Вы находитесь на странице: 1из 3

Guidelines for using epoxy-coated strand

Epoxy-coated strand serves as a corrosion inhibitor in harsh conditions

C
odes for designing prestressed external post-tensioned systems, and coating. ASTM A 882-92 requires that
concrete structures provide cable stays. The grit-impregnated grit-impregnated, epoxy-coated
high levels of corrosion resis- type is used in bonded pretensioned strand be capable of withstanding
tance that result in economical, and post-tensioned systems. 150° F without reducing the bond
durable systems. Since 1958, when the Notwithstanding the coating thick- transfer properties.
American Concrete Institute pub- ness tolerance specified in ASTM A Tests on epoxy-coated strand sam-
lished “Tentative Recommendations 882, epoxy-coated strand is available ples provided these results:
for Prestressed Concrete,” require- with a less-variable coating thickness. • Detensioning of epoxy-coated
ments for prestressed concrete have Reduced variability may need to be strands should be performed at less
included provisions for “elements specified to ensure compatibility with than 160° F.
exposed to weather or corrosive certain stressing hardware. Epoxy- • Bond could be lost at tempera-
atmosphere.” coated-strand manufacturers should tures greater than 165° F. A bond loss
Initially, design re q u i re m e n t s be consulted. is an end slip greater than 0.01 inches.
intended to enhance durability only Strand also is available with the It is important that designers con-
limited allowable concrete tensile interstices between individual wires sider the following temperature
stresses in service. In the 1970s, filled with epoxy, preventing migra- effects:
increased concrete cover require- tion of corrosive chemicals by capil- • For pretensioned applications
ments were introduced. Today, pre- lary action or other hydrostatic forces. where accelerated curing techniques
stressed concrete is recognized as a This strand should be specified when are employed, the temperature of con-
durable structural system with low contaminants or moisture can enter crete surrounding the strand at the
maintenance costs. the ends. Specifications for this time of prestress transfer should not
The effect of exposing prestressed “filled” strand are presented in ASTM exceed 150° F, and the concrete tem-
concrete elements to harsh environ- A 882, Supplement No. 1. perature should be falling. The epoxy
ments has been recognized and cor- Producing filled strand re q u i re s coating will not be impaired if this
rective measures identified. While unstranding, coating, and restrand- recommended temperature is exceed-
using additional corrosion-protection ing. This coating process should not ed during the curing cycle.
systems is not appropriate for all pre- affect the strength of the epoxy-filled • Concrete temperatures under sus-
stressed construction, it may be justi- strand. tained fire conditions likely will be
fied for systems where severe expo- considerably higher than the epoxy
sure is anticipated. The consequences ELONGATION can withstand, which can result in the
of reinforcing steel corrosion in con- Elongation for coated strand may be loss of bond between the tendon and
crete structures under these harsh calculated in the same manner as for the concrete. In pretensioned concrete
conditions may be significant in terms uncoated strand using the load-elon- applications, the fire endurance of a
of structural safety and economic gation data supplied by the manufac- member with epoxy-coated strands
impact. turer. Elastic modulus values of coat- will be negligible unless additional
Epoxy-coated prestressing strands ed strand are based on the load-elon- bonded reinforcement (prestressed or
can provide the needed corrosion gation tests after coating. nonprestressed) is provided. Unlike
resistance. While most prestressed Tests of coated low-relaxation most building structures, bridge
concrete structures will not require strand have shown that relaxation can structures may not require a specific
epoxy-coated strand, stru c t u re s be up to two times that of uncoated fire-resistance rating, but an evalua-
exposed to aggressive corrosion con- strand. Manufacturers recommend tion of the likelihood of vehicle fires
ditions may benefit when epoxy-coat- that the stress-relaxation component and subsequent effects of elevated
ed strand is used. of the losses be figured by doubling temperatures should be performed.
the relaxation loss calculated for
PRODUCT DESCRIPTION uncoated strand. The manufacturer CUTTING
Epoxy-coated strand is 7-wire pre- should be consulted for suitable relax- The preferred method of cutting
stressing strand with a 25- to 45-mil ation-loss values, which may vary epoxy-coated strand is with an abra-
organic coating. Two coatings are depending on the nominal diameter sive saw. When epoxy is burned in the
available: a smooth type and one with of the strand. presence of sufficient oxygen, it
grit particles embedded in the sur- In bonded prestressed concrete results in harmless carbon dioxide and
face. The smooth type has low bond applications, the prestressing force is water. Insufficient oxygen may create
characteristics and is intended for use transferred to the surrounding con- harmful carbon monoxide. If torch cut-
in unbonded post-tensioned systems, crete through the grit in the epoxy ting is used, it should be performed in
HANDLE STRAND WITH CARE include a maximum temperature
allowed in the vicinity of the chuck.
Do not allow the wedges to unseat
Epoxy-coated strand requires spe- should be examined for damage. If
during the stressing operation. Epoxy
cial handling procedures to avoid damage is observed, the coating
in the wedges will be highly com-
damage to the coating and, where should be repaired in accordance
pressed; any wedge movement may
the grit-impregnated type is being with the manufacturer’s instructions
cause the epoxy to debond from the
used, damage to adjacent equipment or the strand should be discarded.
strand, resulting in anchorage failure.
due to the grit’s abrasive action. Unlike packs of uncoated strand
Anchorage seating losses for epoxy-
Except for short lengths, epoxy- that dispense strand from the center
coated strand are typically more than
coated strand is shipped on reels. of the pack, epoxy-coated strand is
for uncoated strand. The difference
The strand should be covered and dispensed from the reel’s circumfer-
often is large enough to be significant.
stored on the reel to afford maxi- ence. The reel needs to be mounted
Seating losses are approximately 1
mum protection; the covers should on a stand such that the reel rotates.
inch at the live-end anchor and
be moisture-resistant and capable of The strand can be pulled off the reel,
approximately 3⁄8 inch at the dead end
shielding the strand from sunlight and a braking device should be used
(after initial preload). If information
and the environment. Except for the to control rotation. The strand
from prior use or from a strand sup-
filled type, strand ends should be should not be dragged across sur-
plier is unavailable, tests should be
protected after each partial use to faces that could damage the coating
conducted to confirm seating-loss val-
avoid the ingress of moisture and and, in the case of grit-impregnated
ues.
harmful contaminants. epoxy-coated strand, cause surface
Workers should wear protective damage.
PRETENSIONED APPLICATIONS
gloves while unreeling grit-impreg- Specific handling instructions are
Because the overall diameter of
nated strand. When unreeling, the available from the strand supplier.
epoxy-coated strand is 50 to 90 mils
condition of the epoxy coating
greater than uncoated strand, it may
be necessary to enlarge the holes in
a well-ventilated area. Water may be Hammering wedges or power seating the stressing abutment. Holes or slots
used to extinguish flaming. may reduce the anchor set loss, but should be chamfered to prevent coat-
the procedure should be tested before ing damage.
INSTALLATION AND STRESSING using it on a regular production basis. Because strand with the grit-
Bite-through wedges specifically In pretensioning, the stress or force impregnated coating should be used
made for use with epoxy-coated induced in the tendons should be in pretensioned applications, abrasion
strand should be specified. Chucks determined by monitoring the of the stressing abutment and form
designed for uncoated strand should applied force and, independently, by end plates may occur. Over time, this
not be used. Special anchors and jack measuring the tendon elongation may result in oversized holes and
grippers are required for coated from initial tension to required ten- possibly mislocating tendons. Each
strand because of the larger diameter sion. The initial tension—usually producer should adopt a quality-con-
and nature of the coating. Conversely, 1,500 to 2,500 pounds—is sufficient to trol procedure for checking strand
stressing hardware designed for coat- remove slack in the strand. An initial templates at the abutments and form
ed strand should not be used with tension of less than 0.06 fpu (ultimate ends.
uncoated strand. tensile strength of strand) should not To cast short members in beds
Anchor wedges and jack jaws severely damage the coating, and the where the stressing abutments may be
should be inspected to ensure that the wedge may be relocated and pulled to 100 to 200 feet apart, it is common to
serrations are intact and free of for- the final stress without cleaning or use lead strand and splice chucks.
eign material. Wedges must be thor- replacing. Lead strand may be reused for many
oughly cleaned and inspected before Final stressing of epoxy-coated casting cycles, minimizing wasted
each use. strand should be a single stroke oper- strand. Splice chucks are used on
For uncoated strand, it is unusual for ation, because after one jacking cycle, uncoated strand, requiring that the
the wedges or chucks to slip during the wedge jaws can become contami- epoxy coating be stripped from the
stressing. At low stress levels, howev- nated with epoxy particles. A second end of the strand. Specially designed
er, slip may occur on coated strand due jacking cycle without cleaning the epoxy-coating stripping machines are
to a low radial force at the chuck and grips can result in a loss of gripping available.
the bite-through jaws’ inability to pen- action. If a second jacking cycle is Rollers in contact with draped
etrate the coating fully. unavoidable, the wedges must be (depressed) strands should be smooth
In the vicinity of the wedges, strand replaced or thoroughly cleaned before and allow for increased strand diame-
should not have been previously reseating. ters. If standard rollers are used, the
heated, damaged, patched, or gripped If a low final stressing force must be epoxy will be distorted and damaged.
because anchorage failure may occur. used, the strand supplier should be After installation in the casting bed,
Wedges should be aligned around the consulted for special stressing proce- the condition of the epoxy coating
strand and seated by light tapping. dures. These procedures should should be re-examined for damage. If
damage is found, the coating should be protected within eight hours after “Tentative Recommendations for
be repaired according to the manufac- final cutting. Prestressed Concrete,” Journal of the
t u re r’s instructions or the strand American Concrete Institute, January,
should be discarded. CABLE STAYS September, and December 1958, Part II,
Detensioning gradually should Cable stays used for bridges or Proceeding V 54.
transfer the force in the strand to the other structures are similar to post-
Donald W. Pfeifer, J. Robert Landgren,
surrounding concrete. If a torch is tensioning tendons in that they con-
and Alexander Zoob, “Protective Systems
used, heat should not be applied clos- sist of the following elements:
for New Prestressed and Substructure
er than 6 inches from where a sound • Prestressing steel (parallel wires,
Concrete,” Report No. FHWA/RD-
epoxy coating is required. An abra- strands, or bars)
86/193, Federal Highway
sive saw should be used to trim the • A cementitious grout or other
Administration, Washington, D.C. 1987.
ends of the strands. material that fills the void between
the steel and the encapsulating Walter Podolny Jr., “Corrosion Protection
POST-TENSIONED APPLICATIONS sheathing of Prestressing Steels,” Vol. 2, FIP XI
For external post-tensioning sys- • Anchorages International Congress on Prestressed
tems, where the tendons are located Epoxy-coating of individual strands Concrete, Hamburg, Germany, June 4-9,
on the outside of the member, avoid provides both the temporary and per- 1990.
sharp curves in the tendon path. manent corrosion protection and
Where tendons pass over a deviation obviates the concern for aggressive W.F. Perenchio, J. Francek, and D.W.
point, it may be necessary to provide corrosion agents reaching the strand Pfeifer, “Corrosion Protection of
cushioning material to avoid abrasion due to cracked grout and potential P re s t ressing Systems in Concrete
of the epoxy coating. sheathing cracks. So as not to compro- Bridges,” National Cooperative Highway
For internal post-tensioning sys- mise the system’s effectiveness, atten- Research Program, Report 313, February
tems, using galvanized metal duct is tion must be paid to anchorage 1989, Transportation Research Board,
not recommended with epoxy-coated details. Special wedges are required National Research Council, Washington,
strand. Severe epoxy abrasion will that bite through the coating and grip D.C.
occur during the stressing operation the prestressing steel. The strand’s cut
as the strand comes in contact with end must be sealed unless filled Fernando E. Fagundo and Daniel
the spiral duct seams. Polyethylene strand is used. Richardson, “Bond Slip of Epoxy-Coated
duct is recommended. Because the effective tension in Strands (ECS) at Elevated
Anchorages used with epoxy-coat- many cable stays, at the time of instal- Temperatures,” University of Florida,
ed strands should be designed and lation, is not sufficient to seat the March 1991.
tested specifically to accommodate wedges all the way to the anchor
Philip J. LeClaire, “The Effect of
the coating. Because wedges used for chuck body, a specific procedure must
Temperature on the Bond Strength of
epoxy-coated strand are larger in be employed. This procedure must be
Epoxy-Coated Prestressing Strand,”
diameter than those for uncoated designed so that there is no longitudi-
Master of Science degree thesis,
strand, anchorage dimensions will nal motion of the wedges with respect
University of Wisconsin-Milwaukee,
increase. Determine what the ade- to the strand after the wedges’ teeth
August 1991.
quate clearances and edge distances begin to penetrate the epoxy surface.
between the anchorage and adjacent In cases where the load in the cable Fernando E. Fagundo and Daniel
concrete surfaces will be. must be adjusted after installation, Richardson, “The Effect of Steam Curing
St ressing should be undertaken such adjustments should be made and Sustained External Elevated
with anchors or chucks designed for without unseating the wedges. This is Temperatures on the Bond-Slip
use with epoxy-coated strand. Give normally accomplished by using Performance of Epoxy-Coated Flo-Bond
attention to the design of pulling (or shims or threaded anchorages with Strands (ECS),” University of Florida,
seating) wedges and wedge seating ring nuts. Where helical spacers are October 1991.
devices. Multiple gripping for long used inside the sheathing, the spacer
tendons is possible when equipment wire should be epoxy-coated to avoid “Design for Fire Resistance of Pre-
designed for the purpose is used. fretting fatigue. c a s t / P re s t ressed Concrete,” Second
Proper lubrication always should be Edition, MNL-124-89, Precast/
used. Information for this article was provided Prestressed Concrete Institute, 1989.
The patching and protective com- by the Pre c a s t / P re s t ressed Concrete
pound should be a two-part epoxy Institute’s Ad Hoc Committee on Epoxy- “Guide Specification for Design and
compatible with the fusion-bonded Coated Strand. Construction of Segmental Concrete
strand coating. The epoxy-coated- Bridges,” 1989, American Association of
strand supplier should be consulted State Highway and Transportation
regarding materials and application REFERENCES Officials, Washington, D.C.
methods. Exposed strand ends should ACI-ASCE Joint Committee 324,

PUBLICATION #J940501A, Copyright © 1994, The Aberdeen Group, All rights reserved

Вам также может понравиться