Doors and Windows

Вам также может понравиться