PR for GPS time synchronization to be release, PR no on PR register,tell Santosh Sahu sir to release
Tower AC 2 nos to be shifted from store issue section, tell Santosh Sahu sir for reservation slip
CO analyser room follow up with puspendra sir
Opacity DT DR value adjustment
TG2 HP heater shell pressure transmitter to be taken in line
SOX analyser room internal painting on progress
DCS new OPU UPS power supply cable trace out and socket connection
DCF 1/6 weigh feeder signal connection with DCS
DCS back up and memory free from OPU 6
UPS signals (output current and voltage) follow up with emerson
WSB VFD signal cable ready for commissioning,service engineer may come on 18th Jan
New sample cooler connection for SWAS
SWAS service engineer will reach on 16 th Jan for 4th qtr visit, pH solution and dry panel readyness
Unit-2 sonic horn checking work
DCF area VFD LCP JB covering, Unit-2 UPDB panel and load cell controller covering
Bag filter DP switch and manometer cleaning work to be done
CHP all belt PCS, BDS and ZSS cleaning and PCS rope replacement as discussed
New room for instrument servicing work in back side of I/O room
SOX analyser room light connection, follow up with Santosh Sahu sir
BC1 drop test after taringwork, follow up with R N sahu sir
Daily PM work, printed hard copy to be signed from shift manager as earlier done