EXCAVATION, BACKFILL & EMBANKMENT

F1/C1
w/r:
 EXCAVATION:
VE = Volume of Excavation
VE = WF · LF · DE · NF WF = Footing Width
LF = Footing Length
VE = 1.9 × 1.9 × 1.2 × 12 DE = Depth of Excavation
VE = 51.984 m3 NF = No. of Footings
BF = Volume of Backfill
VE/F = Volume of Excavation
 BACKFILL: per Footings
VF = Volume of Footing
BF = [VE/F – (VF +VC)] × 1.3 × NF VC = Volume of Embedded
Column
BF = {4.332 – [(1.9×1.9×0.35) + (0.35×0.35×0.85)]} ×
1.3 ×12
BF = 46.244 m3
F2/C2 w/r:
 EXCAVATION: VE = Volume of Excavation
WF = Footing Width
VE = WF · LF ·DE · NF LF = Footing Length
VE = 1.2 × 3.2 × 1.5 × 3 DE = Depth of Excavation
NF = No. of Footings
VE = 17.280 m3
BF = Volume of Backfill
VE/F = Volume of Excavation per Footings
 BACKFILL: VF = Volume of Footing
VC = Volume of Embedded Column
BF = [VE/F – (VF + VC + VFTB-2)] × 1.3 × NF VFTB-2 = Volume of Embedded FTB2
*For F2/C2 with FTB-2 at two sides:

BF = {5.76 – [(3.2×1.2×0.30) + 2(0.30×0.30×1.2)


+2(0.40×0.25×0.90)]} × 1.3 × 1
BF = 5.476 m3

*For F2/C2 with FTB-2 at one sides:

BF = {5.76 – [(3.2×1.2×0.30) + 2(0.30×0.30×1.2) +


2(0.40×0.25×0.45)]} × 1.3 × 2
BF = 11.185 m3
FTB-2 w/r:
EXCAVATION: VE =Volume of Excavation
WFTB-2 =FTB-2 Width
VE = WFTB-2 · DE ·LFTB-2 · NF DE =Depth of Excavation
LFTB-2 =Length of FTB-2
VE = 0.25 × 1.2 × 0.5725 × 4 *Excluding parts of FTB-2 above F2 Area*
VE = 0.687 m3 NFTB-2 = No. of FTB-2
BF = Volume of Backfill
BACKFILL: BF
VE/FTB-2= Volume of Excavation per FTB2
VFTB-2 = Volume of FTB2
BF = (VE/FTB-2 – VFTB-2) × 1.3 × NF
= 0.5954 m3
BF = [0.17175 – (0.25 × 0.40 × 0.5725)] × 1.3 × 4
FTB-1/WF-1 is above Natural Grade Line; no Excavation WF-2 is above Natural Grade Line; no Excavation is
is needed. needed.
____________________________________________________________________________________________________________________

TOTAL VOLUME OF EXCAVATION: TOTAL VOLUME OF BACKFILL:

= 51.984 + 17.280 + 0.687 = 46.244 + 5.476 + 11.185 + 0.5954


= 69.951 m3 = 63.500 m3

____________________________________________________________________________________________________________________

VOLUME OF EMBANKMENTS:
*Assuming Distance from N.G.L. to F.G.L = 600 mm

EMBANKMENT @WATER TANK EMBANKMENT @POWER HOUSE’s EXTERIOR STAIR


𝑆−4 2 𝐴−7 𝑆−3 3
Sheet No. ; Sheet No. & Sheet No. ;
11 | 21 𝑠−4 7 | 21 10 | 21 𝑠−3

= Area × Depth of Excavation Vol. below F.G.L. ≈ (0.6×2.6×1.6) ≈ 2.496 m3


= (3.2 × 1.2) × 0.6 Vol. below Landing ≈ (1×1×1.6) ≈ 1.6 m3
= 2.304 m3 Vol. Below Stairs ≈ ½(1.5×1)(1.6) ≈ 1.2 m3
Total Volume ≈ 2.496+1.6+1.2 ≈ 5.296 m3
EMBANKMENT @POWER HOUSE
𝐴−7
Sheet No. 7 | 21

= Area × Depth of Excavation


= 2.7 × 3.0 × 1.6
= 4.860 m3
EMBANKMENT @GROUND FLOOR EMBANKMENT @EXTERIOR STAIR & FL-1
𝐴−2 2 𝐴−3 5 7 𝑆−3 3
Sheet No. ; Sheet No. ; , & Sheet No. ;
2 | 21 𝐴−3 3 | 21 𝐴−3 𝐴−3 10 | 21 𝑠−3

Floor Area Vol. Below F.G.L.


= 10.400 × 8.400 ≈ 0.6[(3.025×6.335) – (1.35×4.19)]
= 87.360 m2 ≈ 8.104 m3
Volume Embedded by Columns Vol. below FL-1
= 0.350 × 0.350 × 0.600 × 12 ≈ 1.1 × 1.675 × 6.335
= 0.882 m3 ≈ 11.672 m3
Volume Embedded by FTB-1 [@Concreting] Vol. Below Stairs
= 3.270 m3 ≈ ½(1.5 × 1.1)(2.145)
Volume Embedded by WF-2 [@Concreting] ≈ 1.770 m3
= 1.289 m3
Total Volume
Total Volume of Embankment ≈ 8.104 + 11.672 + 1.770
= 87.360(0.6) – (0.882+3.27+1.289) ≈ 21.546 m3
= 46.975 m3
EMBANKMENT @ RAMP AND FL-2
𝐴−3 5 7
Sheet No. ; ,
3 | 21 𝐴−3 𝐴−3

Vol. Below F.G.L.


≈ 0.6 × 7.6 ×2.8
≈ 12.996 m3
Vol. below FL-2
≈ 1.3 × 2.65 × 0.5
≈ 1.723 m3
Volume Below Ramp-1
≈ ½ (6 × 0.5)(1.4)
≈ 2.100 m3
Volume Below Ramp-2
≈ (6 × 0.5 × 1.4) + ½ (6 × 0.5)(1.4)
≈ 6.3 m3

Total Volume
≈ 12.996 + 1.723 + 2.1 + 6.3
≈ 23.119 m3

TOTAL VOLUME OF EMBANKMENTS:

≈ 2.304 + 4.860 + 5.296 + 46.975 + 21.546 + 23.119


≈ 104.1 m3