Вы находитесь на странице: 1из 164

SECTION a

LIST OF PRINCIPAL QUANTITIES/


SCOPE OF WORKS
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT -DOHA LINK SECTION
CONTRACT RA/214 LIST OF PRINCIPAL QUANTITIES/
VOLUME III - DOC.III.5 SCOPE OF WORKS a a/1

NUMBER ITEM DESCRIPTION

SECTION a - LIST OF PRINCIPAL QUANTITIES/SCOPE OF WORKS

The following schedule of main work items with approximate quantities are provided as an
indication of the overall scope/magnitude of work to be executed on the Project. This
information is provided without liability and it is the Tenderer's responsibility to fully assess
and quantify the works to be carried out

Part 1 - General Items (Not Applicable)

Part 2 - Ground Investigation


(Not Applicable)

Part 3 - Geotechnical and Other Special Processes (Not Applicable)

Part 4 - Demolition and Site Clearance (Not Applicable)

Part 5 - Entertainment City Interchange - Civil Works

Concrete 36,000 m3
Reinforcement, carbon steel 5,250 t
Prestressing (strand) 1,000 t
Bearings 120 nr
Expansion joints 220 m
Steel piles, dia 1219 mm 2,000 t
Fill 950,000 m3

Part 6 - Doha Peninsula Road - Civil Works

Concrete 3,500 m3
Reinforcement, carbon steel 500 t
Expansion Joints 100 m
Steel piles, dia. 1219 mm 250 t
Fill 250,000 m3

Part 7 - Doha Interchange - Civil Works

Concrete 12,600 m3
Reinforcement, carbon steel 1,250 t
Prestressing (strand) 150 t
Bearings 72 nr
Expansion Joints 60 m
Steel piles, dia. 1219 mm 560 t
Fill 250,000 m3

Part 8 - Approach Bridge West - Civil Works

Concrete 220,000 m3
Reinforcement, carbon steel 33,000 t
Reinforcement, stainless steel 3,250 t
Prestressing (strand) 9,000 t
Bearings 584 nr
Expansion Joints 550 m
Steel piles, dia. 1524 mm 14,500 t

Part 9 - Main Bridge - Civil Works

Concrete 26,000 m3
Reinforcement, carbon steel 4,300 t
Reinforcement, stainless steel 200 t
Prestressing (strand) 1,000 t
Bearings 56 nr
Expansion Joints 125 m
Steel piles, dia. 1524 mm 1,700 t
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHALINK SECTION
CONTRACT RA/214 LIST OF PRINCIPAL QUANTITIES/
VOLUME III - DOC.III.5 SCOPE OF WORKS a a/2

NUMBER ITEM DESCRIPTION

SECTION a - LIST OF PRINCIPAL QUANTITIES/SCOPE OF WORKS (CONT'D)

Part 10 - Approach Bridge East - Civil Works

Concrete 93,000 m3
Reinforcement, carbon steel 15,000 t
Reinforcement, stainless steel 1,000 t
Prestressing (strand) 4,000 t
Bearings 246 nr
Expansion Joints 280 m
Steel piles, dia. 1524 mm 5,700 t

Part 11 - Building Works

Causeway management/Service & Control Centre buildings 2,600 m2

Part 12 - Engineering Installations

Part 12 A - Road Lighting Works


14 m high lighting columns on concrete foundation 400 nr
14 m high lighting columns on bridge deck 250 nr
Road Lighting Management System

Part 12 B - Mechanical, Electrical and


Communication Works
11 kV substation rooms on bridge girders 6 nr
11 kV substation rooms along road/interchange 4 nr
Diesel generator unit 2 nr
Floodlighting for illumination of girders
Internal bridge lighting system
Intelligent traffic system
Weighbridge
SCADA system
Communication and radio system
Structural monitoring system
Water supply and storm water drainage system
Sewage system including sewage plant

Part 13 - Finishing Works

Overhead Gantries/Cantilever Signage


Structures 66 nr
Bridge parapet railing 42,500 m

Subgrade (Type A) 475,000 m2


Crushed stone sub-base 300 m 400,000 m2
Asphalt concrete wearing course 690,000 m2
Asphalt base/binder courses 1,050,000 m2
Block Paving pavements 20,000 m2
Stone pitching to side slopes 270,000 m2

Traffic guard rails/barriers 40,000 m


Jersey barriers 3,000 m
Highway boundary fencing 22,000 m
SECTION b

PREAMBLES
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b b/1

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES

Generally

A The Lump Sum amount entered by the Contractor in these Bills of Quantities shall constitute the entire
claim for compensation for the work under this Contract in accordance with the Conditions of Contract.
It is to be noted that the Contractor's design costs shall be priced separately and included in Part d/1
General Items of the Bills of Quantities.

The works shall not be remeasured and will be subject to adjustment only as a result of changes in
the scope of work approved by the Employer.

B The Bills of Quantities have been provided as a format/schedule for pricing by the Contractor and in
order that the bids received can be analysed/compared on a like for like basis.

The Contractor is totally and without exception responsible for the measurement of the quantities and
work items required for the completion of the Design and Build Works.

The Bills of Quantities shall be used as a pricing document and the Contractor shall identify any
additional items of work to those stated in the Bill of Quantities, and include in the designated place
at the end of each Bill Section.

C Each unit cost for any single item must be firm and will not be adjusted during the contract.

D The Contractor must include his quantities against the items provided in the Bills of Quantities and his
unit prices to give the total Tender sum.

E If the Contractor determines that there are items on the drawings or in the Specification or required
by his design which are not included in the Bills of Quantities, he should reflect such variances or
omissions in this pricing document.

F Upon award of Contract, the Bills of Quantities shall be used solely for evaluating progress and as a
schedule of rates for any approved changes.

G The Bills of Quantities herein, including all notes and instructions, form an integral part of the Contract
Documents. However, the descriptions contained in the Bills of Quantities for each item are not
necessarily complete. The Contractor is referred to the Conditions of Contract and other Documents,
Specifications and Drawings as well as relevant Standards and Codes of Practice for further information
as no claim or variation will be considered on account of the Contractor's failure to do so.

H The Contractor is cautioned to familiarise himself with the full content of other Contract Documents
including the Instructions to Tenderers, Tender Form, General Conditions, Particular Conditions, Design
Criteria, Tender Drawings and Specifications or any other information that can be reasonably inferred
from any of them and all obligations contained in the documents shall be included in the item rates and
sums.

I The Contractor should note that Ministry of Public Works reserves the right to require the Contractor to
adjust any unfair distribution of moneys within the General Items.

J Drawings, Specifications and Bills of Quantities and all other Contract documents are complementary
and if any item is included in any of them, it shall be deemed included in all.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b R (b/2 - AD1)

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Generally (Cont'd)

A The Contractor's tender for the entire work shall provide for supervision of any or all trades that is not
intended to be performed with his own forces. No extra compensation for services as a General
Contractor will be paid.

B The Contractor is required to provide with his tender one original and two copies of the Bills of
Quantities fully priced out in waterproof ink with summation sheets properly checked and extended
to include any items which are added by the Tenderer.

C Amendment shall not be made to these Bills of Quantities without the authority, in writing, of the
Employer. The Tenderer is allowed to insert items for Method - Related charges in accordance with
Civil Engineering Standard Method of Measurement (Third Edition) CESMM3. CESMM3, Section 7:
paragraphs 7.6, 7.7 and 7.8 are not applicable.

D The Contractor shall not use these Bills of Quantities as the basis for a construction programme or for
the purposes of ordering materials or arranging sub-contracts. The references for these activities shall
be the drawings, specification and instructions issued by the Engineer.

E The Contractor is to ensure that identical items occurring in separate bills are not priced at different
rates unless this is the Contractors deliberate intention.

F The prices and rates entered by the Contractor against items in the Bills of Quantities shall apply
throughout the duration of the Contract to the execution of these items in any location and, except
where otherwise provided for, to any additional work ordered by the Engineer.

G A price or rate is to be entered against each item in the Bills of Quantities and any item left unpriced
will be deemed to be included for elsewhere in the Bills of Quantities and hence the rate for that item
will be taken as NIL.

H Quantities and Rates inserted by the Tenderer must be limited to a maximum of THREE DECIMAL PLACES.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b b/3

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Generally (Cont'd)

Units of Measurement

A The following units of measurement and abbreviations have been used. Clause 5.19 of CESMM3 is
deleted.
Unit Abbreviation
Millimetre mm
Metre m
Square millimetre mm2
Square metre m2
Hectare ha
Cubic metre m3
Gramme g
Kilogramme kg
Tonne t
Sum sum
Number nr
Hour h
Days Day
Man-days man-day
Vehicle-Days Veh-day
Kuwaiti Dinars KD
British Standard BS
California Bearing Ratio CBR
Continued Cont'd
Unplasticised Polyvinyl Chloride uPVC

Method of Measurement

B This form of Bill of Quantities have been prepared generally in accordance with the Rules of the Civil
Engineering Method of Measurement Third Edition (CESMM3) approved and sponsored by the
Institution of Civil Engineers 1 - 7, Great George Street, London SW1P 3AA, England and published
by Thomas Telford Services Ltd. 1 Heron Quay London E14 4JD. In any particular case, in the
Bills of Quantities where the method of measurement for certain items is modified it is stated in these
Preambles. The modified method of measurement expressed for these items must be accepted
and measured in accordance therewith.

C Items in the Preambles Section of these Bills of Quantities are deemed to qualify and to form part of
every description of the work to which they refer including composite descriptions.

D Item reference numbers shown in column 3 for the class of works according to CESMM3 generally
follow the convention used by CESMM3. Any deviation in the convention used shall not be the basis
for a claim.

E Reference to British Standards in CESSM3 are applicable only if not stated unless otherwise in the
Contract Specifications in which case the specified reference standard shall apply.

F CESMM3, Section 1: paragraph 1.2 is deleted. The Conditions of Contract applicable to this Contract
are the General Conditions of Contract for Plant and Design-Build Projects prepared by the
International Federation of Consulting Engineers (FIDIC) First Edition 1999. Reference to Clause
numbers in CESMM3 are applicable to the corresponding Clause numbers which may be
different to the Conditions of Contract applicable to this project.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b b/4

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Pricing

A The pricing of the Bills of Quantities shall be executed in such a way to enable reproduction by
photocopying to be carried out if required. CESMM3, Section 6, Paragraph 6.1 is deleted and
replaced with "Rates and Prices shall be inserted in the rate column of the Bill of Quantities in
Kuwaiti Dinar and fils".

B The prices shall be comprehensive and must include for complying in all respects with the Instructions
to Tenderers, Conditions of Contract, Specifications Design and Drawings and for all matters and things
necessary for the proper construction, completion, and maintenance of the whole of the Works. No
claims for additional payment will be allowed for any error or misunderstanding by the Contractor of the
work involved.

C The rates and sums inserted in the Bill of Quantities are deemed to include for the following:-

1. Labour and all costs in connection therewith.

2. Materials, goods and all costs in connection therewith (e.g. carriage freightage, all duties, delivery,
unloading, storing, returning packings, handling, hoisting or lowering, replacing work, goods or
materials damaged, broken, lost or stolen until the issue of a Certificate of Completion).

3. Fittings and fixing materials or goods in position.

4. Plant.

5. Waste, bulking, shrinkage and overlaps.

6. Land required for tips and stockpiles including all costs for obtaining any necessary licences and
approvals.

7. Allowance for phasing requirements of works, effect on programming of the works of all traffic
diversions and construction activity associated with diversion or installation of services.

8. For taking measures for the support and full protection of pipes, cables and other apparatus required
during the progress of the Works as required by Service Authorities or the Engineer.

9. Dewatering as required.

10. For working alongside and liaising with other Contractors working on the same site.

11. Preparation and supply of shop drawings.

12. Overhead charges and profit.

D Lump sums shall not be inserted where unit rates are applicable.

E Where the word "allow" is used, the cost of the item shall be the responsibility of the Contractor.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b b/5

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Pricing (Cont'd)

A The amounts set against any items of overhead shall include for all costs in connection with letters of
credit bank charges, interest charges and insurance after the materials come under the control of the
Contractor.

B The tenderer shall submit the analysis of "Tender Sum" with a full and detailed rate breakdown of all
the BOQ items, together with the tender submission. The breakdown is to show the actual calculations
of the General Items, Labour, Plant and Materials costs for the Works, the build-up of measured rates
with on-costs and overheads and any other allowances used to arrive at the Tender Price. In addition
the tenderer/contractor will be required to provide the Engineer within 7 days with a full and detailed
breakdown/any other information if requested.

C Where fix only items are specified, the rate shall be deemed to include for taking delivery, storing and
installation of goods or materials in the works where appropriate.

Weather Conditions

D The prices and rates shall include for all restrictions on working due to inclement weather or weather
related conditions.

Variations

E The rates inserted in the Bill of Quantities with the application of the adjustment item will be used to
value any variations to the Works, whether omissions or additions. The Contractor shall not be
entitled to payment for profit and overheads on the value of Work omitted.

Work affected by Water

F CESMM3, Section 5:pursuant to paragraph 5.20 no body of water is identified separately. The Tenderers attention is
particularly drawn to the de facto situation whereby the whole of the Works are affected by Tidal Water.

Adjustment Item

G The Tenderer may insert an Adjustment Item.


The adjustment item, if any, shall apply to all Bill items excluding provisional sums unless clearly
indicated otherwise. The adjustment items shall not be a lump sum but a percentage of the total
tendered sum excluding provisional sums. The adjustment item shall be applied to all applicable
item rates and sums entered in the Bills of Quantities (including any addenda). The Contract shall be
signed with the inclusion of the adjusted rates and sums. The adjusted rates and sums shall be
applied for the valuation of Variations.

H CESMM3, Section 6: paragraphs 6.3, 6.4 and 6.5 are not applicable.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b b/6

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Pricing (Cont'd)

General Items

Contractual Requirements

A (i) Items for insurance classed as contractual requirements shall be deemed to include only provision
of insurance in accordance with Contract Conditions Clause 18 Insurance.

Shop Drawings, Working Drawings, Operations and Maintenance Instructions

B The Contractor is to allow in his rates for the production of all shop drawings, working drawings,
operations and maintenance instructions called for in the Specifications.

These shall include but not be limited to the following:

(i) The surveyed location of all existing services, including gas/oil/other pipelines.

(ii) Existing ground levels/sea bed levels.

(iii) Earthwork cross sections.

(iv) Temporary traffic diversions on detour roads.

(v) Proposed traffic sign design and fixing details.

(vi) Temporary works drawings where requested by the Engineer.

Ground Investigation

C CESMM3 Class B: Ground Investigation is deleted and replaced with the one Item of Ground Investigation as detailed in
the Bill of Quantities. This item is to be priced to include all Ground Investigation works

D Items for ground investigation shall be deemed to include preparation and submission of records and results.

E The items for trial trenches and pits will be executed in accordance with the Engineer's instructions.

Geotechnical and Other Specialist Processes

F CESMM3, Section C: Geotechnical and Other Specialist Processes is deleted and replaced with the one Item of
Geotechnical and Other Specialist Processes as detailed in the Bill of Quantities.
This Item is to be priced to include all Geotechnical and Other Specialist Processes.

Demolition and Site Clearance

G CESMM3 Class D: Demolition and Site Clearance is deleted and replaced with the one Item of Demolition and
Site Clearance as detailed in the Bill of Quantities. This Item is to be priced to include all Demolition and
Site Clearance works.

H Items for demolition and site clearance shall also include disposal of the materials arising
except as otherwise directed.

I The price for general clearance of trees, bushes, other vegetation and debris shall include carting to tip. The limits
of general clearance work will be as instructed by the Engineer.
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 PREAMBLES
VOLUME III - DOC.III.5 b R (b/7 - AD1)

NUMBER ITEM DESCRIPTION

SECTION b - PREAMBLES (Cont'd)

Pricing (Cont'd)

Earthworks

Excavation/Filling

A The quantities of earthworks shall be computed net using dimensions from the Drawings with no
allowance for bulking, shrinkage, waste or working space.

B The rate for imported fill material shall include borrow pit excavation on land,
hauling/pumping, placement and compaction in specified layers.

C No separate pay item is included for the preparation of the existing sea bed in respect of fill areas, all
preparation works such as removal of silt, mud, debris and any other works as required by the
Specifications are to be included for in the pay items for fill.

Contract Pricing / Options

D The Contractor is required to quantify and price his Tender Design using, and where necessary, extending the form of BoQ
provided with the Tender Documents which has been produced on the basis of the Employer's Concept Design and Drawings.

In Section (e) of this document, a Grand Summary is provided for the above item and the Contractor
is to price/complete the form and carry to the Form of Tender.
SECTION c

DAYWORK SCHEDULES
(INCLUDED UNDER DOCUMENT III.6)
SECTION d

WORK ITEMS
PART 1

GENERAL ITEMS
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS 0.000
0.000
Contractual Requirements 0.000
0.000
A Performance Bond A110 Sum 1 1425507.790 1425507.790
0.000
B Insurance of the Works and Contractor's 0.000
Equipment A120 Sum 1 1118532.560 1118532.560
0.000
C Third Party Liability Insurance A130.1 Sum 1 124281.400 124281.400
0.000
D Workmen's Compensation Insurance A130.2 Sum 1 157757.760 157757.760
0.000
E Insurance for Design A140 Sum 1 175000.140 175000.140
0.000
F Additional Extended guarantee Insurance A150 Sum 1 1618156.440 1618156.440
0.000
0.000
Specified Requirements 0.000
0.000
Accommodation for the Employer's staff 0.000
0.000
G Establishment of Permanent and 0.000
Temporary offices for Employer and 0.000
Engineer A211.1 Sum 1 271728.310 271728.310
0.000
H Maintenance of Permanent and 0.000
Temporary offices for Employer and 0.000
Engineer A211.2 Month 48 4470.960 214606.080
0.000
0.000
0.000
Services for the Employer 0.000
0.000
I Marine transport with crew for inspections 0.000
etc. A221.1 Sum 1 512354.230 512354.230
0.000
J Access to Contractor's floating 0.000
equipment A221.2 Sum 1 209578.290 209578.290
0.000
K Telephone and telefax A222 Month 48 724.300 34766.400
0.000
L Set of progress photographs (30 No.) 0.000
as Particular Conditions of Contract 1.16 A229.1 Month 48 335.330 16095.840
0.000
M Video (10 copies) as Particular Conditions of 0.000
Contract 1.17 A229.2 Sum 1 33532.520 33532.520
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 5911897.760


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Specified Requirements (Cont'd) 0.000
0.000
Equipment for use by the Employer's staff 0.000
0.000
A Establishment of office equipment A231.1 Sum 1 71053.120 71053.120
0.000
B Maintenance of office equipment A231.2 Month 48 350.640 16830.720
0.000
C Establishment of surveying equipment A233.1 Sum 1 24562.150 24562.150
0.000
D Maintenance of surveying equipment A233.2 Month 48 51.170 2456.160
0.000
0.000
Attendance upon the Employer's staff 0.000
0.000
E Chainmen/Office Attendance (4 No) A242 month 192 877.410 168462.720
0.000
0.000
Testing 0.000
0.000
Testing of materials 0.000
0.000
F Allow for all specified testing to be carried 0.000
out in accordance with the Specification 0.000
and provision of laboratory A250 Sum 1 176950.260 176950.260
0.000
0.000
Testing of the Works 0.000
0.000
G Testing to be carried out by independent 0.000
approved specialised Testing laboratory A260 Sum 1 35390.050 35390.050
0.000
0.000
Environmental Monitoring 0.000
0.000
H Set up and operate Environmental 0.000
Monitoring Plan during the Contract A280.1 Sum 1 57516.430 57516.430
0.000
I Set up and operate Contractors 0.000
Environmental Management Plan A280.2 Sum 1 373856.800 373856.800
0.000
J Carry out Environmental Monitoring Plan 0.000
(EMP) for 5 years after the issue of the 0.000
Taking Over Certificate A280.3 Sum 1 143791.080 143791.080
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1070869.490


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Specified Requirements (Cont'd) 0.000
0.000
Specified Temporary Works 0.000
0.000
A Traffic diversions in accordance with the 0.000
Employers Requirements A271 Sum 1 667028.170 667028.170
0.000
B Traffic management, safety and control, 0.000
in accordance with the Employers A272 Sum 1 362013.480 362013.480
Requirements 0.000
0.000
C Establishment and removal of access 0.000
roads A273.1 Sum 1 180291.750 180291.750
0.000
D Maintenance of access roads A273.2 Day 1,460 160.710 234636.600
0.000
E Protection and upkeep of site, adjacent 0.000
areas and properties, in accordance 0.000
with the Employers Requirements A279.1 Sum 1 33532.520 33532.520
0.000
F Tidying and cleaning the site, in 0.000
accordance with the Employers A279.2 Sum 1 172498.300 172498.300
Requirements 0.000
0.000
G Erection, maintenance and removal of 0.000
project sign boards A279.3 nr 22 1465.710 32245.620
0.000
H Marker/navigation buoys A279.4 Sum 1 30179.290 30179.290
0.000
0.000
Investigations and Studies and Specs. 0.000
0.000
I Detailed Utility Survey in the Doha A290.1 Sum 1 33532.520 33532.520
Peninsula 0.000
0.000
J Bathymetric and topographic A290.2 Sum 1 33532.520 33532.520
0.000
K Physical model tests of embankment A290.3 Sum 1 33532.520 33532.520
cross sections 0.000
0.000
L Scour models of pier and embankment A290.4 Sum 1 51807.740 51807.740
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1864831.030


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Method Related Charges 0.000
(Inserted by the Tenderer) 0.000
0.000
Accommodation and buildings for the 0.000
Contractor 0.000
0.000
Accommodation for the Employer's staff 0.000
0.000
A Establishment of Permanent and 0.000
Temporary offices for Employer and 0.000
Engineer A211.1 Sum 1 3682895.300 3682895.300
0.000
B Maintenance of Permanent and 0.000
Temporary offices for Employer and 0.000
Engineer A211.2 Month 48 25348.110 1216709.280
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
Services month 0.000
0.000
C Telephone and telefax A222 Month 48 2566.910 123211.680
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 5022816.260


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Method Related Charges (Cont'd) 0.000
(Inserted by the Tenderer) 0.000
0.000
Equipment 0.000
0.000
A Establishment of office equipment A231.1 Sum 1 123609.090 123609.090
0.000
B Maintenance of office equipment A231.2 Month 48 4078.840 195784.320
0.000
C Establishment of surveying equipment A233.1 Sum 1 81856.840 81856.840
0.000
D Maintenance of surveying equipment A233.2 Month 48 407.060 19538.880
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 420789.130


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Method Related Charges (Cont'd) 0.000
(Inserted by the Tenderer) 0.000
0.000
Temporary Works 0.000
0.000
A Temporary Bridge A354 Sum 1 ### 13324360.480
0.000
B PC Yard incl Workshop & Rebar Factory Sum 1 3640039.490 3640039.490
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 16964399.970


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Method Related Charges (Cont'd) 0.000
(Inserted by the Tenderer) 0.000
0.000
Management, Supervision & Labour 0.000
0.000
A Management A371 Sum 1 5571450.570 5571450.570
0.000
B Supervision & Labour A371 Sum 1 4926301.240 4926301.240
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 10497751.810


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
. PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
A Compliance with the Conditions of 0.000
Contract and Specification (the Tenderer 0.000
shall separately list and price below any 0.000
other clause considered to have a 0.000
monetary value) A900 Sum 1 3065760.340 3065760.340
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 3065760.340


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
. PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Contractors Design Costs 0.000
0.000
The Tenderer shall include below the Lump Sum 0.000
amount included in the Tender Design Costs. 0.000
This Lump sum amount shall be broken down 0.000
into design costs for each of the individual project 0.000
elements that follow Section d of this Bill of 0.000
Quantities: Parts 5 - 13 inclusively. 0.000
0.000
The design costs for each project element shall 0.000
be further broken down into cost of:- 0.000
0.000
(i) Basic / Preliminary Design 0.000
(ii) Detailed Design 0.000
0.000
Breakdown of Contractor's Design Costs 0.000
0.000
Part 5 - Entertainment City Interchange - 0.000
Civil Works 0.000
0.000
A Basic Design - Sum 1 130408.080 130408.080
B Detailed Design - Sum 1 304285.540 304285.540
0.000
0.000
Part 6 - Doha Peninsula Road - 0.000
Civil Works 0.000
0.000
C Basic Design - Sum 1 28757.040 28757.040
D Detailed Design - Sum 1 67099.770 67099.770
0.000
0.000
Part 7 - Doha Interchange - Civil Works 0.000
0.000
E Basic Design - Sum 1 74789.640 74789.640
F Detailed Design - Sum 1 174509.170 174509.170
0.000
0.000
Part 8 - Approach Bridge West - 0.000
Civil Works 0.000
0.000
G Basic Design - Sum 1 573128.330 573128.330
H Detailed Design - Sum 1 1337299.420 1337299.420
0.000
0.000
Part 9 - Main Bridge - Civil Works 0.000
0.000
I Basic Design - Sum 1 88632.000 88632.000
J Detailed Design - Sum 1 206808.020 206808.020
0.000
0.000
Part 10 - Approach Bridge East - 0.000
Civil Works 0.000
0.000
K Basic Design - Sum 1 287564.080 287564.080
L Detailed Design - Sum 1 670982.830 670982.830
0.000
0.000
Part 11 - Building Works 0.000
0.000
M Basic Design - Sum 1 25697.610 25697.610
N Detailed Design - Sum 1 59961.090 59961.090
0.000
0.000
Part 12 - Engineering Installations 0.000
0.000
O Basic Design - Sum 1 138053.830 138053.830
P Detailed Design - Sum 1 322125.610 322125.610
0.000
0.000
Part 13 - Finishing Works 0.000
0.000
Q Basic Design - Sum 1 154509.640 154509.640
R Detailed Design - Sum 1 360522.480 360522.480
0.000

To Part Summary 5005134.180


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 d/1/10

NUMBER ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


KD KUWAITI DINARS
. PART 1 - GENERAL ITEMS (CONT'D) 0.000
0.000
Additional Items 0.000
0.000
Existing Services 0.000
0.000
A The Contractor shall take such measure and exercise such care 0.000
to protect the Site during the course of the Works, as directed by 0.000
and to the entire satisfaction of the Engineer, including 0.000
determining and recording all existing on site services routes. It is 0.000
the Contractor's responsibility to obtain all NOC Certificates. 0.000
However, the Employer will liaise with the relevant authorities to 0.000
assist in procuring any "No Objection Certificates" or other 0.000
necessary approvals. The Contractor shall be responsible for the 0.000
protection of all existing services within the Site or their relocation 0.000
(permanent or temporary) as may be required and shall make 0.000
good any damage to existing services resulting from his carrying 0.000
out of the Works to the satisfaction of the Engineer and any 0.000
relevant Authority. Sum 1 165612.110 165612.110
0.000
0.000
0.000
Traffic Management 0.000
0.000
B The Contractor is to allow for all Traffic Management in and around 0.000
the Site and observe all traffic regulations and the Tender is 0.000
deemed include for strict compliance therewith. Sum 1 67065.050 67065.050
0.000
0.000
0.000
0.000
Utility Protection 0.000
0.000
C The Contractor is to allow for the protection of all Utilities at Doha 0.000
Peninsula and Shuwaikh Port areas as identified and detailed 0.000
in the Specification. Sum 1 164258.410 164258.410
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 396935.570


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 Add (d/1/11 - AD1)

NUMBER ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT


KD KUWAITI DINARS
. 0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
0.000
A Overhead Cameras Sum 1 2387.520 2387.520
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2387.520


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 GENERAL ITEMS d 1 R (d/1/11 - AD1)

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 1 - GENERAL ITEMS

PART SUMMARY

Page d/1/1 5911897.760

Page d/1/2 1070869.490

Page d/1/3 1864831.030

Page d/1/4 5022816.260

Page d/1/5 420789.130

Page d/1/6 16964399.970

Page d/1/7 10497751.810

Page d/1/8 3065760.340

Page d/1/9 5005134.180

Page d/1/10 396935.570

Page d/1/11 2387.520

Total for Part 1 - General Items,


carried to Grand Summary 50223573.060
PART 2

GROUND INVESTIGATION
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Ground Investigation d 2 d/2/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 2 - Ground Investigation 0.000
0.000
The contractor is required to price 0.000
under this element the complete 0.000
Ground Investigation Works 0.000
including all Trial Pits, Trenches, 0.000
Boreholes, Samples, Site Tests 0.000
and Observations, Instrumental 0.000
Observations, Laboratory Tests 0.000
and Professional Services 0.000
0.000
A Allow for all Ground Investigation and 0.000
requiredas
Testing for the whole of the Works B900 Sum 1 1624456.560 1624456.560
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1624456.560


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Ground Investigation d 2 d/2/2

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 2 - Ground investigation

PART SUMMARY

Page d/2/1 1624456.560

Total for Part 2 - Ground Investigation


carried to Grand Summary 1624456.560
PART 3

GEOTECHNICAL AND OTHER SPECIALIST


PROCESSES
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Geotechnical and d 3 d/3/1
Other Specialist Processes

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
PART 3 - Geotechnical and Other 0.000
Specialist Processes 0.000
0.000
The Contractor is required to price 0.000
under this element the complete 0.000
Geotechnical and Other Specialist 0.000
Processes for altering the 0.000
properties of soils and rocks 0.000
and Other Processes including 0.000
drilling, grouting, Diaphragm Walls, 0.000
Ground Anchorages and drains 0.000
This should also include for any 0.000
treatment for Hydrogen Sulphide as 0.000
included in Document I-11 of 0.000
Instruction to Tenderers 0.000
0.000
A Allow for all Geotechnical and Other C900 Sum 1 33532.520 33532.520
Specialist Processes as required for the 0.000
whole of the Works 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 33532.520


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Geotechnical and d 3 d/3/2
Other Specialist Processes

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 3 - Geotechnical and Other Specialist Processes

PART SUMMARY

Page d/3/1 33532.520

Total for Part 3 - Geotechnical and Other Specialist Processes


carried to Grand Summary 33532.520
PART 4

DEMOLITION AND SITE CLEARANCE


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Demolition and d 4 d/4/1
Site Clearance

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 4 - Demolition and Site Clearance 0.000
0.000
The contractor is required to price 0.000
under this element the complete 0.000
Demolition and Site Clearance 0.000
including removal of natural, 0.000
and artificial articles, objects 0.000
and obstructions which are above 0.000
the Original Surface including 0.000
General clearance, Trees, 0.000
Stumps, Buildings, other structures 0.000
and pipelines etc 0.000
0.000
A Allow for all Demolition and Site Clearance 0.000
required for the whole of the Works
as D900 Sum 1 736076.490 736076.490
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 736076.490


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 Demolition and d 4 d/4/2
Site Clearance

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 4 - Demolition and Site Clearance

PART SUMMARY

Page d/4/1 736076.490

Total for Part 4 - Demolition and Site Clearance


carried to Grand Summary 736076.490
PART 5

ENTERTAINMENT CITY INTERCHANGE


- CIVIL WORKS
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 5 - ENTERTAINMENT CITY - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 100000 - 101305 0.000
0.000
EARTHWORKS 0.000
0.000
To Interchange 0.000
0.000
Excavation 0.000
0.000
A Excavation for cutting E220 m3 95,505 0.460 43932.300
0.000
Excavation for cutting for artificial hard
B material E240 m3 0.000
0.000
C Excavation for foundation 2 - 5 m E325 m3 18,116 0.460 8333.360
0.000
D Excavation for foundations in rock, 0.000
2-5m E335 m3 0.000 0.000
0.000
0.000
Excavation Ancillaries 0.000
0.000
Trimming of excavated surfaces other than
E rock E512 m2 239,721 0.010 2397.210
0.000
Preparation of excavated surfaces other
F than rock E522 m2 5,519 1.070 5905.330
0.000
G Preparation of excavated surfaces in rock E523 m2 0.000
0.000
H Disposal of excavated surplus material 75,749 1.810 137105.690
to approved tip E532 m3 0.000
0.000
I Disposal of excavated material; rock E533 m3 0.000
Disposal of excavated artificial hard 0.000
J material E534 m3 0.000
0.000
0.000
Filling 0.000
0.000
K Filling to structures, imported natural 0.000
material other than top soil or rock E615 m3 9,949 6.600 65663.400
0.000
L Filling embankments with selected 0.000
excavated material other than top soil 0.000
or rock E624 m3 47,752 1.310 62555.120
0.000
M Filling embankments with imported natural
material other than rock E625 m3 395,702 3.200 1266246.400
0.000

N Crushed rock slope protection 500 mm thick E647 m3 0.000


0.000
0.000
Filling Ancillaries 0.000
0.000
O Trimming of filled surfaces, 10° - 45°,
inclined to the horizontal E712 m2 0.000
0.000
P Preparation of filled surfaces, 10 - 45° 0.000
inclined to the horizontal E722 m2 0.000
0.000
0.000
Q Geotextile, heavy duty E730.1 m2 0.000
0.000
R Geotextile 320g/m2 E730.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1592138.810


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 2,222 27.010 60016.220
0.000
B Concrete Grade 40 MPa F283 m3 15,180 33.810 513235.800
0.000
C Concrete Grade 50 Mpa F293 m3 11,026 37.100 409064.600
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
D Blinding F515 m3 368 5.090 1873.120
0.000
Reinforced 0.000
0.000
E Pile cap/foundation, thickness 0.000
exceeding 500 mm F624.1 m3 9,029 10.760 97152.040
0.000
F Approach slab, thickness 300 - 500 mm F624.2 m3 256 27.120 6942.720
0.000
G Bridge deck 150 - 300 mm F632 m3 10,208 51.260 523262.080
0.000
H Abutment walls, thickness exceeding 0.000
500 mm F644.1 m3 3,783 31.200 118029.600
0.000
I Abutment wing walls, thickness 0.000
exceeding 500 mm F644.2 m3 394 89.680 35333.920
0.000
J Retaining walls, thickness exceeding 500 mm F644.3 m3 361 93.760 33847.360
0.000
K Piers, cross sectional area exceeding 0.000
1 m2 F655 m3 1,344 161.520 217082.880
0.000
L Capping beam thickness exceeding 1 m2 F665 m3 13 192.270 2499.510
0.000
M Bridge box girder, thickness exceeding 500 F680.1 m3 818 5.320 4351.760
0.000
N Parapet edge detail F680.2 m3 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2022691.610


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork 0.000
0.000
A Horizontal (deck/soffit) G315.1 m2 26,902 21.680 583235.360
0.000
B Horizontal (parapet) G315.2 m2 0.000
0.000
C Sloping (face of abutment/wing wall) G325 m2 453 15.760 7139.280
0.000
D Vertical (deck) 0.2 - 0.4m G343 m2 18,920 21.680 410185.600
0.000
E Vertical (edge of approach slab) 0.4 - 1.22m G344 m2 104 122.230 12711.920
0.000
F Vertical (sides of foundation/pile caps) G345.1 m2 2,905 25.140 73031.700
0.000
G Vertical (unexposed face of abutment G345.2 m2 2,302 15.900 36601.800
wall) 0.000
0.000
H Vertical (face of abutment/wing wall) G345.3 m2 2,875 15.830 45511.250
0.000
I Vertical (pier/cross beam) G345.4 m2 40 66.300 2652.000
0.000
J Vertical (retaining wall) G345.5 m2 671 33.520 22491.920
0.000
K Curved G360 m2 0.000
0.000
L Pier, 2.00 m diameter G382 m 428 306.200 131053.600
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
M Diameter 8 mm - 40 mm G549 t 4,023 335.710 1350561.330
0.000
Stainless steel deformed bars Grade 60 0.000
ASTM A 955/955M 0.000
0.000
N Diameter 12 mm - 40 mm G539 t 0.000
0.000
0.000
Joints 0.000
0.000
O Bridge deck expansion joint complete 0.000
as detailed on drawing G690.1 m 254 844.320 214457.280
0.000
P Expansion joint to retaining wall G690.2 m 27 2.340 63.180
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2889696.220


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES (CONT'D) 0.000
0.000
Post-tensioned prestressing 0.000
0.000
Post-tensioned prestressing of bridge 0.000
deck box section girders complete 0.000
in accordance with the drawings and 0.000
specification including low relaxation 0.000
prestressing strands in accordance 0.000
with the specification including all ducts 0.000
anchorages, couplers and grouting 0.000
0.000
A Horizontal/inclined internal tendons 0.000
in precast concrete (….. tonnes) G739 Sum 218 771.210 168123.780
0.000
B Post-tensioning bars G750 Sum 225 576.430 129696.750
0.000
0.000
Concrete Accessories 0.000
0.000
C Finishing of top surfaces of bridge deck G813 m2 13,501 3.190 43068.190
0.000
0.000
Cathodic Protection 0.000
0.000
D Provision for later implementation of
Cathodic Protection G900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 340888.720


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
HDPE pipes or other approved 0.000
perforated or slotted, diameter 200 0.000
stormwater drain in trenches 0.000
0.000
A Depth not exceeding 1.0 m I512 m 0.000
0.000
HDPE pipes medium class or other approved, 0.000
diameter 250 mm with suitable 0.000
couplings, stormwater culvert in trenches 0.000
0.000
B Depth not exceeding 1.5 m I922 m 0.000
0.000
C Depth 1.5 - 2 m I923 m 0.000
0.000
D Depth 2 - 2.5 m I924 m 0.000
0.000
HDPE pipes medium class or other approved, 0.000
diameter 600 mm with suitable 0.000
couplings, stormwater culvert in trenches 0.000
0.000
E Depth 1.5 - 2 m I943 m 0.000
0.000
0 0 0 0 0
Stormwater drainage system for bridge deck
water discharge to Entertainment City
Interchange Bridges 0.000
Drainage pipe system from scupper to 0.000
F ground level discharge including all pipes,
fittings, support and decorative coatings
etc. 1900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Manholes 0.000
0.000
A Insitu concrete, depth not exceeding 2 m, 0.000
complete including heavy duty cover K132 nr 0.000
0.000
0.000
0.000
French drains, rubble drains, ditches 0.000
and trenches 0.000
0.000
B Filling granular material including bedding 0.000
in accordance with Specification K410 m3 0.000
0.000
0.000
C Soakaway, overall size 2 x 2 x 1 m deep, 0.000
filled with single size loose stone K420 nr 0.000
0.000
0.000
D Geotextile filter fabric as specified K490 m2 0.000
0.000
0.000
Gullies 0.000
Scupper grating/chainage outlet 900 x 500
E mm in 0.000
stainless steel cast into bridge deck K390 Sum 1 13382.160 13382.160
complete
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 13382.160


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - SUPPORTS AND 0.000
PROTECTION, ANCILLARIES TO 0.000
LAYING AND EXCAVATION 0.000
0.000
Beds and Surrounds 0.000
0.000
A Blinding concrete class 20/20, thickness 0.000
100 mm L340 m3 0.000
0.000
B Selected excavated material bed and 0.000
surround to pipe diameter 250 mm L522 m 0.000
0.000
C Reinforced concrete class 40/20 bed 0.000
and surround to pipe diameter 600 mm 0.000
including formwork and reinforcement L554 m 0.000
0.000
D Sand layer thickness 500 mm above 0.000
item L554 L590 m 0.000
0.000
0.000
Precast reinforced concrete protection 0.000
slabs placed above pipelines as detailed 0.000
on drawings 0.000
0.000
E 1000 x 1000 x 150 mm thick L900 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge bearings as detailed on the 0.000
drawings 0.000
0.000
A Bearing complete installed on pier 0.000
including grout pad N267 nr 102 1737.500 177225.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 177225.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge piles commencing surface
level to be agreed with Engineer on site 0.000
0.000
Isolated steel, driven piles, high strength low
alloy structural steel to ASTM A7009 Grade
50 0.000
0.000
Diameter 1219 mm vertical 0.000
0.000
A Number of piles, (total length ………………
m) including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1219 mm diameter with
concrete grade ……….. Q537 m 0.000
0.000
B Cutting off surplus length, 1219 mm diamete Q577 m 0.000
0.000
C Preparing heads, 1219 mm diameter as
detailed on drawing Q587 nr 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM
Grade 60 0.000
0.000
Straight bars, nominal size 12 - 40 mm
D Q219.1 t 0.000
diameter
0.000
E Helical bars not exceeding 14 mm diameter Q219.2 t 0.000
0.000
0.000
Pile tests for 1219 mm diameter, piles 0.000
0.000
F Pile testing as specification including
provision / construction and installation of
necessary test piles and pilot piles Q860 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
0.000
0.000
(To be inserted by the Tenderer if deemed 0.000
necessary as part of their chosen 0.000
durability strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/12

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
Tanking (below ground structures) 0.000
0.000
A Tanking self adhesive water proof
membrane to buried concrete W239 m2 0.000
0.000
B Protection to waterproof membrane W429 m2 0.000
0.000
Tanking (Above ground structures) 0.000
0.000
C Spray applied waterproofing membrane 0.000
to bridge deck surface W241 m2 13,501 5.010 67640.010
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 67640.010


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 R (d/5/13 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
A Bored Pile Work Sum 1 1109260.310 1109260.310
0.000
0.000
B Slope Protection m2 78,198 6.580 514542.840
0.000
0.000
C Drainage Work Sum 1 1088884.900 1088884.900
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2712688.050


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENTERTAINMENT CITY INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 5 d/5/14

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 5 - ENTERTAINMENT CITY INTERCHANGE - CIVIL WORKS

PART SUMMARY

Page d/5/1 1592138.810

Page d/5/2 2022691.610

Page d/5/3 2889696.220

Page d/5/4 340888.720

Page d/5/5 0.000

Page d/5/6 13382.160

Page d/5/7 0.000

Page d/5/8 177225.000

Page d/5/9 0.000

Page d/5/10 0.000

Page d/5/11 0.000

Page d/5/12 67640.010

Page d/5/13 2712688.050

Total for Part 5- Entertainment City Interchange - Civil Works,


carried to Grand Summary 9816350.580
PART 6

DOHA PENINSULA ROAD - CIVIL WORKS


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 6 - DOHA PENINSULA ROAD - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 101305 - 103090 0.000
0.000
0.000
EARTHWORKS 0.000
0.000
A Excavation for cutting E220 m3 11,338 0.460 5215.480
0.000
B Excavation for culverts E324 m3 15,351 0.460 7061.460
0.000
0.000
Excavation Ancillaries 0.000
Trimming of excavated surfaces other than
C rock E512 m2 88,289 0.010 882.890
0.000
D Preparation of excavated surfaces other
than rock E522 m2 968 1.070 1035.760
0.000
E Disposal of excavated surplus material 0.000
to approved tip E532 m3 0.000
0.000
F Disposal of unsuitable material to 0.000
approved dumping area E535 m3 24,174 1.810 43754.940
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 57950.530


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
EARTHWORKS (CONT'D) 0.000
0.000
Filling 0.000
0.000
A Filling to structures imported natural
material other than top soil or rock E615 m3 10,208 6.600 67372.800
Filling embankment with selected 0.000
B excavated material other than top soil or
rock E624 m3 5,669 1.310 7426.390
0.000
C Filling embankment with imported natural
material other than rock E625 m3 50,103 3.200 160329.600
0.000
D Crushed rock slope protection 500 mm thick E647 m3 0.000
0.000
Filling Ancillaries 0.000
0.000
E Trimming filled surfaces 10° - 45°inclined to
the horizontal E712 m2 0.000
0.000
F Preparation of filled surfaces to receive 0.000
permanent work E722 m2 0.000
0.000
G Geotextile, heavy duty E730.1 m2 0.000
0.000
H Geotextile 320g/m2 E730.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 235128.790


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Culverts/Bridge Girder 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 396 27.010 10695.960
0.000
B Concrete Grade 40 MPa F283 m3 3,220 33.810 108868.200
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
C Blinding thickness, not exceeding 150mm 0.000
F511 m3 396 3.200 1267.200
0.000
Reinforced 0.000
0.000
D Culvert F622 m3 538 13.410 7214.580
0.000
E Pile caps, thickness exceeding 0.000
500 mm F624.1 m3 1,700 18.480 31416.000
0.000
F Ground slab, thickness exceeding 500 mm F624.2 m3 3,087 12.160 37537.920
0.000
G Approach slab thickness 300 - 500 mm F624.3 m3 74 21.160 1565.840
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 198565.700


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork 0.000
0.000
A Horizontal G315 m2 3,792 27.080 102687.360
0.000
B Vertical G345 m2 8,838 13.620 120373.560
0.000
C Curved G360 m2 57 14.130 805.410
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Diameter 8 mm - 40 mm G549 t 782 315.090 246400.380
0.000
0.000
Joints 0.000
0.000
E Expansion joint complete, including water 0.000
stop, joint filter board, sealant, dowels 0.000
and formwork G690 m 61 848.500 51758.500
0.000
0.000
Concrete Accessories 0.000
0.000
F Finishing of top surfaces of concrete slabs G813 m2 2,306 3.740 8624.440
0.000
0.000
Cathodic Protections 0.000
0.000
G Provision for later implementation of
Cathodic Protection G900 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 530649.650


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
HDPE pipes or other approved, perforated
or slotted diameter 200 stormwater drain in
trenches, 0.000
0.000
0.000
0.000
A Depth not exceeding 1.0 m I512 m 0.000
0.000
HDPE pipes medium class or other
approved, diameter 250 mm with suitable
couplings, stormwater drain in trenches 0.000
0.000
0.000
0.000
B Depth not exceeding 1.5 m I922 m 0.000
0.000
C Depth 1.5 - 2 m I923 m 0.000
0.000
D Depth 2 - 2.5 m I924 m 0.000
0.000
HDPE pipes medium class or other
approved, diameter 600mm with suitable
couplings, stormwater culvert in trenches 0.000
0.000
E Depth 1.5 - 2.0 m I943 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Manholes 0.000
0.000
A Insitu concrete, depth not exceeding 2 m, 0.000
complete including heavy duty cover K132 nr 0.000
0.000
0.000
0.000
French drains, rubble drains, ditches 0.000
and trenches 0.000
0.000
B Filling granular material including 0.000
bedding in accordance with 0.000
Specification K410 m3 0.000
0.000
C Soakaway, overall size 2 x 2 x 1 m deep, 0.000
filled with single size loose stone K420 nr 0.000
0.000
0.000
D Geotextile filter fabric as specified K490 m2 0.000
0.000
0.000
PIPEWORK - SUPPORTS AND 0.000
PROTECTION, ANCILLARIES TO 0.000
LAYING AND EXCAVATION 0.000
0.000
Beds and Surrounds 0.000
0.000
E Selected excavated material bed and 0.000
surround to pipe diameter 250 mm L522 m 0.000
0.000
F Reinforced concrete class 40/20 bed and
surround to pipe diameter 600mm including
formwork and reinforcement L554 m 0.000
0.000
G Sand layer thickness 500mm above item L5 L590 m 0.000
0.000
0.000
Precast reinforced concrete protection slabs
placed above pipelines as detailed on
drawings 0.000
0.000
H 1000 x 1000 x 150mm thick L900 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge crossing over outfall pipes 0.000
commencing surface level to be 0.000
agreed with Engineer on site for each 0.000
location 0.000
0.000
Isolated steel, driven piles, high strength 0.000
low alloy structural steel to ASTM A7009 0.000
Grade 50 0.000
0.000
Diameter 1219 mm vertical 0.000
0.000
A Number of piles (total length …..m) 0.000
including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1,219 mm diameter 0.000
with concrete grade Q537 m 0.000
0.000
B Cutting off surplus length, 1,219 mm 0.000
diameter Q577 m 0.000
0.000
C Preparing heads, 1,219 mm diameter 0.000
as detailed on the drawings Q587 nr 0.000
0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Straight bars, nominal size 8 - 40 mm 0.000
diameter Q219.1 t 0.000
0.000
E Helical bars not exceeding 20 mm 0.000
diameter Q219.2 t 0.000
0.000
0.000
Pile Tests for 1219 mm diameter piles 0.000
0.000
F Pile testing as specifications including
provision construction and installation of
necessary test piles and pilot piles Q860 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
0.000
(To be inserted by the Tenderer if deemed 0.000
necessary as part of their chosen durability 0.000
strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
Tanking (Below Ground Structure) 0.000
0.000
A Tanking self adhesive water proof
membrane to buried concrete W239 m2 0.000
0.000
B Protection to waterproof membrane W429 m2 0.000
0.000
Tanking (Above ground Structure) 0.000
0.000
C Spray applied waterproofing membrane 0.000
to bridge crossing over outfall pipes deck 0.000
surfacing W241 m2 2,306 5.010 11553.060
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 11553.060


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 R (d/6/11 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 50 MPa F283 m3 2,180 37.100 80878.000
0.000
0.000
Concrete Ancillaries 0.000
0.000
Post-tensioned prestressing 0.000
0.000
B Horizzontal/inclined internal tendons in prec G739 t 118 416.310 49124.580
0.000
C Post-tensioning bars G750 t 122 382.840 46706.480
0.000
0.000
Miscellaneous Metal Work 0.000
0.000
Bridge bearings as detailed on the drawings 0.000
0.000
D Bearing complete installed on pier including N267 nr 8 1525.040 12200.320
0.000
0.000
E Bored Pile Work Sum 1 372921.440 372921.440
0.000
0.000
F Slope Protection m2 21,896 6.580 144075.680
0.000
0.000
G Ditch Work Sum 1 424590.940 424590.940
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1130497.440


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA PENINSULA ROAD
VOLUME III - DOC.III.5 CIVIL WORKS d 6 d/6/12

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 6 - DOHA PENINSULA ROAD - CIVIL WORKS

PART SUMMARY

Page d/6/1 57950.530

Page d/6/2 235128.790

Page d/6/3 198565.700

Page d/6/4 530649.650

Page d/6/5 0.000

Page d/6/6 0.000

Page d/6/7 0.000

Page d/6/8 0.000

Page d/6/9 0.000

Page d/6/10 11553.060

Page d/6/11 1130497.440

Total for Part 6 - Doha Peninsula Road - Civil Works,


carried to Grand Summary 2164345.170
PART 7

DOHA INTERCHANGE - CIVIL WORKS


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 7 - DOHA INTERCHANGE - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 103090 - 104710 0.000
0.000
EARTHWORKS 0.000
0.000
To Interchange 0.000
0.000
Excavation 0.000
0.000
A Excavation for cutting E220 m3 21,811 0.460 10033.060
0.000
B Excavation for foundation 2-5m E325 m3 23,503 0.460 10811.380
0.000
C Excavation for foundations in rock, 0.000
2-5m E335 m3 0.000
0.000
0.000
Excavation Ancillaries 0.000
0.000
D Trimming of excavated surfaces other E512 m2 154,235 0.010 1542.350
than rock 0.000
0.000
E Preparation of excavated surfaces E522 m2 11,608 1.070 12420.560
other than rock 0.000
0.000
F Preparation of excavated surfaces in rock E523 m2 0.000
0.000
G Disposal of excavated surplus material 0.000
to approved tip E532 m3 42,408 1.810 76758.480
0.000
H Disposal of excavated material; rock E533 m3 0.000
0.000
0.000
Filling 0.000
0.000
I Filling to structures selected excavated E614 m3 10,044 6.600 66290.400
material other than rock 0.000
0.000
J Filling to structures, imported natural 0.000
material other than top soil or rock E615 m3 0.000
0.000
K Filling embankments with selected 0.000
excavated material other than top soil 0.000
or rock E625.1 m3 308,108 3.200 985945.600
0.000
L Filling embankments with imported natural E625 m3 0.000
material other than rock 0.000
0.000
0.000
0.000
Filling Ancillaries 0.000
0.000
M Preparation of filled surfaces, 10 - 45° 0.000
inclined to the horizontal E722.1 m2 0.000
0.000
N Preparation of filled surfaces E722.2 m2 0.000
0.000
0.000
0.000
O Geotextile; heavy duty E730.1 m2 0.000
0.000
P Geotextile 320g/m2 E730.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1163801.830


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 774 27.010 20905.740
0.000
B Concrete Grade 40 MPa F283 m3 23,354 33.810 789598.740
0.000
C Concrete Grade 50 Mpa F293 m3 2,124 37.100 78800.400
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
D Blinding thickness, not exceeding 150mm F511 m3 774 6.070 4698.180
0.000
Reinforced 0.000
0.000
E Approach slab thickness 300-500mm F623 m3 73 28.170 2056.410
0.000
F Pile cap/foundation, thickness 0.000
exceeding 500 mm F624.1 m3 2,295 13.780 31625.100
0.000
G Wing wall base slabs, thickness exceeding
500 mm F624.2 m3 18,683 10.020 187203.660
0.000
H Abutment walls, thickness exceeding 0.000
500 mm F643 m3 1,222 32.180 39323.960
0.000
I Abutment wing walls, thickness 0.000
exceeding 300 mm F644 m3 140 116.870 16361.800
0.000
J Piers, cross sectional area exceeding 0.000
1 m2 F655 m3 391 173.970 68022.270
0.000
K Pier crosshead beam F680 m3 550 125.770 69173.500
0.000
L Deck slab F780 m3 2,124 11.100 23576.400
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1331346.160


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork 0.000
0.000
A Horizontal, width exceeding 1.22 m,
Crosshead beam G315.1 m2 193 179.230 34591.390
0.000
B Horizontal, width exceeding 1.22m, Deck sla G315.2 m2 1,848 45.060 83270.880
0.000
C Vertical width 0.2 - 0.4 m approach slab G343.1 m2 34 214.430 7290.620
0.000
D Vertical width 0.2 - 0.4 m deck slab G343.2 m2 1,034 44.650 46168.100
0.000
E Vertical width 0.4 - 1.22 abutment/ 0.000
retaining walls G344.1 m2 19,391 8.000 155128.000
0.000
F Vertical width 0.4 - 1.22m, wing walls G344.2 m2 362 31.210 11298.020
0.000
G Vertical width exceeding 1.22 m wing walls G345.1 m2 0.000
0.000
H Vertical width exceeding 1.22 m abutments/ 0.000
retaining walls G345.2 m2 5,257 8.320 43738.240
0.000
I Vertical width exceeding 1.22 m pilecaps G345.3 m2 879 27.120 23838.480
0.000
J Vertical width exceeding 1.22 m crosshead
beam G345.4 m2 40 177.120 7084.800
0.000
K Pier 2.0 m diameter G382 m 125 314.620 39327.500
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
L Diameter 8 mm - 40 mm G549 t 3,030 261.580 792587.400
0.000
0.000
0.000
Joints 0.000
0.000
M Bridge deck expansion joint complete 0.000
as detailed on drawing G690 m 64 874.310 55955.840
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1300279.270


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES (CONT'D) 0.000
0.000
Post-tensioned prestressing 0.000
0.000
Post-tensioned prestressing of bridge 0.000
deck box section girders complete 0.000
in accordance with the drawings and 0.000
specification including low relaxation 0.000
prestressing strands in accordance 0.000
with the specification including all ducts 0.000
anchorages, couplers and grouting 0.000
0.000
A Horizontal/inclined internal tendons 0.000
in precast concrete (….. tonnes) G739 nr 70 904.530 63317.100
0.000
B External jacking operations G750 nr 70 1657.480 116023.600
0.000
0.000
Concrete Accessories 0.000
0.000
C Finishing of top surfaces of bridge deck G813.1 m2 5,508 1.750 9639.000
0.000
D Finishing top surface of pile caps G813.2 m2 0.000
0.000
E Grouting under bearing plates, non-shrink 0.000
cementitious grout, 0.1 - 0.5 m2 G842 nr 140 251.750 35245.000
0.000
F Provision for the later implementations 0.000
of Cathodic Protection to piers G900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 224224.700


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
0.000
PRECAST CONCRETE 0.000
0.000
Concrete Grade 50 MPa 0.000
0.000
A Prestressed pre and post tensioned beams,
approx dims: 30m long, mass of 55 tonnes,
curved in plan H998.1 nr 28 4568.560 127919.680
0.000
B Prestressed pre and post tensioned beams,
approx dims: 40m long, mass of 70 tonnes, H998.2 nr 42 4568.560 191879.520
curved in plan 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 319799.200


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
HDPE pipes or other approved, 0.000
perforated or slotted, diameter 200 0.000
stormwater drain in trenches 0.000
0.000
A Depth not exceeding 1.0 m I512 m 0.000
0.000
HDPE pipes medium class or other approved, 0.000
diameter 250 mm with suitable 0.000
couplings, stormwater culvert in trenches 0.000
0.000
B Depth not exceeding 1.5 m I922 m 0.000
0.000
C Depth 1.5 - 2 m I923 m 0.000
0.000
D Depth 2 - 2.5 m I924 m 0.000
0.000
HDPE pipes medium class or other approved, 0.000
diameter 600 mm with suitable 0.000
couplings, stormwater culvert in trenches 0.000
0.000
E Depth 1.5 - 2 m I943 m 0.000
0.000
0.000
0.000
Stormwater drainage system for bridge 0.000
deck water discharge to section of 0.000
Doha Interchange 0.000
0.000
F Drainage pipe system from scupper to 0.000
ground level discharge, including all 0.000
pipes, fittings, supports, protective and 0.000
decorative coatings etc. as detailed on 0.000
drawings I900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Manholes 0.000
0.000
A Insitu concrete, depth not exceeding 2 m, 0.000
complete including heavy duty cover as 0.000
detailed on drawings K132 nr 0.000
0.000
0.000
French drains, rubble drains, ditches 0.000
and trenches 0.000
0.000
B Filling granular material including bedding 0.000
in accordance with Specification K410.1 m3 0.000
0.000
0.000
C Soakaway, overall size 2 x 2 x 1 m deep, 0.000
filled with single size loose stone rip-rap, 0.000
100 mm to 150 mm K420.1 nr 0.000
0.000
D Geotextile filter fabric as specified K490 m2 0.000
0.000
0.000
Gullies 0.000
0.000
E Scupper grating/drainage outlet 0.000
900 x 500 mm in stainless steel cast into 0.000
bridge deck complete as detailed on the 0.000
drawings K390 Sum 1 4014.650 4014.650
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 4014.650


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - SUPPORTS AND 0.000
PROTECTION, ANCILLARIES TO 0.000
LAYING AND EXCAVATION 0.000
0.000
Beds and Surrounds 0.000
0.000
A Blinding concrete class 20/20, thickness 0.000
100 mm L340 m3 0.000
0.000
B Selected excavated material bed and 0.000
surround to pipe diameter 250 mm L522 m 0.000
0.000
C Reinforced concrete class 40/20 bed 0.000
and surround to pipe diameter 600 mm 0.000
including formwork and reinforcement L554 m 0.000
0.000
D Sand layer thickness 500 mm above 0.000
item L554 L590 m 0.000
0.000
0.000
Precast reinforced concrete protection 0.000
slabs placed above pipelines as detailed 0.000
on drawings 0.000
0.000
E 1000 x 1000 x 150 mm thick L900 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge bearings as detailed on the 0.000
drawings 0.000
0.000
A Bearing complete installed on pier 0.000
including grout pad N267 nr 140 650.540 91075.600
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 91075.600


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge piles commencing 0.000
surface level to be agreed with Engineer 0.000
on site 0.000
0.000
Isolated steel, driven piles, high strength 0.000
low alloy structural steel to ASTM A7009 0.000
Grade 50 0.000
0.000
Diameter1219 mm vertical 0.000
0.000
A Number of piles (total length ………. m) 0.000
including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1219 mm diameter 0.000
with concrete grade ………. Q537 m 0.000
0.000
B Cutting off surplus length, 1219 mm 0.000
diameter Q577 m 0.000
0.000
C Preparing heads, 1219 mm diameter 0.000
as detailed on the drawings to foundation 0.000
Type 1 Q587 nr 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Straight bars, nominal size 12-40 mm Q219.1 t 0.000
diameter 0.000
0.000
E Helical bars not exceeding 14 mm diameter Q219.2 t 0.000
0.000
0.000
0.000
Pile tests for 1524 mm diameter, piles 0.000
0.000
F Pile testing as specification including 0.000
provision/construction and installation 0.000
of necessary test piles and pilot piles Q860 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/12

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
0.000
(To be inserted by the Tenderer if deemed 0.000
necessary as part of their chosen 0.000
durability strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/13

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
Tanking (below ground structures) 0.000
0.000
A Self adhesive waterproof membrane 0.000
to buried concrete W239 m2 0.000
0.000
B Protection to waterproof membrane W429 m2 0.000
0.000
0.000
0.000
Tanking (above ground structures) 0.000
0.000
C Spray applied waterproofing membrane 0.000
to bridge deck surface W500.1 m2 5,508 5.010 27595.080
0.000
0.000
0.000
Miscellaneous Works 0.000
0.000
D Weighbridge and associated works 0.000
complete as specification, drawings and 0.000
Employers Requirements X990 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 27595.080


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 R (d/7/14 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
A Bored Pile Work Sum 1 387392.840 387392.840
0.000
0.000
B Slope Protection m2 45,174 6.580 297244.920
0.000
0.000
C Drainage Works Sum 1 481956.420 481956.420
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1166594.180


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 DOHA INTERCHANGE
VOLUME III - DOC.III.5 CIVIL WORKS d 7 d/7/15

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 7 - DOHA INTERCHANGE - CIVIL WORKS

PART SUMMARY

Page d/7/1 1163801.830

Page d/7/2 1331346.160

Page d/7/3 1300279.270

Page d/7/4 224224.700

Page d/7/5 319799.200

Page d/7/6 0.000

Page d/7/7 4014.650

Page d/7/8 0.000

Page d/7/9 91075.600

Page d/7/10 0.000

Page d/7/11 0.000

Page d/7/12 0.000

Page d/7/13 27595.080

Page d/7/14 1166594.180

Total for Part 7- Doha Interchange - Civil Works,


carried to Grand Summary 5628730.670
PART 8

APPROACH BRIDGE WEST - CIVIL WORKS


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 8 - APPROACH BRIDGE WEST - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 104710 to 109930 0.000
0.000
EARTHWORKS 0.000
0.000
To Pile Caps 0.000
0.000
Excavation 0.000
0.000
A Excavation for foundation, 2 - 5 m E325 m3 708 0.460 325.680
0.000
B Excavation for foundations in rock, 0.000
2-5m E335 m3 0.000
0.000
0.000
Excavation Ancillaries 0.000
0.000
C Preparation of excavated surfaces 0.000
other than rock E522 m2 262 1.070 280.340
0.000
D Preparation of excavated surfaces in rock E523 m2 0.000
0.000
E Disposal of excavated surplus material 0.000
to approved tip E532 m3 361 1.810 653.410
0.000
F Disposal of excavated material; rock E533 m3 0.000
0.000
0.000
Filling 0.000
0.000
G Filling to structures, selected excavated 0.000
material other than top soil or rock E614 m3 199 1.310 260.690
0.000
Behind Abutment 0.000
0.000
H Filling embankments with imported natural E625 m3 695 3.200 2224.000
material other than rock 0.000
0.000
0.000
I Geotextile; heavy duty E730.1 m2 1,044 0.880 918.720
0.000
J Geotextile 320g/m2 E730.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 4662.840


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 12 27.010 324.120
0.000
B Concrete Grade 40 MPa F283 m3 11,829 33.810 399938.490
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
C Blinding thickness, not exceeding 150mm F511 m3 12 5.050 60.600
0.000
Reinforced 0.000
0.000
D Approach slab, thickness 300 - 500 mm F623 m3 37 4.260 157.620
0.000
E Pile cap, thickness exceeding 500 mm F624 m3 411 10.490 4311.390
0.000
F Abutment/Retaining wall, thickness 0.000
exceeding 500 mm F643 m3 529 12.440 6580.760
0.000
G Abutment wing walls, thickness 0.000
300-500 mm F644 m3 52 15.370 799.240
0.000
H Piers, cross sectional area exceeding 0.000
1 m2 Type I F655.1 m3 4,122 105.990 436890.780
0.000
I Piers, cross sectional area exceeding 1m2 0.000
Type II F655.2 m3 1,890 50.810 96030.900
0.000
J Pier head Type I F680.1 m3 3,810 148.480 565708.800
0.000
K Pier head Type II F680.2 m3 965 108.520 104721.800
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1615524.500


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork 0.000
0.000
A Vertical width 02-0.4 wing walls G343.1 m2 0.000
0.000
B Vertical width 0.2-0.4 approach slab G345.2 m2 85 6.620 562.700
0.000
C Vertical width exceeding 1.22mm wing walls G345.1 m2 140 13.380 1873.200
0.000
D Vertical width exceeding 1.22m 0.000
abutment/retaining walls G345.2 m2 668 14.220 9498.960
0.000
E Vertical width exceeding 1.22m pilecaps G345.3 m2 210 9.450 1984.500
0.000
F Pier, 2.50 m diameter (Type I) G382.1 m 1,473 275.100 405222.300
0.000
G Pier, (Type II) G382.2 m 218 397.410 86635.380
0.000
H Pier head, 2.50 mm diameter at base 0.000
increasing to 2.5 x 5.38 m overall at head, 0.000
overall height 2.3 m, as detailed on the 0.000
drawings (TYPE I) G394.1 nr 226 1841.230 416117.980
0.000
I Pier head (Type II) G394.2 nr 32 2589.290 82857.280
0.000
0.000
Formwork - Precast Concrete 0.000
0.000
J Vertical; width exceeding 1. ,pilecaps G490.1 m2 0.000
0.000
K Horizontal; width exceeding 1.22m, pilecaps G490.2 m2 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
L Diameter 12 mm - 40 mm G549 t 1,680 249.610 419344.800
0.000
Stainless steel deformed bars Grade 60 0.000
ASTM A 955/955M 0.000
0.000
M Diameter 12 mm - 40 mm G539 t 467 1364.120 637044.040
0.000
0.000
Joints 0.000
0.000
N Bridge deck expansion joint complete 0.000
as detailed on drawing G690 m 544 1013.980 551605.120
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2612746.260


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES (CONT'D) 0.000
0.000
Post-tensioned prestressing 0.000
0.000
Post-tensioned prestressing of bridge 0.000
deck box section girders complete 0.000
in accordance with the drawings and 0.000
specification including low relaxation 0.000
prestressing strands in accordance 0.000
with the specification including all ducts 0.000
anchorages, couplers and grouting 0.000
0.000
A Horizontal/inclined internal tendons 0.000
in precast concrete (…….. tonnes) G739 nr 226 4022.500 909085.000
0.000
B External jacking operations G750 nr 226 3534.630 798826.380
0.000
0.000
Concrete Accessories 0.000
0.000
C Finishing of top surfaces of bridge deck G813.1 m2 176,120 1.410 248329.200
0.000
0.000
Cathodic Protection 0.000
0.000
D Finishing top surface of pile caps G813.2 m2 0.000
0.000
E Grouting under bearing plates, non-shrink 0.000
cementitious grout, 0.1-0.5m2 G842 nr 588 406.580 239069.040
0.000
F Provision for the later implementation of 0.000
Cathodic Protection to piers G900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2195309.620


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PRECAST CONCRETE 0.000
0.000
Concrete Grade 50 MPa 0.000
0.000
Note : 0.000
0.000
The descriptions/quantities provided 0.000
below are for a typical one metre length 0.000
of bridge box girder. The precast 0.000
concrete girders are constructed in 0.000
varying widths/type and the Contractor 0.000
shall make due allowance in his pricing 0.000
0.000
A Bridge box girder overall cross section 0.000
dimensions 17,000 mm wide x 2,500 mm 0.000
depth including post tensioning to bridge 0.000
deck slab all as detailed on the drawings H900.1 m 10,220 2102.250 21484995.000
0.000
0.000
B Allow for closing both ends of bridge box 0.000
girders for post tensioning as detailed on 0.000
the drawings (quantity given is for 0.000
the total number of individual box girder 0.000
elements to Approach Bridge West) H900.2 nr 0.000
0.000
0.000
C Transition Section of Bridge box girder 0.000
overall cross section dimension 17,000 mm 0.000
wide depth increasing from 2500mm to 0.000
3000 mm including transverse post 0.000
tensioning to bridge deck slab as detailed 0.000
on the drawings H900.3 m 200 2849.450 569890.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 22054885.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
Stormwater drainage system for bridge 0.000
deck water discharge to section of 0.000
Approach Bridge West that is overwater 0.000
0.000
A Drainage pipe system from scupper to 0.000
ground level discharge, including all 0.000
pipes, fittings, supports, protective and 0.000
decorative coatings etc. as detailed on 0.000
the drawings I900 Sum 0.000
0.000
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Gullies 0.000
0.000
B Scupper grating/drainage outlet 0.000
900 x 500 mm in stainless steel cast 0.000
into bridge deck complete as detailed 0.000
on the drawings K390 Sum 1 115922.970 115922.970
0.000
0.000
0.000
HDPE or other approved pipes 0.000
perforated or slotted, diameter 200 0.000
stormwater drain in trenches 0.000
0.000
C Depth not exceeding 1.0 m I512 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 115922.970


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge bearings as detailed on the 0.000
drawings 0.000
0.000
A Bearing complete installed on pier 0.000
including grout pad N267 nr 588 3004.070 1766393.160
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1766393.160


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge piles commencing 0.000
surface level to be agreed with Engineer 0.000
on site 0.000
0.000
Isolated steel, driven piles, high strength 0.000
low alloy structural steel to ASTM A7009 0.000
Grade 50 0.000
0.000
Diameter 1524 mm vertical 0.000
0.000
A Number of piles, (total length ……. m) 0.000
including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1524 mm diameter 0.000
with concrete grade ………. Q537 m 0.000
0.000
B Cutting off surplus length, 1524 mm 0.000
diameter Q577 m 0.000
0.000
C Preparing heads, 1524 mm diameter Q587 nr 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Straight bars, nominal size 12 - 40 mm 0.000
diameter Q219.1 t 0.000
0.000
E Helical bars not exceeding 14 mm 0.000
diameter Q219.2 t 0.000
0.000
0.000
Pile tests for 1524 mm diameter, piles 0.000
0.000
F Pile testing as specification including 0.000
provision/construction and installation of 0.000
necessary test piles and pilot piles Q860 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
0.000
(To be inserted by the Tenderer if 0.000
deemed necessary as part of their 0.000
chosen durability strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
Tanking (Above ground structures) 0.000
0.000
A Self adhesive waterproof membrane 0.000
to buried concrete W239 m2 0.000
0.000
B Protection to waterproof membrane W429 m2 0.000
0.000
0.000
Tanking (Above ground structures) 0.000
0.000
C Spray applied waterproofing membrane 0.000
to bridge deck surface W500.1 m2 179,836 5.010 900978.360
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 900978.360


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 R (d/8/12 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
A Bored Pile Work Sum 1 ### 11581089.270
0.000
0.000
B Scour Protection Sum 1 326095.910 326095.910
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 11907185.180


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE WEST
VOLUME III - DOC.III.5 CIVIL WORKS d 8 d/8/13

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 8 - APPROACH BRIDGE WEST - CIVIL WORKS

PART SUMMARY

Page d/8/1 4662.840

Page d/8/2 1615524.500

Page d/8/3 2612746.260

Page d/8/4 2195309.620

Page d/8/5 22054885.000

Page d/8/6 115922.970

Page d/8/7 1766393.160

Page d/8/8 0.000

Page d/8/9 0.000

Page d/8/10 0.000

Page d/8/11 900978.360

Page d/8/12 11907185.180

Total for Part 8 - Approach Bridge West - Civil Works,


carried to Grand Summary 43173607.890
PART 9

MAIN BRIDGE - CIVIL WORKS


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 9 - MAIN BRIDGE - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 109930 to 110530 0.000
0.000
EARTHWORKS 0.000
0.000
To Pile Caps 0.000
0.000
Excavation 0.000
0.000
A Excavation for foundation, 2 - 5 m E325 m3 0.000
0.000
B Excavation for foundations in rock, 0.000
2-5m E335 m3 0.000
0.000
0.000
Excavation Ancillaries 0.000
0.000
C Preparation of excavated surfaces 0.000
other than rock E522 m2 0.000
0.000
D Preparation of excavated surfaces in rock E523 m2 0.000
0.000
E Disposal of excavated surplus material 0.000
to approved tip E532 m3 0.000
0.000
F Disposal of excavated material; rock E533 m3 0.000
0.000
0.000
Filling 0.000
0.000
G Filling to structures, selected excavated 0.000
material other than top soil or rock E614 m3 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 0.000
0.000
B Concrete Grade 40 MPa F283 m3 0.000
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
C Blinding thickness, not exceeding 150mm F511 m3 0.000
0.000
Reinforced 0.000
0.000
D Pile cap, thickness exceeding 500 mm F624.1 m3 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork - Precast Concrete 0.000
0.000
A Vertical; width exceeding 1.22 m, pilecaps G490.1 m2 0.000
0.000
B Horizontal; width exceeding 1.22m, pilecaps G490.2 m2 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
C Diameter 12 mm - 40 mm G549 t 0.000
0.000
0.000
Joints 0.000
0.000
D Bridge deck expansion joint complete 0.000
as detailed on drawing G690 m 136 1250.590 170080.240
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 170080.240


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES (CONT'D) 0.000
0.000
Post-tensioned prestressing 0.000
0.000
Post-tensioned prestressing of bridge 0.000
deck box section girders complete 0.000
in accordance with the drawings and 0.000
specification including low relaxation 0.000
prestressing strands in accordance 0.000
with the specification including all ducts 0.000
anchorages, couplers and grouting 0.000
0.000
A Horizontal/inclined internal tendons 0.000
in precast concrete (…….. tonnes) G739 nr 16 4396.050 70336.800
0.000
B External jacking operations G750 nr 16 14463.960 231423.360
0.000
0.000
Concrete Accessories 0.000
0.000
C Finishing of top surfaces of bridge deck G813.1 m2 20,400 3.200 65280.000
0.000
D Grouting under bearing plates, non-shrink 0.000
cementitious grout, 0.1-0.5m2 G842 nr 48 443.650 21295.200
0.000
E Provision for the later implementation of 0.000
Cathodic Protection to piers G900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 388335.360


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PRECAST CONCRETE 0.000
0.000
Concrete Grade 50 MPa 0.000
0.000
A Precast Pier Type I, approx weight 250t H459.1 nr 0.000
0.000
B Precast Pier Type II, approx weight 375t H459.2 nr 0.000
0.000
Note : 0.000
0.000
The descriptions/quantities provided 0.000
below are for a typical one metre length 0.000
of bridge box girder. The precast 0.000
concrete girders are constructed in 0.000
varying widths/type and the Contractor 0.000
shall make due allowance in his pricing 0.000
0.000
C Bridge box girder overall cross section 0.000
dimensions 17,000 mm wide 4,000 mm 0.000
depth including post tensioning to bridge 0.000
deck slab all as detailed on the drawings H900.1 m 1,200 2406.910 2888292.000
0.000
0.000
D Allow for closing both ends of bridge box 0.000
girders for post tensioning as detailed on 0.000
the drawings (quantity given is for 0.000
the total number of individual box girder 0.000
elements to Main Bridge) H900.2 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2888292.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
Stormwater drainage system for bridge 0.000
deck water discharge to section of 0.000
Main Bridge that is overwater 0.000
0.000
A Drainage pipe system from scupper to 0.000
ground level discharge, including all 0.000
pipes, fittings, supports, protective and 0.000
decorative coatings etc. as detailed on 0.000
the drawings I900 Sum 0.000
0.000
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Gullies 0.000
0.000
B Scupper grating/drainage outlet 0.000
500 x 450 mm in stainless steel cast 0.000
into bridge deck complete as detailed 0.000
on the drawings K390 Sum 1 13382.160 13382.160
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 13382.160


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge bearings as detailed on the 0.000
drawings 0.000
0.000
A Bearing complete installed on pier 0.000
including grout pad N267 nr 48 4197.590 201484.320
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 201484.320


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge piles commencing 0.000
surface level to be agreed with Engineer 0.000
on site 0.000
0.000
Isolated steel, driven piles, high strength 0.000
low alloy structural steel to ASTM A7009 0.000
Grade 50, diameter 1524 mm vertical 0.000
0.000
0.000
0.000
A Number of piles, (total length ……. m) 0.000
including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1524 mm diameter 0.000
with concrete grade ………. Q537 m 0.000
0.000
B Cutting off surplus length, 1524 mm 0.000
diameter Q577 m 0.000
0.000
C Preparing heads, 1524 mm diameter 0.000
as detailed on drawing to foundation 0.000
Type 1 Q587 nr 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Straight bars, nominal size 12 - 40 mm 0.000
diameter Q219.1 t 0.000
0.000
E Helical bars not exceeding 14 mm 0.000
diameter Q219.2 t 0.000
0.000
0.000
Pile tests for 1524 mm diameter, piles 0.000
0.000
F Pile testing as specification including Q860 Sum 0.000
provision/construction and installation 0.000
of necessary test piles and pilot piles 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
0.000
(To be inserted by the Tenderer if 0.000
deemed necessary as part of their 0.000
chosen durability strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
0.000
Tanking (Above ground structures) 0.000
0.000
A Spray applied waterproofing membrane 0.000
to bridge deck surface W500.1 m2 18,360 5.010 91983.600
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 91983.600


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 R (d/9/12 - AD1)
R (d/9/12 - AD2)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any
additional item will be entertained. 0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 40 MPa F283 m3 2,617 33.810 88480.770
0.000
Placing of Concrete 0.000
0.000
B Pier Type I m3 914 70.500 64437.000
C Pier Type II m3 895 39.900 35710.500
D Pier head Type I m3 488 96.020 46857.760
E Pier head Type II m3 320 73.140 23404.800
0.000
Formwork for Pier & Coiping 0.000
0.000
F Pier, (Type I) m 360 141.600 50976.000
G Pier, (Type II) m 188 170.790 32108.520
H Pier head (Type I) nr 16 3892.070 62273.120
I Pier head (Type II) nr 6 4023.490 24140.940
0.000
Reinforcement for Pier & Coiping 0.000
0.000
J Deformed high yield steel bars to ASTM G60 t 391 249.610 97597.510
K Stainless steel deformed bars Grade 60 t 81 1364.120 110493.720
0.000
L Bored Pile Work Sum 1 1861008.550 1861008.550
0.000
0.000
M Scour Protection Sum 1 425422.790 425422.790
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2922911.980


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 MAIN BRIDGE
VOLUME III - DOC.III.5 CIVIL WORKS d 9 d/9/13

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 9 - MAIN BRIDGE - CIVIL WORKS

PART SUMMARY

Page d/9/1 0.000

Page d/9/2 0.000

Page d/9/3 170080.240

Page d/9/4 388335.360

Page d/9/5 2888292.000

Page d/9/6 13382.160

Page d/9/7 201484.320

Page d/9/8 0.000

Page d/9/9 0.000

Page d/9/10 0.000

Page d/9/11 91983.600

Page d/9/12 2922911.980

Total for Part 9 - Main Bridge - Civil Works,


carried to Grand Summary 6676469.660
PART 10

APPROACH BRIDGE EAST - CIVIL WORKS


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 10 - APPROACH BRIDGE EAST - 0.000
CIVIL WORKS 0.000
0.000
From Chainage 110530 to 112430 0.000
0.000
EARTHWORKS 0.000
0.000
To Pile Caps 0.000
0.000
Excavation 0.000
0.000
A Excavation for foundation, 2 - 5 m E325 m3 560 0.460 257.600
0.000
B Excavation for foundations in rock, 0.000
2-5m E335 m3 0.000
0.000
0.000
Excavation Ancillaries 0.000
0.000
C Preparation of excavated surfaces E522 m2 262 1.070 280.340
other than rock 0.000
0.000
D Preparation of excavated surfaces in rock E523 m2 0.000
0.000
E Disposal of excavated surplus material 0.000
to approved tip E532 m3 361 1.810 653.410
0.000
F Disposal of excavated material; rock E533 m3 0.000
0.000
0.000
Filling 0.000
0.000
G Filling to structures, selected excavated 0.000
material other than top soil or rock E614 m3 199 1.310 260.690
0.000
Behind Abutment 0.000
0.000
H Filling embankment with imported natural E625 m3 384 3.200 1228.800
material other than rock 0.000
0.000
0.000
I Geotextile; heavy duty E730.1 m2 376 0.880 330.880
0.000
J Geotextile 320g/m2 E730.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 3011.720


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
INSITU CONCRETE 0.000
0.000
Provision of Concrete 0.000
0.000
A Concrete Grade 20 MPa F243 m3 12 27.010 324.120
0.000
B Concrete Grade 40 MPa F283 m3 6,187 33.810 209182.470
0.000
0.000
Placing of Concrete 0.000
0.000
Mass 0.000
0.000
C Blinding thickness, not exceeding 150mm F511 m3 12 5.050 60.600
0.000
Reinforced 0.000
0.000
D Approach slab, thickness 300 - 500 mm F623 m3 28 4.270 119.560
0.000
E Pile cap, thickness exceeding 500 mm F624 m3 411 10.490 4311.390
0.000
F Abutment/Retaining wall, thickness 0.000
exceeding 500 mm F643 m3 178 115.890 20628.420
0.000
G Abutment wing walls, thickness 0.000
300- 500 mm F644 m3 33 17.970 593.010
0.000
H Piers, cross sectional area exceeding 0.000
1 m2 Type I F655.1 m3 2,316 93.360 216221.760
0.000
I Piers, cross sectional area exceeding 0.000
1m2 Type II F655.2 m3 1,018 63.160 64296.880
0.000
J Pier head Type I F680.1 m3 1,798 139.920 251576.160
0.000
K Pier head Type II F680.2 m3 405 129.330 52378.650
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 819693.020


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES 0.000
0.000
Formwork 0.000
0.000
A Vertical width 02-0.4 wing walls G343.1 m2 0.000
0.000
B Vertical width 0.2-0.4 approach slab G345.2 m2 85 6.620 562.700
0.000
C Vertical width exceeding 1.22mm wing walls G345.1 m2 93 12.940 1203.420
0.000
D Vertical width exceeding 1.22m 0.000
abutment/retaining walls G345.2 m2 701 11.910 8348.910
0.000
E Vertical width exceeding 1.22m pilecaps G345.3 m2 210 9.450 1984.500
0.000
F Pier, 2.50 m diameter, Type I G382.1 m 447 377.970 168952.590
0.000
G Pier, Type II G382.2 m 158 389.940 61610.520
0.000
H Pier head, 2.50 mm diameter at base 0.000
increasing to 2.5 x 5.38 m overall at head, 0.000
overall height 2.3 m, as detailed on the 0.000
drawings (Type I) G394.1 nr 98 1920.370 188196.260
0.000
I Pier head (Type II) G394.2 nr 20 2063.010 41260.200
0.000
0.000
Formwork - Precast Concrete 0.000
0.000
J Vertical; width exceeding 1.22m G490.1 m2 0.000
0.000
K Horizontal; width exceeding 1.22m G490.2 m2 0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
L Diameter 12 mm - 40 mm G549 t 993 249.610 247862.730
0.000
Stainless steel deformed bars Grade 60 0.000
ASTM A 955/955M 0.000
0.000
M Diameter 12 mm - 40 mm G539 t 240 1364.120 327388.800
0.000
0.000
Joints 0.000
0.000
N Bridge deck expansion joint complete 0.000
as detailed on drawing G690 m 362 994.750 360099.500
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1407470.130


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
CONCRETE ANCILLARIES (CONT'D) 0.000
0.000
Post-tensioned prestressing 0.000
0.000
Post-tensioned prestressing of bridge 0.000
deck box section girders complete 0.000
in accordance with the drawings and 0.000
specification including low relaxation 0.000
prestressing strands in accordance 0.000
with the specification including all ducts 0.000
anchorages, couplers and grouting 0.000
0.000
A Horizontal/inclined internal tendons 0.000
in precast concrete (…….. tonnes) G739 nr 95 4307.650 409226.750
0.000
B External jacking operations G750 nr 95 3549.450 337197.750
0.000
0.000
Concrete Accessories 0.000
0.000
C Finishing of top surfaces of bridge deck G813.1 m2 74,856 3.190 238790.640
0.000
D Finishing top surface of pile caps G813.2 m2 0.000
0.000
E Grouting under bearing plates, non-shrink 0.000
cementitious grout, 0.1-0.5m2 G842 nr 290 456.510 132387.900
0.000
F Provision for the later implementation of 0.000
Cathodic Protection to piers G900 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1117603.040


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PRECAST CONCRETE 0.000
0.000
Concrete Grade 50 MPa 0.000
0.000
Note : 0.000
0.000
The descriptions/quantities provided 0.000
below are for a typical one metre length 0.000
of bridge box girder. The precast 0.000
concrete girders are constructed in 0.000
varying widths/type and the Contractor 0.000
shall make due allowance in his pricing 0.000
0.000
A Bridge box girder overall cross section 0.000
dimensions 17,000 mm wide x 2,500 mm 0.000
depth including transverse post tensioning to 0.000
bridge deck slab as detailed on the drawings H900.1 m 3,080 1956.410 6025742.800
0.000
Bridge box girder supporting 2 carriageway
B lanes, overall cross section dimension
2500mm deep, width varying from 20.7 to
13.3m including transverse post tensioning
to bridge deck slab as detailed on the
drawings H900.2 m 300 2086.860 626058.000
0.000
C Bridge box girder with overall cross section 0.000
dimensions 13.3m wide 2.5m deep including 0.000
transverse post tensioning to bridge deck sl H900.3 nr 17 155011.280 2635191.760
as detailed on the drawings 0.000
0.000
D Transition Section of Bridge box girder 0.000
overall cross section dimension 17,000 mm 0.000
wide depth increasing from 2500mm to 0.000
3000 mm including transverse post 0.000
tensioning to bridge deck slab as detailed 0.000
on the drawings H900.4 m 200 2856.120 571224.000
0.000
E Transition section of Bridge box girder: 0.000
Depth 2.5m with width varying from 13.3 to 20.7m 0.000
blending with mainline box, including transverse 0.000
post tensioning to bridge deck slab as detailed 0.000
on the drawings H900.5 m 520 4246.880 2208377.600
0.000
F Allow for closing both ends of bridge box 0.000
girders for post tensioning as detailed on 0.000
the drawings (quantity given is for 0.000
the total number of individual box girder 0.000
elements to Approach Bridge East) H900.6 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 12066594.160


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PIPEWORK - PIPES 0.000
0.000
Stormwater drainage system for bridge 0.000
deck water discharge to section of 0.000
Approach Bridge East that is overwater/overland 0.000
0.000
0.000
A Drainage pipe system from scupper to 0.000
ground level discharge, including all 0.000
pipes, fittings, supports, protective and 0.000
decorative coatings etc. as detailed on 0.000
the drawings I900 Sum 0.000
0.000
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Gullies 0.000
0.000
B Scupper grating/drainage outlet 0.000
900 x 500 mm in stainless steel cast 0.000
into bridge deck complete as detailed 0.000
on the drawings K390 Sum 1 53361.370 53361.370
0.000
0.000
0.000
HDPE or other approved pipes 0.000
perforated or slotted, diameter 200 0.000
stormwater drain in trenches 0.000
0.000
C Depth not exceeding 1.0 m I512 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 53361.370


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge bearings as detailed on the 0.000
drawings 0.000
0.000
A Bearing complete installed on pier 0.000
including grout pad N267 nr 290 2986.710 866145.900
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 866145.900


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILES 0.000
0.000
Piling for bridge piles commencing 0.000
surface level to be agreed with Engineer 0.000
on site 0.000
0.000
Isolated steel, driven piles, high strength 0.000
low alloy structural steel to ASTM A7009 0.000
Grade 50 0.000
0.000
Diameter 1524 mm vertical 0.000
0.000
A Number of piles, (total length ……. m) 0.000
including protective coatings P771 nr 0.000
0.000
B Depth driven P772 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PILING ANCILLARIES 0.000
0.000
Isolated steel piles 0.000
0.000
A Filling hollow piles 1524 mm diameter 0.000
with concrete grade ………. Q537 m 0.000
0.000
B Cutting off surplus length, 1524 mm 0.000
diameter Q577 m 0.000
0.000
C Preparing heads, 1524 mm diameter 0.000
as detailed on drawing Q587 nr 0.000
0.000
0.000
0.000
Reinforcement 0.000
0.000
Deformed high yield steel bars to ASTM 0.000
Grade 60 0.000
0.000
D Straight bars, nominal size 12 - 40 mm 0.000
diameter Q219.1 t 0.000
0.000
E Helical bars not exceeding 14 mm 0.000
diameter Q219.2 t 0.000
0.000
0.000
Pile tests for 1524 mm diameter, piles 0.000
0.000
F Pile testing as specification including 0.000
provision/construction and installation of 0.000
necessary test piles and pilot piles Q860 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PAINTING 0.000
### 0.000
(To be inserted by the Tenderer if 0.000
deemed necessary as part of their 0.000
chosen durability strategy) 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
WATERPROOFING 0.000
0.000
Tanking (Above ground structures) 0.000
0.000
A Self adhesive waterproof membrane 0.000
to buried concrete W239 m2 0.000
0.000
B Protection to waterproof membrane W429 m2 0.000
0.000
0.000
Tanking (Above ground structures) 0.000
0.000
C Spray applied waterproofing membrane 0.000
to bridge deck surface W500.1 m2 62,824 5.010 314748.240
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 314748.240


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 R (d/10/12 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
A Bored Pile Work Sum 1 4714112.780 4714112.780
0.000
0.000
B Scour Protection Sum 1 298795.210 298795.210
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 5012907.990


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 APPROACH BRIDGE EAST
VOLUME III - DOC.III.5 CIVIL WORKS d 10 d/10/13

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 10 - APPROACH BRIDGE EAST - CIVIL WORKS

PART SUMMARY

Page d/10/1 3011.720

Page d/10/2 819693.020

Page d/10/3 1407470.130

Page d/10/4 1117603.040

Page d/10/5 12066594.160

Page d/10/6 53361.370

Page d/10/7 866145.900

Page d/10/8 0.000

Page d/10/9 0.000

Page d/10/10 0.000

Page d/10/11 314748.240

Page d/10/12 5012907.990

Total for Part 10 - Approach Bridge East - Civil Works,


carried to Grand Summary 21661535.570
PART 11

BUILDING WORKS
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 BUILDING WORKS d 11 d/11/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 11 - BUILDING WORKS 0.000
0.000
The contractor is required to price 0.000
under this element the complete 0.000
Building Works (civil, architectural 0.000
mechanical, electrical and 0.000
plumbing works, including all 0.000
necessary external works 0.000
and services described in the 0.000
specification and shown on the 0.000
concept drawings 0.000
0.000
Doha Peninsula Area 0.000
0.000
Permanent Buildings 0.000
0.000
A MPW Causeway Secondary Administration 0.000
and Management Building Z800.1 Sum 1 1180535.920 1180535.920
0.000
0.000
B MOI weighbridge station and truck yard Z800.2 Sum 1 220119.190 220119.190
0.000
0.000
C MOI Traffic Monitoring and Control Centre 0.000
building for Traffic Police Department Z800.3 Sum 1 534994.500 534994.500
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1935649.610


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 BUILDING WORKS d 11 d/11/2

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 11 - BUILDING WORKS

PART SUMMARY

Page d/11/1 1935649.610

Total for Part 11 - Building Works,


carried to Grand Summary 1935649.610
PART 12

ENGINEERING INSTALLATIONS

d12/A Road Lighting Works

d12/B Mechanical, Electrical & Communication


Works
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A d/12A/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
PART 12A - ROAD LIGHTING WORKS 0.000
0.000
PIPEWORK - MANHOLES AND 0.000
PIPEWORK ANCILLARIES 0.000
0.000
Ducts 0.000
0.000
uPVC ducts to BS 3506, Class C, 0.000
100 mm diameter, laid and jointed in 0.000
trenches beneath carriageways, 0.000
including end caps, draw ropes and 0.000
duct markers 0.000
0.000
Depth not exceeding 1.50 m 0.000
0.000
A One way duct K512 Sum 1 30552.320 30552.320
0.000
B Two way ducts K522 Sum 0.000
0.000
C Three way ducts K532 Sum 0.000
0.000
D Four way ducts K542 Sum 1 89739.420 89739.420
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 120291.740


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A d/12A/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
PIPEWORK - SUPPORTS AND 0.000
PROTECTION, ANCILLARIES TO 0.000
LAYING AND EXCAVATION 0.000
0.000
Beds and surrounds 0.000
0.000
Selected excavated material beds and 0.000
surrounds to 100 mm diameter ducts, 0.000
including warning tape 0.000
0.000
A One way duct L511.1 Sum 0.000
0.000
B Two way ducts L511.2 Sum 0.000
0.000
C Three way ducts L511.3 Sum 0.000
0.000
D Four way ducts L511.4 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A d/12A/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
MISCELLANEOUS WORK 0.000
0.000
Mass concrete lighting column foundation 0.000
complete, as detailed on the drawings, 0.000
including excavation, backfilling, 0.000
compaction, formwork, concrete, 0.000
holding down bolts, nuts and washers 0.000
protected with denso tape before casting 0.000
the foundation and after column erection, 0.000
ducts and all other necessary works 0.000
0.000
A For 14.00 m high lighting columns with 0.000
1 luminaire X800.1 nr 167 60.910 10171.970
0.000
B For 14.00 m high lighting columns with 0.000
2 luminaires X800.2 nr 190 77.510 14726.900
0.000
0.000
Lighting column foundation complete as 0.000
detailed on drawings for lighting columns 0.000
installed on bridge deck including holding 0.000
down bolts, nuts and washers protected 0.000
with denso tape, ducts and all other 0.000
necessary works 0.000
0.000
C For 14.00 m high lighting columns with 0.000
1 luminaire X800.3 nr 0.000
0.000
D For 14.00 m high lighting columns with 0.000
2 luminaires X800.4 nr 0.000
0.000
0.000
Feeder Pillar Foundations 0.000
0.000
E Mass concrete feeder pillar foundations 0.000
complete as detailed on drawing, 0.000
including necessary earthworks, formwork, 0.000
concrete work, holding down nuts, 0.000
washers and back plate with bars X800.5 nr 1 56.050 56.050
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 24954.920


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A d/12A/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
MISCELLANEOUS WORK (CONT'D) 0.000
0.000
Lighting Column Installations 0.000
0.000
Install lighting columns complete with 0.000
brackets, cut-outs, terminate cables, and 0.000
grouting of base plates 0.000
0.000
A 14 m high lighting column with 1 luminaire X880.1 nr 194 595.930 115610.420
0.000
B 14 m high lighting column with 2 luminaires X880.2 nr 393 1146.490 450570.570
0.000
0.000
Cable Trays 0.000
0.000
C Install cable trays with necessary fitting 0.000
and supports and commission complete 0.000
for road lighting LV cables X880.3 Sum 0.000
0.000
0.000
Power Supply Cable Installations 0.000
0.000
Excavate for cable trenches, including 0.000
warning tapes and protection measures 0.000
depth not exceeding 1.0 m 0.000
0.000
D One way cable X890.1 Sum 1 138033.290 138033.290
0.000
E Two way cables X890.2 Sum 0.000
0.000
F Three way cables X890.3 Sum 0.000
0.000
G Four way cables X890.4 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 704214.280


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A d/12A/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
MISCELLANEOUS WORK (CONT'D) 0.000
0.000
Power Supply Cable Installations 0.000
(Cont'd) 0.000
0.000
Supply and install the following power 0.000
supply cables including cable tiles, route 0.000
marker tapes, junction boxes, as shown 0.000
on the drawings (laying of loop lengths, 0.000
cut-out lengths at terminations to be 0.000
included in the rate) 0.000
0.000
A Power cables for road lighting at 0.000
approach roads, embankment and 0.000
interchange area including excavation 0.000
and backfilling X980.1 Sum 1 175809.030 175809.030
0.000
B Power cable for road lighting on bridge 0.000
carriageway X980.2 Sum 1 205615.910 205615.910
0.000
0.000
Feeder Pillar Installations 0.000
0.000
C Supply and install feeder pillar, 0.000
termination cables, and commission X990.1 Sum 1 1965.390 1965.390
0.000
0.000
Earthing Installations 0.000
0.000
D Supply and installation of complete 0.000
Earthing System, including earthing pits 0.000
covers, earthing rod, clamp with denso 0.000
tape, protection etc. X990.2 Sum 1 16248.810 16248.810
0.000
E Earthing cable copper X990.3 Sum 1 16248.810 16248.810
0.000
0.000
Road Lighting Management System 0.000
0.000
F Supply and installation of complete Road 0.000
Lighting Management System, 0.000
including control units in each 0.000
lighting column, communication cabling, 0.000
connection to WAN, software, main 0.000
computer and interfacing with SCADA X990.4 Sum 1 176582.640 176582.640
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 592470.590


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A R (d/12A/6 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 ENGINEERING INSTALLATIONS
VOLUME III - DOC.III.5 ROAD LIGHTING WORKS d 12/A R (d/12A/7 - AD1)

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 12/A - ENGINEERING INSTALLATIONS ROAD LIGHTING WORKS

PART SUMMARY

Page d/12A/1 120291.740

Page d/12A/2 0.000

Page d/12A/3 24954.920

Page d/12A/4 704214.280

Page d/12A/5 592470.590

Page d/12A/6 0.000

Total for Part 12/A - Engineering Installations Road Lighting Works,


carried to Grand Summary of Part 12 (sheet e/1) 1441931.530
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
PART 12B - MECHANICAL, 0.000
ELECTRICAL AND COMMUNICATION 0.000
WORKS 0.000
0.000
12B.01 - 11 kV Distribution System 0.000
0.000
In Bridge Girders: 0.000
0.000
(Approach Bridge West, Main bridge, 0.000
Approach Bridge East, Shuwaikh Port 0.000
area) 0.000
0.000
0.000
A 11kV cable system (Including joints and 0.000
terminations) X 501.1 m 15,600 18.720 292032.000
0.000
B Cable ways in Girders X 501.2 m 62,000 15.440 957280.000
0.000
C Type 3 Substation rooms and platforms X 501.3 nr 5 3044.970 15224.850
0.000
D Cast resin transformer, small 0.000
(11/.4 kV 50-100kVA) Including enclosure X 501.4 nr 5 5871.810 29359.050
0.000
E Cast resin transformer large, 0.000
(11/.4 kV 160-250kVA) Including enclosure X 501.5 nr 0.000
0.000
F 11 kV and 400 V cable systems for 0.000
transformers X 501.6 Sum 1 17991.190 17991.190
0.000
G 11kV Switchgear (2 line feeder, 0.000
1 transformer feeder) including platforms and 0.000
substation rooms X 501.7 nr 5 28958.240 144791.200
0.000
H Cable ways at expansion joints including 0.000
flexible arrangement X 501.8 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1456678.290


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.01 - 11 kV Distribution System 0.000
(Cont'd) 0.000
0.000
On land : 0.000
0.000
(Shuwaikh Port Interchange/ Doha Interchange/ 0.000
Doha Peninsula Road/Entertainment City 0.000
Interchange 0.000
0.000
A 11kV cable system along Causeway 0.000
(Including joints and terminations) X 501.9 m 8,300 20.980 174134.000
0.000
B Cable Trench, including (PVC pipes, 0.000
warning and protective measures) X 501.10 m 14,200 8.480 120416.000
0.000
C Type 1 Kiosk Substation building, One 0.000
transformer and switch gear. X 501.11 nr 3 29013.610 87040.830
0.000
D Type 2 Coupling Substation building, 0.000
transformer and switch gear. X 501.12 nr 2 48706.960 97413.920
0.000
E Switchgear building next to Doha Peninsula 0.000
existing substation. X 501.13 nr 1 29013.610 29013.610
0.000
F 11/.4 kV Oil immersed transformer 0.000
Small (≤100 KVA) X 501.14 nr 1 22380.000 22380.000
0.000
G 11/.4 kV Oil immersed transformer 0.000
Large (> 100 KVA) X 501.15 nr 1 21214.050 21214.050
0.000
H 11kV Switchgear (6 line feeder, 0.000
1 buscoupler, 1 transformer feeder) X 501.16 nr 0.000
0.000
I 11kV Switchgear (2 line feeder, 0.000
1 transformer feeder) X 501.17 nr 0.000
0.000
J 11kV Switchgear (6 line feeder, 0.000
1 buscoupler, 2 transformer feeder) X 501.18 nr 0.000
0.000
K 11kV Switchgear (9 line feeder, 0.000
2 buscoupler, 3 transformer feeder) X 501.19 nr 0.000
0.000
L 11kV cable system to buildings X 501.20 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 551612.410


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.01 - 11 kV Distribution System 0.000
(Cont'd) 0.000
0.000
11 kV interconnection to public grid/ 0.000
Main Causeway 0.000
0.000
A 11kV cable system connection to existing 0.000
Main Causeway Substation/Shuwaikh 0.000
Interchange X 500.21 m 0.000
0.000
B 11kV cable system connection to existing 0.000
substation Doha Peninsula X 500.22 m 0.000
0.000
C Cable Trench, including (PVC pipes, 0.000
warning and protective measures) X 500.23 m 0.000
0.000
D Complete 11 kV feeder cubicle at 0.000
connection SS point 1and2 X 500.24 nr 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.02 - LV-Systems, Causeway 0.000
Operation 0.000
0.000
In Bridge Girders: 0.000
0.000
(Approach Bridge West, Main Bridge, 0.000
Approach Bridge East) 0.000
0.000
0.000
A Main LV switchboards for Causeway 0.000
operation in transformer substations. X 502.1 nr 5 9469.310 47346.550
0.000
B Cable ways in Girder X 502.2 m 0.000
0.000
C LV sub-distribution boards/marshalling 0.000
cabinets along causeway X 502.3 Sum 0.000
0.000
D LV cable system for powering SCADA, 0.000
ITS, Dehumidification units etc. X 502.4 Sum 0.000
0.000
E UPS-system for essential loads in each 0.000
transformer station X 502.5 nr 5 27958.370 139791.850
0.000
0.000
On land along Causeway: 0.000
0.000
0.000
(Doha Interchange/ Doha Peninsula Road, 0.000
Entertainment City Interchange) 0.000
0.000
F Main LV switchboards in substations 0.000
situated in transformer buildings along the 0.000
Causeway X 502.6 nr 6 19868.040 119208.240
0.000
G Main LV switchboards in substations for 0.000
commercial facilities on Doha Peninsula 0.000
Road with separate kWh-measurement X 502.7 nr 0.000
0.000
H UPS-system for essential loads in 0.000
transformer stations located on 0.000
Doha Peninsula Road X 502.8 nr 6 16055.310 96331.860
0.000
I Cable trenches and pulling holes along 0.000
the Causeway, incl. (PVC pipes , warning 0.000
and protective measures) X 502.9 m 0.000
0.000
J Earthing system at transformer 0.000
substations X 502.10 nr 6 415.230 2491.380
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 405169.880


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.02 - LV-Systems, Causeway 0.000
Operation (Cont'd) 0.000
0.000
Main Substation Shuwaikh Port Area: 0.000
0.000
A Main LV switchboard in substation X 502.11 nr 0.000
0.000
B Distribution switchboards for auxiliary 0.000
systems X 502.12 Sum 0.000
0.000
C Cable ways in building for main power-, X 502.13 Sum 0.000
control- and communication circuits 0.000
0.000
D UPS-system for essential loads X 502.14 Sum 0.000
0.000
E Earthing system for transformer station X 502.15 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.03 - Emergency Power Supply 0.000
0.000
0.000
Situated in Separate 0.000
Building in Doha Peninsula 0.000
0.000
A Diesel Generator Unit including control 0.000
systems and building complete X 503.1 nr 3 11903.090 35709.270
0.000
B Fuel tank, cooling system, exhaust 0.000
systems etc. for diesel Generator X 503.2 Sum 0.000
0.000
C Step-up transformer including 11 kV and 0.000
400 V cable systems for transformer 0.000
connection X 503.3 Sum 1 3266.530 3266.530
0.000
D Control and auxiliary cables at Main 0.000
Substation building X 503.4 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 38975.800


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.04 - Electrical Facilities in Bridge 0.000
Girders 0.000
0.000
Electrical Facilities 0.000
0.000
A Cable ways for LV power-, control 0.000
cables, SCADA and communication 0.000
cables including (Ladders, trays, 0.000
conduits, pipes etc.) X 504.1 m 0.000
0.000
B Complete internal lighting system 0.000
normal and emergency lights including 0.000
luminaires, cables, boxes, switches etc. X 504.2 m 18,600 3.180 59148.000
0.000
C Floodlighting for illumination of girder X 504.3 Sum 1 272189.540 272189.540
0.000
D Small power installations including 0.000
(sockets, switches etc.) X 504.4 Sum 1 136511.950 136511.950
0.000
E Power supply installation for forced 0.000
ventilation system including cables, 0.000
boxes local control and attachments. X 504.5 Sum 0.000
0.000
F Earthing system along Girder and 0.000
grounding electrodes at pillars X 504.6 Sum 1 865165.440 865165.440
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1333014.930


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/8

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.05 - Intelligent Traffic Systems 0.000
0.000
Field equipment along Causeway 0.000
0.000
(Including poles, gantries, foundations, 0.000
mounting brackets, antennas, interfaces, 0.000
equipment cabinets and enclosures) 0.000
0.000
A - CCTV sensors, 0.000
- Variable Text Function, VTF-signs 0.000
- Warning Function, WF-signs 0.000
- Lane Control Function, LCF-signs 0.000
- Speed Control Function, SCF-signs 0.000
- Carriage Cross over Function, X 505.1 Sum 1 1585744.710 1585744.710
0.000
0.000
B Cabling to and between respective items 0.000
and all cabling to the interface with other 0.000
systems incl. Cable Trench, including 0.000
(PVC pipes , warning and protective 0.000
measures for ITS & Communication) 0.000
on land X 505.2 Sum 1 163366.710 163366.710
0.000
0.000
Control Room Equipment 0.000
0.000
C TMS software for 2 nos control room X 505.3 Sum 1 558798.440 558798.440
0.000
D TMS hardware fro 2 nos control room X 505.4 Sum 1 412885.850 412885.850
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 2720795.710


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/9

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.06 - Telecommunication Systems 0.000
Including necessary fittings and 0.000
accessories as per specification 0.000
0.000
Radio communication system 0.000
0.000
A Antenna masts X 506.1 nr 2 46505.030 93010.060
0.000
B Base stations X 506.2 nr 8 14948.040 119584.320
0.000
C Fibre optic RF-Amplifiers X 506.3 nr 14 1605.530 22477.420
0.000
D Cabling to and between respective items 0.000
and all cabling to the interface with other 0.000
systems X 506.4 Sum 0.000
0.000
E Communication server/switch X 506.5 nr 2 9134.910 18269.820
0.000
F Mobile and handheld Radios complete 0.000
handset X 506.6 Sum 1 442.910 442.910
0.000
G Operators console in Control Rooms X 506.7 Sum 1 146712.300 146712.300
0.000
H Leaky coaxial cable X 506.8 m 15,400 4.120 63448.000
0.000
0.000
Wide Area Network 0.000
0.000
I Dual FO type cable, 96 cores single 0.000
mode connection X 506.9 m 23,900 4.130 98707.000
0.000
J Hardware including SDH access point 0.000
(nodes), Transmission systems , SDH 0.000
Transmission Management System, 0.000
Racks, patch panels, etc X 506.10 Sum 0.000
0.000
K Cable ways in bridge girder X 506.11 Sum 0.000
0.000
L Cabling to and between respective items 0.000
and all cabling to the interface with other 0.000
systems incl. Cable Trench, including 0.000
(PVC pipes , warning and protective 0.000
measures for ITS & Communication) 0.000
on land X 507.12 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 562651.830


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/10

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.06 - Telecommunication Systems 0.000
(Cont'd) 0.000
0.000
Cable ways for Telecom Operator's 0.000
0.000
A Cable way in bridge Girder Construction 0.000
(From Port Interchange to Doha 0.000
Peninsula Road) X 506.13 m 0.000
0.000
B Cable Trench, including PVC pipes, 0.000
warning and protective measures 0.000
(On Doha Embankment and along 0.000
Doha Approach Road/Interchanges at 0.000
Doha and Entertainment City) X 506.14 m 0.000
0.000
0.000
IT Systems: 0.000
0.000
LAN/Cabling systems/Servers/Routers/ 0.000
Switches/PC's / Printers/Cable 0.000
management and control system/ 0.000
Network management System/Software 0.000
and licences to the following 0.000
0.000
C Causeway Management Building, 0.000
Shuwaikh Port Interchange X 506.15 Sum 0.000
0.000
D Secondary Control Room/Management 0.000
Building at Doha Peninsula Road X 506.16 Sum 0.000
0.000
0.000
0.000
Telephone System: 0.000
0.000
Including PBX, telephone sets/fax 0.000
machines / UPS, cabling, Software 0.000
and licences to the following 0.000
0.000
E Causeway Management Building, 0.000
Shuwaikh Port Interchange X 506.17 Sum 0.000
0.000
F Secondary Management Building/ 0.000
Control Room at Doha Peninsula Road X 506.18 Sum 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/11

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.07 - SCADA (SCADA, PMS, CCMS) 0.000
0.000
Field equipment along Causeway 0.000
0.000
(Including but not limited to: cabling/ 0.000
racks/enclosures/mounting brackets, 0.000
interfaces), as per specification 0.000
0.000
A Racks with local control units along 0.000
Causeway X 507.1 Sum 1 101093.060 101093.060
0.000
B Software for local control systems X 507.2 Sum 1 57516.150 57516.150
0.000
C Computers with monitors including 0.000
complete software and licences X 507.3 Sum 1 44659.590 44659.590
0.000
D LAN, Interfaces, control cabling - 0.000
and communication cables X 507.4 Sum 1 1050.250 1050.250
0.000
0.000
0.000
Control Room: 0.000
0.000
Causeway Management Building, Shuwaikh 0.000
Port Interchange and Doha Peninsula Road 0.000
0.000
E Large Area Display Walls X 507.5 nr 2 2875.810 5751.620
0.000
F Computers including printers, software 0.000
and licences X 507.6 Sum 1 13025.710 13025.710
0.000
G Operation Consoles for E&M systems/ 0.000
Alarm handling / TMS-Traffic Monitoring / 0.000
IDS-Accident Detection / Structural 0.000
monitoring, Meteorological 0.000
measurements / CCMS / PMS X 507.7 Sum 1 410394.590 410394.590
0.000
H Maintenance Management System 0.000
including Hardware / Software / Licences X 507.8 Sum 1 50749.530 50749.530
0.000
I Furniture's for Control Room X 507.9 Sum 1 79968.950 79968.950
0.000
0.000
0.000
Web Cameras 0.000
0.000
J Cameras mounted on towers, complete with 0.000
foundations, power supply, and connections for live 0.000
Internet broadcast of the works under constr X507.10 Sum 1 22145.240 22145.240
0.000
0.000
0.000
Weigh Station: 0.000
0.000
K Weigh Station, complete with platform, 0.000
foundations, office building, computer, 0.000
software and licenses, display, printer, 0.000
CCTV cameras on poles, cables, solar 0.000
power supply and service roads X507.11 Sum 1 44598.080 44598.080
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 830952.770


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/12

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.08 - Structural Monitoring 0.000
0.000
Field equipment along Causeway 0.000
0.000
(Including poles, gantries, foundations, 0.000
mounting brackets, interfaces, equipment 0.000
cabinets, ducts, cable trays, enclosures,) 0.000
0.000
0.000
A - Metrological sensors 0.000
- Structural sensors 0.000
- Local Data Acquisition System 0.000
- Portable Data Acquisition System 0.000
- Interfaces, Control cables - 0.000
and communication cables X 508.1 Sum 1 88115.100 88115.100
0.000
0.000
Control Room : 0.000
0.000
Causeway Management Building, 0.000
Shuwaikh/ Secondary Management Building 0.000
Control Room at Doha Peninsula Road 0.000
0.000
B Computers including printers, software 0.000
and licences for structural monitoring and 0.000
control X 508.2 Sum 1 147610.560 147610.560
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 235725.660


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/13

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.09 - Electrical Infrastructure, 0.000
Doha Peninsula Road and 0.000
Interchanges 0.000
0.000
A Lighting luminaires on poles. 0.000
Exterior lighting for street, roads, rest 0.000
areas and parking areas X 600.1 nr 0.000
0.000
B Decorative Lighting luminaires X 600.2 nr 0.000
0.000
C LV-cable network for lighting systems X 600.3 m 0.000
0.000
D Power installations including 0.000
(socket, switches, etc.) X 600.4 Sum 0.000
0.000
E Main LV-cable network for buildings and 0.000
services X 600.5 Sum 0.000
0.000
F Main cable trenches and pulling holes 0.000
for infrastructure ( for power system, 0.000
telephone, data communication etc.), 0.000
including PVC pipes , warning and 0.000
protective measures. X 600.6 m 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/14

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.10 - Water Supply 0.000
Including valves, fittings and 0.000
accessories as per specification 0.000
0.000
Shuwaikh Port Interchange 0.000
0.000
A Main Connection to public water supply I 900.1 Sum 1 34535.140 34535.140
0.000
B Water booster plants including pumps, 0.000
valves, fittings, etc. I 900.2 nr 1 2952.690 2952.690
0.000
C Local Water Distribution Piping system I 900.3 Sum 1 4060.010 4060.010
0.000
0.000
Doha Interchange, Doha Peninsula Road & 0.000
Entertainment City Interchange 0.000
0.000
D Main connection to public water supply I 900.4 Sum 1 218262.150 218262.150
0.000
E Water booster plants including pumps 0.000
valves, fittings, etc. I 900.5 nr 3 40929.990 122789.970
0.000
F Local Water Distribution Piping system I 900.6 Sum 1 36170.630 36170.630
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 418770.590


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/15

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.11 - Storm Water Drainage System 0.000
Including all necessary fittings and 0.000
accessories as per specification 0.000
0.000
0.000
0.000
Shuwaikh Port Interchange : 0.000
0.000
A Storm water drainage system K900.1 Sum 1 10785.970 10785.970
0.000
0.000
Approach Bridge West 0.000
0.000
B Storm water drainage system on Girder 0.000
Structures K 900.2 Sum 1 38909.790 38909.790
0.000
Approach Bridges East 0.000
0.000
C Storm water drainage system on Girder 0.000
Structures K 900.3 Sum 1 19490.490 19490.490
0.000
0.000
Main Bridge 0.000
0.000
D Storm water drainage system on Girder 0.000
Structures K 900.4 Sum 1 4080.240 4080.240
0.000
0.000
Doha Interchange 0.000
0.000
E Storm water drainage system K 900.5 Sum 1 16392.420 16392.420
0.000
0.000
Doha Peninsula Road 0.000
0.000
F Storm water drainage system K 900.6 Sum 1 6911.540 6911.540
0.000
0.000
Entertainment City Interchange 0.000
0.000
G Storm water drainage system K 900.7 Sum 1 36543.150 36543.150
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 133113.600


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/16

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.12 - Sewage Systems 0.000
Including all necessary fittings and 0.000
accessories as per specification 0.000
0.000
0.000
Doha Interchange, Doha Peninsula Road, 0.000
Entertainment City Interchange 0.000
0.000
A Septic Tank Y 900.1 Sum 1 49211.660 49211.660
0.000
B Irrigation water system Y 900.3 Sum 1 103654.060 103654.060
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 152865.720


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B d/12B/17

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
12B.13 - HVAC, Dehumidification 0.000
and Ventilation 0.000
0.000
0.000
0.000
0.000
Approach Bridges East and West 0.000
0.000
A Ventilation, louvers in Bridge Girders Z 800.1 m 0.000
0.000
0.000
Main Bridge 0.000
0.000
B Ventilation, louvers in Bridge Girders Z 800.2 m 0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B R (d/12B/18 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
A Nautical Marking System Sum 1 27404.870 27404.870
0.000
B RWIS (Road Weather Information System) Sum 1 89162.330 89162.330
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 116567.200


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK ENGINEERING INSTALLATIONS SECTION
CONTRACT RA/214 MECHANICAL, ELECTRICAL AND
VOLUME III - DOC.III.5 COMMUNICATION WORKS d 12/B R (d/12B/19 - AD1)

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 12/B - ENGINEERING INSTALLATIONS


MECHANICAL, ELECTRICAL AND COMMUNICATION WORKS

PART SUMMARY

Page d/12B/1 1456678.290

Page d/12B/2 551612.410

Page d/12B/3 0.000

Page d/12B/4 405169.880

Page d/12B/5 0.000

Page d/12B/6 38975.800

Page d/12B/7 1333014.930

Page d/12B/8 2720795.710

Page d/12B/9 562651.830

Page d/12B/10 0.000

Page d/12B/11 830952.770

Page d/12B/12 235725.660

Page d/12B/13 0.000

Page d/12B/14 418770.590

Page d/12B/15 133113.600

Page d/12B/16 152865.720

Page d/12B/17 0.000

Page d/12B/18 116567.200

Total for Part 12/B - Engineering Installations


Mechanical, Electrical and Communication Works,
carried to Grand Summary of Part 12 (sheet e/1) 8956894.390
PART 13

FINISHING WORKS
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/1

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
PART 13 - FINISHING WORKS 0.000
0.000
STRUCTURAL METALWORK 0.000
0.000
Hot rolled structural steelwork, all in 0.000
accordance with the Specification and 0.000
drawings including all necessary 0.000
protective coatings to sign structures, 0.000
0.000
Cantilever sign structures 0.000
0.000
Steelwork supporting structures complete 0.000
as detailed on drawing ……………… 0.000
including all supports, bracings, catwalk 0.000
assembly and anchoring system 0.000
to concrete foundations 0.000
0.000
A Type ……………, span ……… m M900.1 nr 0.000
0.000
B Type ……………, span ……… m M900.2 nr 0.000
0.000
C Type ……………, span ……… m M900.3 nr 0.000
0.000
D Type ……………, span ……… m M900.4 nr 0.000
0.000
Overhead Gantries 0.000
0.000
Steelwork supporting structures complete 0.000
as detailed on drawing …………………… 0.000
including all supports, bracings, catwalk 0.000
assembly and anchoring system 0.000
to concrete foundations 0.000
0.000
E Type ……………, span ……… m M900.5 nr 12 12618.460 151421.520
0.000
F Type ……………, span ……… m M900.6 nr 9 14456.400 130107.600
0.000
G Type ……………, span ……… m M900.7 nr 2 18073.070 36146.140
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 317675.260


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/2

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS METALWORK 0.000
0.000
Bridge Parapets 0.000
0.000
A Aluminium bridge parapet railing complete 0.000
including support posts, base plates, 0.000
stainless steel holding down bolts, 0.000
expansion joints, grouting etc., as shown 0.000
on the drawings N150.1 m 36,082 86.250 3112072.500
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 3112072.500


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/3

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ROADS AND PAVINGS 0.000
0.000
To Interchanges/Embankments 0.000
0.000
Sub-bases, flexible road bases and 0.000
surfacing 0.000
0.000
A Subgrade compacted sand fill depth 0.000
300mm R197.1 m2 384,464 0.970 372930.080
0.000
B Sub base Type A depth 300 mm R197.2 m2 331,396 3.650 1209595.400
0.000
C Asphalt Base course depth 80 mm R322.1 m2 310,672 4.440 1379383.680
0.000
D Asphalt binder course depth 60 mm, R322.2 m2 310,672 3.330 1034537.760
0.000
E Asphalt wearing course depth 40 mm R322.3 m2 310,672 2.220 689691.840
0.000
F Bituminous prime coat R359.1 m2 310,672 0.250 77668.000
0.000
G Bituminous tack coat R359.2 m2 310,672 0.090 27960.480
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 4791767.240


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/4

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ROADS AND PAVINGS (CONT'D) 0.000
0.000
To Concrete Bridge Deck 0.000
0.000
Sub-bases, flexible road bases and 0.000
surfacing 0.000
0.000
A Wearing course depth 20 mm R321.1 m2 288,541 1.790 516488.390
0.000
B Asphalt binder course depth 50mm, R322 m2 288,541 2.220 640561.020
0.000
C Spray tack coat Bituminous prime coat R359 m2 288,541 0.330 95218.530
0.000
0.000
0.000
Kerbs complete 0.000
0.000
D Precast concrete half battered kerb 0.000
150 x 300 mm including mortar bed R690.1 m 0.000
0.000
E Precast concrete drop kerb 300 x 150 mm R690.2 m 0.000
0.000
F Precast flush kerb 200 x 300 mm R690.3 m 0.000
0.000
G Precast heal kerb 100 x 150 mm R690.4 m 0.000
0.000
0.000
Light duty pavements 0.000
0.000
H Aggregate (granular) road base, 0.000
depth 130 mm below block paving tiles R714 m2 0.000
0.000
I Precast concrete block paving tiles 0.000
thickness 60 mm on and including mortar 0.000
bed R792.1 m2 0.000
0.000
J Precast concrete block paving tiles 0.000
thickness 60 mm on and including 50 mm 0.000
(granular) sand bed R792.2 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1252267.940


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/5

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ROADS AND PAVINGS (CONT'D) 0.000
0.000
Ancillaries 0.000
0.000
Traffic signs 0.000
0.000
In accordance with the specification 0.000
0.000
A Aluminium channel traffic sign panels for 0.000
illuminated warning signs, Type HVS1 R812.1 nr 38 341.500 12977.000
0.000
B Aluminium channel traffic sign panels for 0.000
illuminated warning signs Type HVS4 R812.2 nr 0.000
0.000
C Aluminium channel traffic sign panels for 0.000
illuminated guide signs (GS) R812.3 m2 1,880 121.580 228570.400
0.000
Warning and Regulatory Signs; including 0.000
posts 0.000
0.000
D Triangular sign panel H = 0.6 m R811.1 nr 0.000
0.000
E Triangular sign panel H = 0.75 m R811.2 nr 0.000
0.000
F Triangular sign panel H = 0.9 m R811.3 nr 0.000
0.000
G Triangular sign panel H = 1.2 m R811.4 nr 0.000
0.000
H Circular sign panel H = 0.6 m R811.5 nr 0.000
0.000
I Circular sign panel H = 0.75 m R811.6 nr 0.000
0.000
J Circular sign panel H = 0.9 m R811.7 nr 0.000
0.000
K Circular sign panel H = 1.2 m R811.8 nr 0.000
0.000
L Octagonal stop sign panel H = 0.6 m R811.9 nr 0.000
0.000
M Rectangular Sign panel 0.4 x 0.4 m R811.10 nr 0.000
0.000
N Sign panel 0.6 x 0.6 m R811.11 nr 54 338.460 18276.840
0.000
O Supplementary Plates R811.12 m2 0.000
0.000
P Sign panel for interchange number 0.000
affixed to bridge R811.17 m2 244 101.410 24744.040
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 284568.280


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/6

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ROADS AND PAVINGS (CONT'D) 0.000
0.000
Surface markings 0.000
0.000
A Heavy duty raised pavement markers 0.000
(retro reflective white/red or yellow/red) R822 nr 0.000
0.000
B Thermoplastic continuous pavement 0.000
marking 100 mm wide white R824.1 m 0.000
0.000
C Thermoplastic continuous pavement 0.000
marking 150 mm wide white R824.2 m 22,438 0.390 8750.820
0.000
D Thermoplastic continuous pavement 0.000
marking 200 mm wide white R824.3 m 0.000
0.000
E Thermoplastic continuous pavement 0.000
marking 150 mm wide yellow R824.4 m 22,758 0.390 8875.620
0.000
F Thermoplastic continuous pavement 0.000
marking 300 mm wide white R824.5 m 0.000
0.000
G Thermoplastic continuous pavement 0.000
marking 200 mm wide yellow R824.6 m 0.000
0.000
H Thermoplastic pavement marking 0.000
including hatching, chevrons and arrows R824.7 m2 1,488 4.780 7112.640
0.000
I Thermoplastic intermittent pavement 0.000
marking 100 mm wide white R825.1 m 0.000
0.000
J Thermoplastic intermittent pavement 0.000
marking 150 mm wide white R825.2 m 40,082 0.390 15631.980
0.000
K Thermoplastic intermittent pavement 0.000
marking 200 mm wide white R825.3 m 0.000
0.000
L Thermoplastic intermittent pavement 0.000
marking 300 mm wide white R825.4 m 0.000
0.000
M Chlorinated rubber based quick drying 0.000
paint (black and white) applied in two 0.000
coats to exposed faces of precast 0.000
concrete upstand kerbs (marking 691) R825.5 m2 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 40371.060


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/7

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
MISCELLANEOUS WORK 0.000
0.000
Fences 0.000
0.000
A Galvanised mild steel guard rail height 0.000
785 mm comprising 310 x 83 mm 0.000
proprietary system guard rail bolted to 0.000
150 x 75 x 6 mm channel section posts 0.000
driven or bedded in concrete as required X181.1 m 31,195 16.300 508478.500
0.000
B Metal beam guard rail terminal approach X181.2 nr 12 271.810 3261.720
0.000
C Metal beam guard rail terminal departure X181.3 nr 142 271.810 38597.020
0.000
D Reinforced precast concrete class 40/20 0.000
signal sided crash barrier height 950 mm 0.000
including concrete base, locating dowels 0.000
and sockets, and movement joints X191 m 585 59.840 35006.400
0.000
E Fence to Shuwaikh Port Interchange area as 0.000
required and detailed in the specification, 0.000
drawings and Employers Requirements X198.1 m 600 29.730 17838.000
0.000
F Fence to Doha Interchange ditto X198.2 m 4,055 27.380 111025.900
0.000
G Fence to Doha Peninsula Road ditto X198.3 m 3,570 28.740 102601.800
0.000
H Fence to Entertainment City X198.4 m 3,250 25.640 83330.000
Interchange ditto 0.000
0.000
0.000
I Energy absorbing barriers X198.5 m 26 3525.440 91661.440
0.000
0.000
Stone pitching to side slopes 0.000
0.000
J Stone pitching grouted in mass concrete 0.000
class 20/20 overall thickness 0.25 m to 0.000
embankment slopes X590.1 m2 0.000
0.000
K Loose stone pitching at drainage outfalls 0.000
and culverts X590.2 m3 89 136.590 12156.510
0.000
0.000
0.000
Landscaping 0.000
0.000
L Landscaping as required Shuwaikh Port X500.1 Sum 0.000
interchange 0.000
0.000
M Landscaping Doha Interchange X500.2 Sum 1 216397.890 216397.890
0.000
N Landscaping Doha Peninsula Road X500.3 Sum 1 215962.600 215962.600
0.000
O Landscaping Entertainment City Interchange X500.4 Sum 1 371902.430 371902.430
0.000
0.000
P Emergency Crossings to Approach Bridge X900.1 Sum 1 27903.810 27903.810
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 1836124.020


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 R (d/13/8 - AD1)

NUMBER ITEM DESCRIPTION CESMM3 UNIT QUANTITY RATE AMOUNT


REF. KD KUWAITI DINARS
0.000
ADDITIONAL ITEMS 0.000
0.000
The tenderer is to detail below any additional items with quantities, enumerated or itemised and 0.000
rates which were not previously included to complete the build-up of the lump-sum tender price for 0.000
this section of work. Should the tenderer fail to insert any item here, it will be deemed that his 0.000
lump sum price for the tender includes all items either shown on the Concept Drawings and 0.000
described in the Specification or deemed necessary by the tenderer to develop the design/ 0.000
drawings and specification to represent the entire cost of the Works. No subsequent claim for any 0.000
additional item will be entertained. 0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

To Part Summary 0.000


SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214
VOLUME III - DOC.III.5 FINISHING WORKS d 13 d/13/9

NUMBER ITEM DESCRIPTION AMOUNT


KUWAITI DINARS

PART 13 - FINISHING WORKS

PART SUMMARY

Page d/13/1 317675.260

Page d/13/2 3112072.500

Page d/13/3 4791767.240

Page d/13/4 1252267.940

Page d/13/5 284568.280

Page d/13/6 40371.060

Page d/13/7 1836124.020

Page d/13/8 0.000

Total for Part 13 - Finishing Works,


carried to Grand Summary 11634846.300
SECTION e

GRAND SUMMARY
EMPLOYER'S CONCEPT DESIGN
SHEIKH JABER AL AHMAD AL SABAH FORM OF BILL OF QUANTITIES BILL PART NO PAGE NO.
CAUSEWAY PROJECT - DOHA LINK SECTION
CONTRACT RA/214 GRAND SUMMARY
VOLUME III - DOC.III.5 EMPLOYER'S CONCEPT e e/1
DESIGN

SECTION E - GRAND SUMMARY - EMPLOYER'S CONCEPT DESIGN AMOUNT


KUWAITI DINARS

SECTION C

DAYWORK SCHEDULES (INCLUDED IN DOCUMENT III.6)

SECTION D

Part 1 General Items 50223573.060

Part 2 Ground Investigation 1624456.560

Part 3 Geotechnical Investigation 33532.520

Part 4 Demolition and Site Clearance 736076.490

Part 5 Entertainment City Interchange 9816350.580

Part 6 Doha Peninsula Road 2164345.170

Part 7 Doha Interchange 5628730.670

Part 8 Approach Bridge West 43173607.890

Part 9 Main Bridge 6676469.660

Part 10 Approach Bridge East 21661535.570

Part 11 Building Works 1935649.610

Part 12 Engineering Installations 10398825.920

Part 13 Finishing Works 11634846.300

Sub Total of Part 1 to Part 13 KD 165708000.000

Adjustment item: Percentage of * KD 0.000


(+ive for Addition or -ive for Deduction)

TOTAL AMOUNT TO FORM OF TENDER KD 165708000.000

AMOUNT IN WORDS: …One hundred sixty-five million seven hundred eight thousand Only..
(KUWAITI DINARS)
.…………………………………..………………..

SIGNATURE OF TENDERER ………………………………….………

DATE …05. 01. 2014…………………………….…………..………………..

STAMP

(* Tenderer to Specify)
SECTION f

PRICE ANALYSIS SCHEDULE


(INCLUDED UNDER DOCUMENT III.6)

Вам также может понравиться