Вы находитесь на странице: 1из 8

Design Data 23

Low Pressure Air Testing of Sewers


Acceptance tests are included in sewer contract some areas, the trench may be flooded to simulate
documents to assure the necessary combination groundwater conditions for the infiltration test. In
of good workmanship and materials is obtained the exfiltration test, the sewer line is filled with wa-
during construction of the project. This Design ter and the amount of water loss is measured. The
Data describes the application and limitations of exfiltration test can be used if the groundwater lev-
low pressure air testing of installed concrete pipe el is less than two feet above the crown of the pipe
sewers and provides information and guidelines at the highest elevation of the sewer. Procedures
for proper application of the test and interpretation and test criteria for water infiltration and exfiltration
of results. tests of concrete pipe sewer lines are prescribed in
No correlation has been found between air loss ASTM C969.
and water leakage from sewers. Although such In the low-pressure air test, the sewer line to be
relationships exist for an orifice of known dimen- tested is plugged at both ends, air is introduced at
sions, in concrete sewers, the orifices are gener- low pressure into the plugged line and the amount
ally of capillary tube size, or smaller, and surface of air loss during a specified time period is mea-
tension may stop the flow of water while dry air may sured. Test procedures and criteria are prescribed
pass through the openings. Experience has dem- in ASTM Standard C924, Testing Concrete Pipe
onstrated this and has shown a sewer line pass- Sewer Lines by Low Pressure Air Test Method.
ing the air test should pass the water infiltration or This Design Data discusses the development and
exfiltration test specified in ASTM C969, Practice use of low-pressure air test.
for Infiltration and Exfiltration Acceptance Testing
of Installed Precast Concrete Pipe Sewer Lines. It Air Test Development
should also be noted that there is no relationship The low-pressure air test was developed to de-
between the criteria and results of low-pressure air tect damaged pipe or improper jointing and is a test
testing of sewer lines and that of low-pressure air to determine the rate at which air, under pressure,
testing of individual joints. escapes from an isolated section of sewer. Initially
water testing, the air rest is now a common method
General of testing installed sewer lines for acceptance by
Precast concrete pipe is plant tested prior to demonstrating the integrity of the pipe and joints
acceptance and delivery to the job site. Since plant and a quality of construction methods.
leakage testing is a check on the pipes perfor- Due to the physical differences between air and
mance, field leakages test demonstrates the qual- water, and the difference in behavior of gases and
ity of construction procedures and integrity of the fluids under pressure conditions, there is no direct
installation. The leakage tests applicable to pipe correlation between air loss and water infiltration
installations are the water infiltration, water exfiltra- and exfiltration. In most cases the air test is a “go”
tion and low-pressure air tests of the sewer line, or “no go” situation, and, if the sewer passes the
and individual joints. test, it should perform satisfactory under an infiltra-
In the infiltration test the amount of water leak- tion or exfiltration test. In the event of failure to pass
age into the sewer line is measured. This test is the air test, the sewer line should be subjected to a
generally applicable only when the groundwater water infiltration or exfiltration test as prescribed by
level is a minimum of two feet above the crown of ASTM C696 before rehabilitation or reconstruction
the pipe for the entire length of the test section. In is considered.

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 1


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
Method
VL
ASTM C924 specifies the test method, criteria TT = (2)
and procedures, and limits the size of the pipe that QL

can be tested to 4-inch through 24-inch diameters. The volume of air loss is a function of the vol-
The lower limit of 4-inch diameter is the smallest ume of the test section which, in turn, is a function
concrete pipe currently produced in some areas of of the test section length and pipe diameter. By
North America. The upper limit of 24-inch diameter substituting these relationships into Equation [2]
was primarily for safety reasons, and the fact that the required test time (on page 8) can be stated as:
larger diameters can be more readily tested by vi-

[ DQL
sual inspection or testing individual joints. The cri-
TT = 0.00037
2 [ (3)
teria, pressures, holding times and procedures are
L
not applicable to air testing of individual joints.

The Time Pressure Drop Method (on page 8)
where:
is the most commonly used air test method. The D = Inside diameter of main sewer line in test
section of sewer to be tested is isolated, and the section, inches
internal air pressure is raised to a specific level. If L = Length of main sewer line in test section,
the drop in pressure is one pound per square inch, feet
or less, within a specified time interval, the line is
acceptable. From Equation [3], required air test times can
For safety reasons, and to prevent damage to be calculated for any combination of length and di-
joint integrity, under no circumstances should the ameter of pipe. ASTM C924 includes a table of the
sewer line and laterals be subjected to more than allowable air loss rates for concrete pipe diameters
six pounds per square inch. from 4 to 24 inches. Table 1 establishes the allow-
able air loss rate as a constant rate for each pipe
Criteria diameter, regardless of the length of the test sec-
Allowable air loss rates were established for tion. This concept, and the loss rate values, were
different diameters of concrete pipe to identify sig- based on experience and results obtained from
nificant losses. Field experience with testing sewer many field air tests. To calculate the required test
lines, combined with other test observations, in- time, use Equation [3] and the allowable air loss
dicate that any defect of significance will result in rate from Table 1 for the pipe diameter.
losses which exceed the allowable air loss rates.
Table 1 Allowable Air Loss Rates
To pass the air test, the sewer being tested must
not lose a total volume of air greater than the prod- Pipe QL cubic Pipe QL cubic
uct of the allowable rate of air loss and the test Diameter, feet per Diameter, feet per
Inches minute Inches minute
time, which is expressed as:
4 2 15 4
6 2 18 5
VL = QL + TT (1) 8 2 21 5.5
10 2.5 24 6
where: 12 3
VL   = total volume of air loss, cubic feet
QL   = allowable rate of air loss, cubic feet per To simplify the calculation process, the total re-
minute quired test time for a specific pipe diameter can
TT  = required test time, minute converted to a test time per unit length of pipe.
ASTM C924 includes a table of test times per 100
The required test time is a function of the total feet of sewer line for pipe diameters from 4 through
volume of air loss divided by the allowable rate of 24 inches. Table 2 was developed using Equation
air loss which can be expressed by rearranging [3] and the allowable air loss rates in Table 1. This
terms: is represented by Equation [4].

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 2


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
d2 l
(
TT = L T
( (4)
Le =
D2
(5)
100
where:
where:
Le   = Total value of all laterals connected to the
T = Required test time, minutes per 100 feet of
main sewer line expressed as an equiv-
pipe
alent length of the mail sewer line, feet
Table 2 Minimum Test Times d = inside diameter of lateral, inches
l = Total length of each diameter lateral, feet
Pipe T Pipe T

Diameter, Minutes per Diameter, Minutes per
Inches 100 Feet Inches 100 Feet
To obtain the required total test time for a mul-
tiple diameter system, add the equivalent length
4 0.3 15 2.1
of laterals to the main sewer line length, divide by
6 0.7 18 2.4
8 1.2 21 3.0 100, and then multiply by the appropriate test time
10 1.5 24 3.6 value from Table 2 for the main sewer pipe diam-
12 1.8 eter, as follows:

( L100+ L T
To test a sewer system involving multiple diam-
TT =
(
e
(6)
eter pipe, the volume of each size of pipe must be
converted to an equivalent length of main sewer
line, which length is then added to the test length From Table 3 for Figure 1, the required hold-
of the main sewer line. Equivalent length is deter- ing times may be directly selected for the specified
mined by: length and diameter of multiple and single diame-
Table 3 Time Holding Chart: Minimum Required Test Time in Minutes and Seconds for Pressure Drop from 3.5
to 2.5 psi
Length Pipe Diameter in Inches
in Feet 4 6 8 10 12 15 18 21 24
50 0-09 0-20 0-36 0-44 0-53 1-02 1-12 1-29 1-47
75 0-13 0-30 0-53 1-07 1-20 1-34 1-48 2-14 2-40
100 0-18 0-40 1-11 1-29 1-47 2-05 2-24 2-58 3-33
125 0-22 0-50 1-29 1-51 2-13 2-36 3-00 3-43 4-26
150 0-27 1-00 1-47 2-13 2-40 3-07 3-36 4-27 5-20
175 0-31 1-10 2-04 2-36 3-06 3-39 4-12 5-12 6-13
200 0-36 1-20 2-22 2-58 3-33 4-10 4-48 5-56 7-06
225 0-40 1-30 2-40 3-20 4-00 4-41 5-24 6-41 8-00
250 0-44 1-40 2-58 3-42 4-26 5-12 6-00 7-25 8-53
275 0-49 1-50 3-15 4-04 4-53 5-43 6-36 8-10 9-46
300 0-53 2-00 3-33 4-26 5-20 6-15 7-12 8-54 10-39
325 0-58 2-10 3-51 4-49 5-46 6-46 7-48 9-39 11-33
350 1-02 2-20 4-09 5-11 6-13 7-17 8-23 10-23 12-26
375 1-07 2-30 4-26 5-33 6-40 7-48 8-39 11-08 13-19
400 1-11 2-40 4-44 5-55 7-06 8-20 9-35 11-52 14-12
425 1-15 2-50 5-02 6-18 7-33 8-51 10-11 12-37 15-06
450 1-20 3-00 5-20 6-40 8-00 9-22 10-47 13-21 15-59
475 1-24 3-10 5-37 7-02 8-26 9-53 11-23 14-06 16-52
500 1-29 3-20 5-55 7-24 8-53 10-24 11-59 14-50 17-46
525 1-33 3-30 6-13 7-46 9-19 10-56 12-35 15-35 18-39
550 1-38 3-40 6-31 8-08 9-46 11-27 13-11 16-19 19-32
575 1-42 3-50 6-48 8-31 10-13 11-58 13-47 17-04 20-25
600 1-47 4-00 7-06 8-53 10-39 12-29 14-23 17-48 21-19

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 3


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
ter pipe systems. The required holding times in Ta- with ASTM C969, the line is acceptable and no ad-
ble 3 and Figure 1 were calculated using Equation ditional testing is required.
[3] and the minimum test times, T, given in Table If the groundwater level is two feet, or more,
2. To use Table 3, simply select the required hold- above the crown of the pipe at the upstream end,
ing time for the specified diameter and the length or if the test pressure required is greater than six
or equivalent length of the sewer system. To use pounds per square inch gage, the air test should
Figure 1, project a horizontal line from the length not be used, since damage to unrestrained later-
or equivalent length to the pipe diameter line, and als is possible. If the groundwater level is two feet
then vertically to the horizontal scale to obtain the or more, above the crown of the pipe, for the en-
value for the required holding time. tire length of the test section, the infiltration test,
or visual inspection, should be used depending on
Procedure the size of the pipe. If the groundwater level is less
Before conducting any leakage test, deter- than two feet above the crown of the pipe at up-
mine the groundwater conditions surrounding the stream end of the test section, the low-pressure air
sewer to be tested and select the type of test to test, exfiltration test, and individual joint tests and
be conducted. The requirements and limitations for visual inspection are all appropriate depending on
each test are summarized in Table 4. The first step the size of the pipe. If the air test is appropriate and
in each such procedures is to stop all dewatering selected, the proper procedures are presented in
operations and allow the groundwater to return to the following paragraphs.
it’s normal level.
If groundwater pressure is equal to or great- Line Preparation
er than the test pressure and the installed sewer is Where practical, the section of sewer line
not leaking, the sewer line is acceptable and no to be tested should be flushed and cleaned prior to
additional testing is required. If one or more joints conducting the low-pressure air test. This serves to
are leaking, but the total amount of leakage in the clean out any debris and produce more consistent
sewer line being tested is equal to or less than the test results, since air may escape through the walls
allowable leakage rate established in accordance of dry concrete pipe.
Figure 1 Low Pressure Air Testing by the Time Pressure Drops Method
600
4”-DIA

IA

IA
6”-D

IA

IA IA
IA
8”-D

-D
”-D

-D
”-D

” ” IA
500 15 18 ”-D
12
10

A
21 -DI
24”

400
Length, Feet

300

200

100

0
0 2 4 6 8 10 12 14 16 18 20 22
Time, Minutes
American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 4
© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
Table 4 Applicable Leakage Tests for Sewer Lines
Pipe Groundwater Condition Applicable Tests Comments
Infiltration Exfiltration Air Visual
Inspection

Groundwater pressure is X If there is no visual leakage, or leakage at


greater than test pressure one or more joints that is less than allow-
able, the sewer line is acceptable without
any additional testing,
Groundwater is either: X X Do not air test. Air testing may result in
All • Two feet or greater above damage to the unrestrained laterals.
the crown of the sewer
lines at inlet
• Two feet above the sewer
line’s crown along its
entire length.
4” to 24” Groundwater is two feet or X X X X All test are appropriate.
less above the highest point of Note: Air test pressure is restricted to a
the crown of the sewer line. maximum of 6 psi.
Greater All groundwater conditions X Do not air test. Testing should be limited to
Than 24” visual inspection of the sewer line or testing
of individual joints.

Isolate the section of sewer line to be test- air flows into the test section and to enable moni-
ed by inflatable plugs or other suitable means. The toring the air pressure within the test section. The
ends of all branches, laterals, tees, wyes and stubs system should be equipped with a six pound per
to be included in the test should be plugged. Se- square inch pressure relief valve to reduce hazards
curely anchor and brace all plugs to prevent blow- and avoid possible damage to the sewer and unre-
out due to the internal air pressure. strained laterals. The system should have a bleed-
er valve to depressurize the sewer at the comple-
Safety tion of the air test.
The materials, equipment and operation To provide realistic test results, the air com-
of the air test may be hazardous, and this Design pressor should be capable of pressurizing the test
Data does not purport to address all of the safety section in the required test time, or less. The mini-
problems associated with its use. It is the responsi- mum compressor capacity required is equal to the
bility of the user to consult and establish appropri- rate necessary to fill the sewer line to the desired
ate safety and health practices and to determine pressure plus the allowable air loss rate:
the applicability of regulatory limitation prior to use.
[
No one should be allowed in the trench or C = 0.17L D [ 2

+ QL (7)
manhole during pressurization, testing, or depres- TT 12
surization. Pressurizing a 24-inch diameter pipe to
4.0 pounds per square inch gage results in a to- where:
tal force of over 1800 pounds on the 24-inch plug. C = Compressor capacity, cubic feet per minute
Such force could cause the violent expulsion of an
improperly installed plug, and the energy of the Test Pressure
plug released air could injure persons within the If the test section is below groundwater lev-
manhole or manhole opening. el, determine the height of the groundwater above
the crown of the pipe at each end of the test sec-
Air Supply tion. Compute the average groundwater height and
Connect the air compressor to the inlet tap. increase the gage test pressure by 0.43 pounds
The air supply system should include the neces- per square inch for each foot of groundwater above
sary valves and gages to control the rate at which the pipe crown. Under no circumstances should

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 5


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
the test pressure be allowed to exceed six pounds rable, air losses are probably distributed
per square inch. Test pressures above six pounds throughout the line, and further analyses and
per square inch are unsafe and may damage unre- tests should be made.
strained laterals. • If the values in each segment are significant-
ly different, each segment should be evalu-
Initial Pressurization ated and further tests made to determine the
Slowly add air to the test section until the location of the air losses.
pressure inside the pipe is raised to 4.0 pounds Again, it is important to emphasize that the low-
per square inch gage. Regulate the air supply so pressure air test is an acceptable test which de-
that pressure is maintained between 3.5 and 4.0 tects pipe damaged during installation or improper
pounds per square inch gage for a period of time jointing and is not intended to be an indicator of
to allow the air and pipe wall temperatures to sta- possible water leakage under service conditions.
bilize. The pressure will drop slightly until equilib- Use or failure of this air test should not preclude
rium is reached, which normally takes about five acceptable by water test or other methods.
minutes. If the air and pipe wall temperatures are
greatly different, equilibrium may take longer to Disconnection
reach. Upon completion of the test, the bleeder
During initial pressurization, the plugs valve is opened to reduce the pressure to atmo-
should be checked to determine if there is any air spheric. it is imperative that all pressure in the pipe
leakage from the plugs. This can be accomplished be eliminated completely before any plug is loosed
by listening at the top of the open manhole for the for removal.
sound of air leakage.
Examples
Testing
The following examples have been pre-
Disconnect the air supply, decrease the
pared to demonstrate the techniques applied to
pressure to about 3.5 pounds per square inch
determine minimum test times.
gage, and begin timing the test. Experience has
shown that the low pressure air test usually is a Example 1
“go” or “no go” test and borderline cases are rarely Given: A sewer system consists of 342 feet of
encountered. If the gage holds steady, or has a low 24-inch diameter concrete pipe between
steady drop, the sewer line will usually pass the manholes A and B, and 135 feet of 18-inch
test. A sewer line with significant leaks will be indi- diameter pipe between manholes B and
C.
cated by an immediate or rapid drop in gage pres-
Find: The minimum test times required to
sure. demonstrate the integrity of the installed
lines.
Acceptance Solution: For the main sewer between manholes A
If the pressure holds between 3.5 to 2.5 and B, use Equation [4], and from Table
pounds per square inch gage for the required test 2, T=3.6 minutes per 100 feet for 24-inch
time, the line is acceptable. pipe:
If the air pressure drops more than one
[100L T
pound per square inch in less than the test time, TT =
[
stop the test. Either conduct the air test again to
T = [ 342 3.6
check equipment, plugs, procedures and results,
[
T 100
or use other methods to test the sewer line for
leakage. If the sewer line still fails, the following TT = 12.3 minutes

courses of action should be considered: For the main sewer between manholes
• Segmentally test the line and compare the B and C, use Equation [4], and Table 2,
time-air loss values in each segment. T=2.4 minutes per 100 feet for 18-inch
• If the values in each segment are compa- pipe:

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 6


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
[
TT = 135 2.4
[ Find: The test time required to demonstrate the
integrity of the installed lines.
100
Solution: Use Equation [5] to convert the total
TT = 3.2 minutes
volume of 6-inch laterals to an equivalent
To calculate the required compressor length of main sewer:
capacity for the main sewer between
Le = d2l
manholes A and B, use Equation [7] and D2
from Table 1, QL=6 cubic feet per minute
Le = (6) x 900
2
for 24-inch diameter pipe: (24)2

[
[ 2 Le = 56 feet
D
C = 0.17L + QL For the total system, use Equation [6] from
TT 12

[
C = 0.17(342) 24 + 6
[ 2 Table 2, T=3.6 minutes per 100 feet for
24-inch pipe:
12.3 12

[ L100
C = 24.9 cubic feet per minute [
+L
TT = T e
For the main sewer between manholes B

T = [342 + 56 3.6
and C, from Table 1, QL=5 cubic feet per [
minute for 18-inch diameter pipe: T 100

[
[ 2 TT = 14.3 minutes

C = 0.17(135) 18 + 5 To calculate the compressor capacity for
3.2 12
C = 21.1 cubic feet per minute the equivalent system, use Equation [7]
and from Table 1, QL=6 cubic feet per
minute for 24-inch diameter pipe:

[
Example 2
Given: The 342 feet of 24-inch diameter concrete C = 0.17L D [
+ QL
2

TT 12

[
pipe between manholes A and B in [ 2
Example 1 has several 6-inch laterals with C = 0.17(342 +56) 24 + 6
a total length of 900 feet connected to the 14.3 12
main. C = 24.9 cubic feet per minute

Figure A-1
ATMOSPHERIC CONDITION

V3.5 at atmospheric pressure V2.5 at atmospheric pressure

PRESSURE CONDITION

VT at 3.5 psig VT at 2.5 psig

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 7


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
APPENDIX - Time Pressure Drop method
VL = V3.5 - V2.5
The time pressure Drop Method is derived 18.2VT - 17.2VT
from Boyle’s Law, which states that the product of =
14.7
absolute pressure intensity and specific volume of VT
any given mass of air is constant for any compres- =
14.7
sion or expansion at constant temperature. Ex-
πD2L
pressed in equation form: x 1
substituting
VT =
4 144
P1V1 = P2V2 [A.1] where:
p = 3.1416
where: D  = diameter, inches
P1 = pressure at point 1, pounds per square L  = length of test section, feet
inch or foot
V1 = volume at point 1, cubic inches or feet therefore:
P2 = pressure at point 2, pounds per square VL = 0.00037 D2L [A.2]
inch or foot
V2 = volume at point 2, cubic inches or feet The time in which the volume of air is lost is equal
to the volume of air loss divided by the rate of air loss.
To determine the volume of air loss within a pipe test
section for a pressure drop from 3.5 pounds per square VL
TT =
inch gage (18.2 psia) to 2.5 pounds per square inch QL
gage (17.2 psia), it is necessary to evaluate the pressure-
volume relationship at both of these pressure conditions. 0.00037D2L
= [A.3]
Referring to Figure A-1 and applying Boyle’s law: QL

where:
14.7V3.5 = 18.2VT & 14.7V2.5 = 17.2VT TT  = test time, minutes
QL  = rate of air loss, cubic feet per minute
where:
14.7 = atmospheric pressure at sea level,
pounds per square inch
V3.5  = volume of air at atmospheric pressure
required to be compressed into the
volume of the test section to develop a
gage pressure of 3.5 psig, cubic feet
18.2  = absolute pressure corresponding to 3.5
psi gage pressure within the test section,
pounds per square inch
VT  = volume of pipe test section, cubic feet
V2.5  = volume of air at atmospheric pressure
required to be compressed into the
volume of the test section to develop a
gage pressure of 2.5 psig, cubic feet
17.2   = absolute pressure corresponding to 2.5
psi gage pressure within the test section,
pounds per square inch

The volume of air loss (VL) for the pressure
drop from 3.5 to 2.5 pounds per square inch gage is
expressed as:

American Concrete Pipe Association • www.concrete-pipe.org • info@concrete-pipe.org 8


© 2011 American Concrete Pipe Association, all rights reserved. DD 23 (08/11)
Technical data herein is considered reliable, but no guarantee is made or liability assumed.

Вам также может понравиться