JIS F 5609-1996
Shipbuilding – Forged steel 20K reflex type water gauges with cocks for boilers −
Explanatory note
This explanatory note accounts for the matters specified in the text, and related matters, but is not part of
the Japanese Industrial Standard.
1. Purpose of constitution As for a standard of cocks for marine boilers, there were previously JIS F
5602 (Bronze 20kg/cm2 type water gauge cocks for boilers) and JIS F 5603 (Bronze 20kg/cm2 water gauge
drain cocks for boilers) (abolished November 1, 1967). These cocks are however rarely used for the reason
that water easily leaks through their packings, etc. and the products made by specialized water gauge
manufacturers are mostly applied.
In this case, modifying these JIS cocks might be possible, but this standard is constituted by the support
of major opinion that a new standard should be prepared with the cooperation of these specialized manufacturers,
taking account of the actual circumstances where their products are widely accepted.
TO TITLE
F 5609: 1996 Explanatory note
(7) CuP1-0 in JIS H 3101 (Copper plates), a reference standard for ○ 27 ~○
31 gaskets, is revised into TCuP1-0
3. Outline and contents of the standard This standard specifies the shape and installation dimensions
of components of water gauges for marine boilers. It is compiled to include water gauge bodies specified in
JIS B 8213 (Boilers – Reflex type water gauges) and JIS B 8215 (Boilers – Transparent type water gauges) for
the convenience of users, in addition to cocks and valves for water gauges.
(1) For a cock plug, an asbestos laminate product without taper and with a metal reinforcement ring used for
a sleeve packing is used. It has the structure that packing tightness can be adjusted by operating a
tightening nut from below.
(2) Among materials in Attached Figure 2 (text), the standard for part number ○ 25 sleeve packing and ○ 26
packing is JIS F 7102 (Shipbuilding-Piping system in machinery space-Application standard for gaskets
and packing). Their shapes and dimensions are as shown in Figs. 1 and 2 (explanatory note) below.
Fig. 1 (explanatory note) Sleeve packing Fig. 2 (explanatory note) Gland packing
Unit: mm
Detent
Full layer
reinforcement ring
(3) The cock body is separated from the gauge holder to facilitate its removal.
(4) It is difficult to provide the steel balls for blockage at the upper cock structure of water gauges.
According to the results of a user questionnaire, there are many opinions that they may only be provided
at the lower cock structure, and this standard follows them.
(5) The handles shall be a 90° full-open lever type, and both cocks can be opened and closed individually
and easily operated from below.
Remark The caliber of all cocks shall be 10mm including the drain cock. ASME specifies the caliber to be
1/2″ PIPE SIZE. Studies are done on the possibility of adopting this value. However 1/2″ PIPE
SIZE means the actual caliber of 16.1mm, leading to a very large entire structure including the cocks.
10mm is therefore adopted here.