Академический Документы
Профессиональный Документы
Культура Документы
net/publication/267157050
CITATION READS
1 86
3 authors, including:
Gerhardus J Keyter
Aurecon Group
19 PUBLICATIONS 33 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Gerhardus J Keyter on 26 August 2015.
Introduction
The Ingula pumped storage scheme is being constructed in the Drakensberg escarpment
between the Free State and KwaZulu Natal provinces, South Africa. The powerhouse
complex comprises two main caverns as well as other galleries, tunnels and shafts.
This paper provides details of instrumentation and monitoring work carried out in
the power caverns during construction and monitoring results are compared with those
predicted during design. Excessive overbreak in a side heading when excavating the
machine hall crown resulted locally, in undue roof deformation. Remedial actions
taken to stabilize the excavation in this area are discussed.
The high pressure waterways and underground powerhouse lie under a prominent
mountain ridge off the escarpment. The main power caverns are located at a depth of
almost 400 m below ground level, about halfway between the two reservoirs.
The machine hall is approximately 184 m long with a span of 26 m. The crown,
23.5 m above operating floor level, has a double curvature profile with a relatively low
span : height ratio of 2.5. The cavern width reduces to 24.6 m below crane beam level.
The turbine pits extend another 27 m below operating floor level.
The adjacent transformer hall has a 19 m span, a height of 21 m and a length of
approximately 176 m, with a cable and pipe gallery on one side running the length of
the cavern and extending another 6 m below operating floor level.
606 G.J. Keyter et al. / Instrumentation and Monitoring During Construction of Ingula Power Caverns
2. Geology
Faults in the project area generally trend E-W and ESE-WNW with a further two
sets of small displacement faults striking NW-SE and NE-SW. A sub-vertical, sheared
and faulted dolerite dyke with strike orientation NNW-SSE intersects the power
caverns and main access tunnel at an oblique angle. A normal fault zone comprising
slickensided, striated joints, infilled with calcite and mylonitic material, was intersected
in access tunnels near the powerhouse with a few of these fault planes intersecting the
far eastern end of the transformer hall. A number of bedding parallel shears have also
been identified in boreholes and underground excavations in the powerhouse area and
surrounds, three of which are located in and above the machine hall crown. However,
there are no known seismically active faults in the immediate project area. The Tugela
Fault which follows the boundary between the Kaapvaal Craton and the Namaqua
Province in this region, is located some 50 km to the south.
G.J. Keyter et al. / Instrumentation and Monitoring During Construction of Ingula Power Caverns 607
Initial estimates of the support required in the Ingula power caverns were based on
precedent experience. The final support design was based on a detailed evaluation of
all available geological and geotechnical information followed by numerical modelling
using UDEC, Phase2 version 7 and FLAC3D [3, 4]. The convergence of different
points located on the crown and sidewalls of the main power caverns was estimated on
the basis of the results of this modelling work, for the anticipated excavation sequence
as well as specified timing of support installation.
50m
40m
50m
50m
25m
25m 25m
25m
25m 20m
20m 20m
13m
13m 13m
45°
13m 20m
20m
13m
6.5m
6.5m 6.5m 10m
6.5m 10m 10m
45°
6.5m 10m 10m
25m 25m 5m
5m 5m
13m 13m 5m 5m
6.5m 6.5m
10° 20m 20m
10m 10m
5m 5m
Transformer
Machine Hall Hall 5m 10m 20m
0 1m 2 5 10 15
N Decreasing convergence
Dolerite dyke
Less than expected convergence has been noted to date on cavern centre line, possibly
due to permanent ground anchorages in the roof being installed closer to the face than
originally designed. Convergence measured in the cavern side headings are nearer to
that predicted during design as shown in Figure 4. However, in October 2009,
overbreak occurred along a bedding shear plane in one of the machine hall side
headings, see Figure 5. The overbreak developed over 3 days in as many blast rounds
in this heading and increased to more than 2 m beyond the theoretical excavation line
by the third blast. Increases in anchor loads were noted in load cells and a jump in
convergence was noted in MPBX readings in the cavern crown. By then, cracking of
shotcrete developed in the ‘brow’ in the roof as shown in Figure 4. With primary
support rock bolts already installed up to the face of the side heading at that point in
time, all blasting work in this heading was stopped and the following remedial action
taken in the affected area: All rock bolts already installed were full column grouted; all
cable bolts were installed up to the face and grouted up; a layer of steel fibre reinforced
shotcrete was applied over the area of cracked shotcrete followed by a layer of
weldmesh reinforced shotcrete; permanent cable anchors were installed closer to the
side heading face; and voids behind the cracked shotcrete were grouted to ensure good
contact between the shotcrete and the rock substrate. The monitoring frequency was
also increased to check the adequacy or otherwise of the above remedial measures;
these measures successfully stabilized the roof in this area.
6. Acknowledgements
This paper could not have been published without permission from the client, ESKOM,
and the support of the Braamhoek Consultants Joint Venture (BCJV). The monitoring
results presented in this paper are based on regular readings of instruments and
presentation of data as prepared by the main contractor for construction of the
underground works, CMI JV, as submitted to the BCJV site supervision team.
610 G.J. Keyter et al. / Instrumentation and Monitoring During Construction of Ingula Power Caverns
150 1220
WARNING LEVEL
ALARM LEVEL
Machine Hall Side Heading Convergence (mm)
75 1190
60 1184
45 1178
30 1172
Expected
15 Convergence 1166
0 1160
First bench excavated
As-built profile
Bedding shear
References
[1] H. J. Olivier, A new engineering-geological rock durability classification, Engineering Geology, Vol. 14
(1979), 255–279.
[2] G. J. Keyter, M. Ridgway and P. M. Varley, Rock engineering aspects of the Ingula powerhouse caverns,
6th International Symposium on Ground Support in Mining and Civil Engineering Construction,
SAIMM (2008), 409-445.
[3] G. J. Keyter and P. M. Varley, Design of the Ingula powerhouse caverns: General design considerations,
SANCOT Seminar, SAIMM, Ladysmith, South Africa, 2008.
[4] G. J. Keyter and P. M. Varley, Ingula pumped storage scheme: Excavation and support of the main
powerhouse caverns, Braamhoek Consultants Joint Venture, Construction design brief – Main
underground works, 2010.
[5] Civil Engineering and Building Structures Standards Policy Committee, British Standard Code of
Practice for Ground Anchorages, British Standards Institution, London, 1989.