Академический Документы
Профессиональный Документы
Культура Документы
Planning:
Organizing
Implementing
Controlling
9. Track, monitor and control progress using project management
tools and techniques.
10.Compare projected versus actual results. Update project plan.
Repeat Implementing.
Closeout
1) Resources
2) Time
3) Money and most importantly
4) Scope.
1) Resources
People, equipment, material
2) Time
Task durations, dependencies, critical path
3) Money
Costs, contingencies, profit
4) Scope
Project size, goals, requirements
However, the fourth element is the most important and it is the first and
last task for a successful project manager.
• Tasks
Duration, resources, dependencies
• Schedule
Tasks, predecessors, successors
• CriticalPath
Changeable, often multiple, float
o Task Management:
Any project can be broken down into a number of tasks that have to
be performed. To prepare the project schedule, the project manager
has to figure out
Manage Resources:
The project manager must also manage the equipment used for the
project and the material needed by the people and equipment
assigned to the project.
o People
Project employees, vendor staff, subcontract labor etc.
o Equipment
Cranes, trucks, backhoes, other heavy equipment or
Development, test, and staging servers, CD burners or
Recording studio, tape decks, mixers, microphones and speakers
etc.
o Material
Concrete, pipe, rebar, CD blanks, computers, jewel cases,
instruction manuals etc.
• Costs
Estimated, actual, variability
• Contingencies
Weather, suppliers, design allowance
• Profit
Cost, contingencies, remainder
o Each project task will have a cost, whether it is the cost of the
labor hours of a computer programmer or the purchase price of a
cubic yard of concrete.
o In preparing the project budget, each of these costs is estimated
and then totaled. Some of these estimates will be more accurate
than others.
o When the estimated cost of an item is uncertain, the project
budget often includes a design allowance.
o This is money that is set aside in the budget "just in case" the
actual cost of the item is wildly different than the estimate.
o Unusual weather or problems with suppliers are always a
possibility on large projects.
o Companies usually include a contingency amount in the project
budget to cover these kinds of things.
o So a project budget is composed of the estimated cost, plus the
contingency and design allowance, plus any profit.
o The project manager's job is to keep the actual cost at or below
the estimated cost, to use as little of the design allowance and
contingency as possible, and to maximize the profit the company
earns on the project.
o To maximize your chances of meeting your project budget, meet
your project schedule.
o The most common cause of blown budgets is blown schedules.
Meeting the project schedule won't guarantee you will meet the
project budget, but it significantly increases your chances.
o And above all, manage the project scope. Don't allow the project
scope to "creep" upward without getting budget and/or schedule
adjustments to match.
Project Planning Steps
Project planning is part of project management, which relates to the use of
schedules such as Gantt charts to plan and subsequently report progress
within the project environment.
1) Define the project scope
A goal, target, to be achieved by a certain time, i.e. The Boundary of the
project
WBS Levels:
L1 Project
L2 Sub – Project
L3 Task
L4 Activity / Work Package
L5 Element / Level of effort.
The summations of all elements in one level must be the sum of
all work in the next lower level.
o Determine Dependencies:
The logical dependencies between tasks are defined using an
activity network diagram that enables identification of the
critical path.
5) Assemble Project Team Get the people on team together and start
a dialog
6) Identify the risks may occur in projects and make a note on how to
overcome the these risks
o Technology risks.
o People risks.
o Organisational risks.
o Requirements risks.
o Estimation risks.
7) Make Gantt Chart For scheduling tasks
A Gantt chart is a type of bar chart that illustrates a project schedule
Gantt charts illustrate the start and finish dates of the terminal
elements and summary elements of a project.
Terminal elements and summary elements comprise the work
breakdown structure of the project.
Some Gantt charts also show the dependency (i.e., precedence
network) relationships between activities.
10) At this stage, the project plan may be optimized to achieve the
appropriate balance between resource usage and project duration
to comply with the project objectives.
11) Create Your Baseline Plan Get feedback on your preliminary plan
from your team and from any other stakeholders. Adjust your
timelines and work schedules to fit the project into the available
time.
1.Time
2.Resources
3.Cost
4.Performance Criteria.
2nd - Phase:
To monitor actual ongoing operations to ensure that
objectives, short-term and long –term are met.
3rd - Phase:
To improve activities.