METRADO DE PABELLON PRIMARIA 3 INC/ ESCALERA

ADECUACIÓN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA INSTITUCIÓN EDUCATIVA “JUAN CRESPO Y


PROYECTO: CASTILLO”-HUANUCO-HUANUCO-AMBO

Un
Item Descripción Rep. Cantidad Largo Ancho Altura Parcial Total
d
02 TRABAJOS PRELIMINARES GENERALES
02.03 TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO
02.03.01 TRAZO Y REPLANTEO DE OBRA m2 190.66
1.00 1.00 22.17 8.60 190.66

03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACIONES
03.01.01 EXCAVACION DE ZANJAS Y ZAPATAS MANUAL, Rt=0.87 kg/cm2, Df=1.70m m3 156.53
EJE A 1.00 1.00 21.61 1.50 1.70 55.11
EJE C' 1.00 1.00 22.17 1.75 1.70 65.96

EJE 4 1.00 1.00 5.35 0.90 1.70 8.19


EJE 5 Y 6 1.00 1.00 5.35 1.60 1.70 14.55

EJE 8 1.00 1.00 5.35 1.40 1.70 12.73

03.02 RELLENOS
03.02.01 RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJAS m3 61.29
-
EJE A 1.00 1.00 21.00 1.25 0.85 22.31
EJE C' 1.00 1.00 21.30 1.50 0.85 27.16

-
EJE 4 1.00 1.00 5.35 0.60 0.85 2.73
EJE 5 Y 6 1.00 1.00 5.35 0.95 0.85 4.32

-
EJE 8 1.00 1.00 5.35 1.05 0.85 4.77

03.02.03 RELLENO C/ARENILLA COMPACTADA m3 7.21


EJE A 1.00 1.00 21.00 1.25 0.10 2.63
EJE C' 1.00 1.00 21.30 1.50 0.10 3.20

EJE 4 1.00 1.00 5.35 0.60 0.10 0.32


EJE 5 Y 6 1.00 1.00 5.35 0.95 0.10 0.51
-
EJE 8 1.00 1.00 5.35 1.05 0.10 0.56

03.03 ESCARIFICADO
03.03.01 ESCARIFICADO Y COMPACTACION CON RODILLO m2 190.66
1.00 1.00 22.17 8.60 190.66

03.04 ELIMINACION DE EXCAVACIONES


03.04.01 ACARREO INTERNO DE MATERIAL EXCEDENTE CON CARRETILLA m3 123.81
Coef.
1.00 1.00 95.24 1.30 123.81

03.04.02 ELIMINACION DE DESMONTE,P/DEMOLICION DE ESTRUCT. CONCR, LADRIL. DIST.=5 KM m3 123.81


1.00 1.00 123.81 123.81
04 CONCRETO SIMPLE
04.01 SOLADOS
04.01.01 SOLADO PARA ZAPATAS Y CIMIENTOS: CONCRETO C:H 1:12 e=4".. m2 18.42
EJE A 1.00 1.00 21.61 1.50 0.20 6.48
EJE C' 1.00 1.00 22.17 1.75 0.20 7.76

EJE 4 1.00 1.00 5.35 0.90 0.20 0.96


EJE 5 Y 6 1.00 1.00 5.35 1.60 0.20 1.71

EJE 8 1.00 1.00 5.35 1.40 0.20 1.50

04.03 CIMIENTOS CORRIDOS


04.03.01 CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3 3.51
SECCION A-A 1.00 1.00 5.35 0.45 0.90 2.17
1.00 1.00 3.32 0.45 0.90 1.34

04.04 SOBRECIMIENTO
04.04.01 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO m2 93.54
EJE A 2.00 2.00 3.30 0.15 0.40 10.56
2.00 2.00 2.90 0.15 0.40 9.28
2.00 2.00 3.10 0.15 0.40 9.92
2.00 2.00 3.73 0.15 0.40 11.94

EJE C 2.00 2.00 3.30 0.15 0.40 10.56


2.00 2.00 1.90 0.15 0.40 6.08

EJE 4 2.00 2.00 2.75 0.25 0.40 8.80

EJE 5 2.00 2.00 2.75 0.25 0.40 8.80

EJE 6 2.00 2.00 2.75 0.25 0.40 8.80


EJE 8 2.00 2.00 2.75 0.25 0.40 8.80

04.04.02 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 8.78


EJE A 2.00 2.00 3.30 0.15 0.40 0.79
2.00 2.00 2.90 0.15 0.40 0.70
2.00 2.00 3.10 0.15 0.40 0.74
2.00 2.00 3.73 0.15 0.40 0.90
-
EJE C 2.00 2.00 3.30 0.15 0.40 0.79
2.00 2.00 1.90 0.15 0.40 0.46
-
EJE 4 2.00 2.00 2.75 0.25 0.40 1.10
-
EJE 5 2.00 2.00 2.75 0.25 0.40 1.10
-
EJE 6 2.00 2.00 2.75 0.25 0.40 1.10
-
EJE 8 2.00 2.00 2.75 0.25 0.40 1.10

05 CONCRETO ARMADO
05.02 VIGA DE CIMENTACION 42.85
05.02.01 VIGA DE CIMENTACION 210 KG/M2 m3
EJE A 1.00 1.00 21.61 1.50 0.50 16.21
EJE C' 1.00 1.00 22.17 1.75 0.50 19.40

EJE 4 1.00 1.00 5.35 0.90 0.50 2.41


EJE 5 Y 6 1.00 1.00 5.35 1.60 0.50 4.28

EJE 8 1.00 1.00 1.40 0.80 0.50 0.56

05.02.02 ENCOFRADO Y DESENCOFRADO EN CIMIENTOS REFORZADOS m2 43.03


EJE A 1.00 1.00 21.61 1.50 0.70 15.13
EJE C' 1.00 1.00 22.17 1.75 0.80 17.74

EJE 4 1.00 1.00 5.35 0.90 0.60 3.21


EJE 5 Y 6 1.00 1.00 5.35 1.60 0.60 3.21

EJE 8 1.00 1.00 5.35 0.80 0.70 3.75

05.02.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA CIMIENTOS kg 3,167.87


EJEJ A VIGA DE CIMENTACION VCC-B Traslape long. Coef.
5/8" 1.00 3.00 1.20 21.00 1.55 117.18
3/4" 1.00 4.00 1.20 21.00 2.24 225.79
1/2" 1.00 2.00 1.20 21.00 1.00 50.40
Parrilla 5/8" 1.00 6.00 1.20 21.00 1.55 234.36
5/8" 1.00 97.67 1.40 1.55 211.95
ESTRIVOS 3/8" 1.00 120.00 2.50 0.56 168.00

EJE C VIGA DE CIMENTACION VCC-A Traslape long. Coef.


5/8" 1.00 3.00 1.20 21.00 1.55 117.18
3/4" 1.00 4.00 1.20 21.00 2.24 225.79
1/2" 1.00 2.00 1.20 21.00 1.00 50.40
Parrilla 5/8" 1.00 6.00 1.20 21.00 1.55 234.36
5/8" 1.00 97.67 1.40 1.55 211.95
ESTRIVOS 3/8" 1.00 120.00 2.50 0.56 168.00

SECCION Q-Q Traslape long. Coef.


5/8" 1.00 6.00 1.20 21.00 1.55 234.36
3/4" 1.00 2.00 1.20 21.00 2.24 112.90

EJEJ 4 VIGA DE CIMENTACION VCC-1 Traslape long. Coef.


5/8" 1.00 6.00 7.60 1.55 70.68
3/4" 1.00 - 7.60 2.24 -
1/2" 1.00 - 7.60 1.00 -
Parrilla 5/8" 1.00 4.00 7.60 1.55 47.12
5/8" 1.00 35.35 1.00 1.55 54.79
ESTRIVOS 3/8" 1.00 43.43 1.50 0.56 36.48

EJE 5,6 VIGA DE CIMENTACION VCC-4 Traslape long. Coef.


5/8" 1.00 6.00 7.60 1.55 70.68
3/4" 1.00 4.00 7.60 2.24 68.10
1/2" 1.00 - 7.60 1.00 -
Parrilla 5/8" 1.00 6.00 7.60 1.55 70.68
5/8" 1.00 35.35 1.00 1.55 54.79
ESTRIVOS 3/8" 1.00 43.43 1.50 0.56 36.48

EJE 8" VIGA DE CIMENTACION VCC-4 Traslape long. Coef.


5/8" 1.00 2.00 7.60 1.55 23.56
3/4" 1.00 4.00 7.60 2.24 68.10
1/2" 1.00 2.00 7.60 1.00 15.20
Parrilla 5/8" 1.00 4.00 7.60 1.55 47.12
5/8" 1.00 35.35 1.00 1.55 54.79
ESTRIVOS 3/8" 1.00 43.43 1.50 0.56 36.48

SECCION Q-Q Traslape long. Coef.


5/8" 1.00 5.00 4.00 1.55 31.00

ESTRIVOS 3/8" 1.00 22.86 1.50 0.56 19.20


05.03 SOBRECIMIENTO REFORZADO
05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO m2 68.10
EJE A 1.00 1.00 3.30 0.25 0.65 2.15
2.00 1.00 2.90 0.25 0.65 3.77
2.00 1.00 3.09 0.25 0.65 4.02
2.00 1.00 3.11 0.25 0.65 4.04
2.00 1.00 3.73 0.25 0.65 4.85

EJE B 1.00 1.00 3.30 0.25 0.65 2.15


2.00 1.00 2.90 0.25 0.65 3.77
2.00 1.00 3.09 0.25 0.65 4.02
2.00 1.00 3.11 0.25 0.65 4.04
2.00 1.00 3.73 0.25 0.65 4.85

EJE 4" 2.00 1.00 2.90 0.25 0.75 4.35

EJE 5 2.00 1.00 2.90 0.25 0.75 4.35

EJE 6 2.00 1.00 2.90 0.25 0.75 4.35

EJE 7 2.00 1.00 2.90 0.25 0.75 4.35

EJE 8 2.00 1.00 2.90 0.25 0.75 4.35

EJE 9 2.00 1.00 2.90 0.25 0.75 4.35

EJE 10 2.00 1.00 2.90 0.25 0.75 4.35

05.03.02 SOBRE-CIMIENTO REFORZADO: ACERO FY=4200 kg/cm² kg 725.17

EJE A Traslape long. Coef.

3/8" 1.00 6.00 22.00 0.56 73.92


ESTRIVOS 3/8" 1.00 125.71 2.00 0.56 140.80

EJE C Traslape long. Coef.

3/8" 1.00 6.00 21.50 0.56 72.24


ESTRIVOS 3/8" 1.00 122.86 2.00 0.56 137.60

EJE 4 Traslape long. Coef.

3/8" 1.00 6.00 7.70 0.56 25.87


ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE 5 Traslape long. Coef.

3/8" 1.00 6.00 7.70 0.56 25.87


ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE 6 Traslape long. Coef.

3/8" 1.00 6.00 7.70 0.56 25.87


ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

EJE 8 Traslape long. Coef.


3/8" 1.00 6.00 7.70 0.56 25.87
ESTRIVOS 3/8" 1.00 44.00 2.00 0.56 49.28

05.03.03 CONCRETO f'c=210 kg/cm2 PARA SOBRECIMIENTO m3 12.31


EJE A 1.00 1.00 3.30 0.25 0.55 0.45
2.00 1.00 2.90 0.25 0.55 0.80
2.00 1.00 3.09 0.25 0.55 0.85
2.00 1.00 3.11 0.25 0.55 0.86
2.00 1.00 3.73 0.25 0.55 1.03

EJE B 1.00 1.00 3.30 0.25 0.55 0.45


2.00 1.00 2.90 0.25 0.55 0.80
2.00 1.00 3.09 0.25 0.55 0.85
2.00 1.00 3.11 0.25 0.55 0.86
2.00 1.00 3.73 0.25 0.55 1.03

EJE 4" 2.00 1.00 2.90 0.25 0.75 1.09

EJE 5 2.00 1.00 2.90 0.25 0.75 1.09

EJE 6 2.00 1.00 2.90 0.25 0.75 1.09

EJE 8 2.00 1.00 2.90 0.25 0.75 1.09

05.05 COLUMNAS
05.05.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 35.39
Area
C-1 6.00 1.00 0.1875 9.50 10.69
C-2 4.00 1.00 0.2750 9.50 10.45
C-3 2.00 1.00 0.2625 9.50 4.99
C-4 5.00 1.00 0.1250 9.50 5.94
P-1 2.00 1.00 0.1750 9.50 3.33

05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 336.78


perimetro
C-1 6.00 1.00 2.00 9.50 114.00
C-2 4.00 1.00 2.60 9.50 98.80
C-3 2.00 1.00 2.60 9.50 49.40
C-4 5.00 1.00 1.50 9.50 71.25
P-1 2.00 1.00 0.1750 9.50 3.33

05.05.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 7,482.15


C-1 Traslape long. Coef.
5/8" 6.00 8.00 1.20 9.50 1.55 848.16
1/2" 6.00 4.00 1.20 9.50 1.00 273.60
ESTRIVO 3/8" 4.00 54.29 2.00 0.56 243.20
ESTRIVO 3/8" 4.00 11.43 1.65 0.56 42.24
S. 3/8" 8.00 54.29 1.65 0.56 401.28

C-2 Traslape long. Coef.

3/4" 4.00 5.00 1.20 9.50 2.24 510.72


5/8" 4.00 12.00 1.20 9.50 1.55 848.16
1/2" 4.00 6.00 1.20 9.50 1.00 273.60
ESTRIVO 3/8" 4.00 54.29 2.70 0.56 328.32
ESTRIVO 3/8" 4.00 15.43 1.80 0.56 62.21
S. 3/8" 12.00 54.29 1.65 0.56 601.92

C-3 Traslape long. Coef.

3/4" 2.00 2.00 1.20 9.50 2.24 102.14


5/8" 2.00 8.00 1.20 9.50 1.55 282.72
ESTRIVO 3/8" 2.00 54.29 2.70 0.56 164.16
ESTRIVO 3/8" 2.00 15.43 1.80 0.56 31.10
S. 3/8" 12.00 54.29 1.65 0.56 601.92

C-4 Traslape long. Coef.

5/8" 5.00 4.00 1.06 9.50 1.55 310.86


1/2" 5.00 4.00 9.50 1.00 190.00
ESTRIVO 3/8" 5.00 54.29 2.70 0.56 410.40
ESTRIVO 3/8" 5.00 15.43 1.80 0.56 77.76

P-1 Traslape long. Coef.


3/4" 2.00 - 1.06 9.50 2.24 -
5/8" 2.00 12.00 1.06 9.50 1.55 373.03
1/2" - 4.00 9.50 1.00 -
ESTRIVO 3/8" 2.00 54.29 2.50 0.56 152.00
ESTRIVO 3/8" 2.00 54.29 2.50 0.56 152.00
S. 3/8" 4.00 54.29 1.65 0.56 200.64

05.06 COLUMNETAS
05.06.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 m3 1.65
EJE A CA 20.00 2.00 0.25 0.15 1.10 1.65

05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 17.60


EJE A' CA 20.00 2.00 0.25 0.15 1.10 17.60

05.06.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNETAS kg 194.35


Traslape long. Coef.
EJE A' CA 3/8" 40.00 4.00 2.30 0.56 71.68
ESTRIVO 1/4" 40.00 15.33 0.70 0.25 122.67

05.07 VIGAS
05.07.01 CONCRETO EN VIGAS f'c=210 kg/cm2 m3 36.05
1er PISO
EJE A VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE A VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72


2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE C VS - 102 (.20X.55) 4.00 1.00 3.12 0.20 0.55 1.37


2.00 1.00 3.65 0.20 0.55 0.80
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 4 VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 3.12 0.25 0.55 0.43

EJE 5 VP - 101(.25x.55) 1.00 1.00 2.50 0.25 0.55 0.34


1.00 1.00 2.92 0.25 0.55 0.40

EJE 6 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE 7 VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE 8 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE 9 VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE 10 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

2DO PISO
EJE A VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE C VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72


2.00 1.00 3.02 0.25 0.55 0.83
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE D CORREDOR VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 1.72
2.00 1.00 3.02 0.25 0.55 0.83

EJE D VS - 202 (.20X.55) 4.00 1.00 3.12 0.20 0.55 1.37


2.00 1.00 3.65 0.20 0.55 0.80
ESCALERA 1.00 1.00 3.30 0.25 0.40 0.33

EJE 4 VP - 201(.25x.40) 2.00 1.00 2.90 0.25 0.40 0.58


1.00 1.00 3.12 0.25 0.55 0.43

EJE 5' VP - 201(.25x.55) 1.00 1.00 2.50 0.25 0.55 0.34


1.00 1.00 2.92 0.25 0.55 0.40

EJE 6 VP -202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE 7 VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE 8 VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

EJE 9 VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 0.65


1.00 1.00 2.50 0.25 0.55 0.34

EJE 10' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 1.04


1.00 1.00 2.50 0.30 0.55 0.41

VS-203 (.15x.28) 4.00 1.00 3.12 0.15 0.28 0.52


2.00 1.00 3.02 0.15 0.28 0.25

05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 364.89

EJE A VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE A VS - 101 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE C VS - 102 (.20X.55) 4.00 1.00 3.12 0.20 0.55 16.22


2.00 1.00 3.65 0.20 0.55 9.49
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 4 VP - 101(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 3.12 0.25 0.55 4.21

EJE 5 VP - 101(.25x.55) 1.00 1.00 2.50 0.25 0.55 3.38


1.00 1.00 2.92 0.25 0.55 3.94

EJE 6 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE 7 VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE 8 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE 9 VP - 103(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE 10 VP - 102(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

2DO PISO
EJE A VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85
2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE C VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85


2.00 1.00 3.02 0.25 0.55 8.15
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE D CORREDOR VS - 201 (.25X.55) 4.00 1.00 3.12 0.25 0.55 16.85
2.00 1.00 3.02 0.25 0.55 8.15

EJE D VS - 202 (.20X.55) 4.00 1.00 3.12 0.20 0.55 16.22


2.00 1.00 3.65 0.20 0.55 9.49
ESCALERA 1.00 1.00 3.30 0.25 0.40 3.47

EJE 4 VP - 201(.25x.40) 2.00 1.00 2.90 0.25 0.40 6.09


1.00 1.00 3.12 0.25 0.55 4.21

EJE 5' VP - 201(.25x.55) 1.00 1.00 2.50 0.25 0.55 3.38


1.00 1.00 2.92 0.25 0.55 3.94
EJE 6 VP -202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82
1.00 1.00 2.50 0.30 0.55 3.50

EJE 7 VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE 8 VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

EJE 9 VP - 203(.25x.45) 2.00 1.00 2.90 0.25 0.45 6.67


1.00 1.00 2.50 0.25 0.55 3.38

EJE 10' VP - 202(.30x.55) 1.00 1.00 6.30 0.30 0.55 8.82


1.00 1.00 2.50 0.30 0.55 3.50

-
VS-203 (.15x.28) 4.00 1.00 3.12 0.15 0.28 8.86
2.00 1.00 3.02 0.15 0.28
EJE I' VP - 201(.25x.55 2.00 1.00 2.90 0.25 0.40 6.09
1.00 1.00 2.50 0.25 0.55 3.38

05.07.03 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS kg 12,432.53


1ER PISO
Traslape long. Coef.
EJE A VS - 101 (.25X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE C VS - 101 (.25X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE D VS - 102 (.20X.55) 5/8" 4.00 1.00 28.00 1.55 173.60
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 160.00 1.70 0.56 609.28

Traslape long. Coef.


EJE 4 VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE 5 VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 6 VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE 7 VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 8 VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38

Traslape long. Coef.


EJE 9 VP - 102(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 10 VP - 101(.25x.40) 5/8" 4.00 1.00 7.60 1.55 47.12
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 43.43 1.70 0.56 165.38
2DO PISO
Traslape long. Coef.
EJE A VS - 201 (.25X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE C VS - 201 (.25X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


VS - 202 (.20X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE D VS - 202 (.20X.55) 5/8" 4.00 1.00 27.00 1.55 167.40
3/4" 8.00 5.00 1.20 2.24 107.52
5/8" 4.00 5.00 2.70 1.55 83.70

ESTRIVOS 3/8" 4.00 1.00 154.29 1.70 0.56 587.52

Traslape long. Coef.


EJE 5 VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE 6 VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 7 VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE 8 VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 9 VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


EJE 10 VP - 202(.30x.55) 3/4" 4.00 1.00 10.00 1.55 62.00
5/8" 1.00 4.00 1.80 1.55 11.16
5/8" 4.00 4.00 3.20 1.55 79.36
5/8" 1.00 4.00 5.20 1.55 32.24
5/8" 2.00 4.00 5.00 1.55 62.00
ESTRIVOS 3/8" 4.00 1.00 57.14 1.70 0.56 217.60

Traslape long. Coef.


EJE 11 VP - 201(.25x.40) 5/8" 4.00 1.00 7.70 1.55 47.74
1/2" 1.00 4.00 2.50 1.55 15.50
5/8" 4.00 4.00 3.20 1.55 79.36
1/2" 1.00 1.00 3.20 1.00 3.20
ESTRIVOS 3/8" 4.00 1.00 44.00 1.70 0.56 167.55

Traslape long. Coef.


VS-203 (.15x.28) 5/8" 4.00 1.00 27.00 1.55 167.40
ESTRIVOS 3/8" 4.00 154.29 0.80 0.56 276.48

VIGETAS
CONCRETO EN VIGETAS f'c=210 kg/cm2 m3 0.66
1ER PISO
SECCION T-T EJE A 5.00 1.00 3.30 0.15 0.10 0.25
SECCION T-T EJE C 1.00 1.00 2.25 0.15 0.10 0.03
1.00 1.00 3.30 0.15 0.10 0.05

2DO PISO
SECCION T-T EJE A 5.00 1.00 3.30 0.15 0.10 0.25
SECCION T-T EJE C 1.00 1.00 2.25 0.15 0.10 0.03
1.00 1.00 3.30 0.15 0.10 0.05
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGETAS m2 4.41

1ER PISO
SECCION T-T EJE A 5.00 1.00 3.30 0.10 1.65
SECCION T-T EJE C 1.00 1.00 2.25 0.10 0.23
1.00 1.00 3.30 0.10 0.33

2DO PISO
SECCION T-T EJE A 5.00 1.00 3.30 0.10 1.65
SECCION T-T EJE C 1.00 1.00 2.25 0.10 0.23
1.00 1.00 3.30 0.10 0.33

ACERO fy=4200 kg/cm2 GRADO 60 en VIGETAS kg 50.37

1ER PISO Traslape long. Coef.


SECCION T-T EJE A3/8" 5.00 1.00 3.60 0.56 10.08
ESTRIVO 1/4" 5.00 18.00 0.30 0.25 6.75
SECCION T-T EJE C 3/8" 1.00 3.00 2.50 0.56 4.20
ESTRIVO 1/4" 1.00 12.50 0.30 0.25 0.94
3/8" 2.00 3.00 3.30 0.10 1.98
ESTRIVO 1/4" 1.00 16.50 0.30 0.25 1.24

2DO PSIO Traslape long. Coef.


SECCION T-T EJE A3/8" 5.00 1.00 3.60 0.56 10.08
ESTRIVO 1/4" 5.00 18.00 0.30 0.25 6.75
SECCION T-T EJE C 3/8" 1.00 3.00 2.50 0.56 4.20
ESTRIVO 1/4" 1.00 12.50 0.30 0.25 0.94
3/8" 2.00 3.00 3.30 0.10 1.98
ESTRIVO 1/4" 1.00 16.50 0.30 0.25 1.24

05.09 LOSA MACIZA


05.09.01 LOSAS MACIZAS.- ENCOFRADO Y DESENCOFRADO m2 15.96
1ER PISO
ESCALERA 1.00 1.00 4.20 1.90 7.98
2DO PISO
ESCALERA 1.00 1.00 4.20 1.90 7.98

05.09.02 LOSAS MACIZAS.- CONC.175 kg/cm2 m3 3.19


1ER PISO
ESCALERA 1.00 1.00 4.20 1.90 0.20 1.60
2DO PISO
ESCALERA 1.00 1.00 4.20 1.90 0.20 1.60

05.09.03 LOSA MACIZA: ACERO FY=4200 kg/cm² kg 131.60

2DO PISO Traslape long. Coef.


ESCALERA 3/8" 2.00 12.50 4.70 0.56 65.80
2.00 23.50 2.50 0.56 65.80

05.08 LOSAS ALIGERADAS


05.08.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 m3 37.49
1ER PISO Coef.
4.00 1.00 6.80 3.80 0.11 11.37
4.00 1.00 3.80 2.30 0.11 3.85

2DO PISO Coef.


aula 4.00 1.00 6.80 3.80 0.11 11.37
corredor 4.00 1.00 3.80 2.30 0.11 3.85
ESCALERA 1.00 1.00 6.80 4.20 0.11 3.14
1.00 1.00 4.20 1.35 0.11 0.62
1.00 1.00 4.20 2.30 0.11 1.06
volado 4.00 1.00 3.76 1.35 0.11 2.23

05.08.02 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2 324.45


1ER PISO
aula 4.00 1.00 6.80 3.80 103.36
corredor 4.00 1.00 3.80 2.30 34.96

2DO PISO
aula 4.00 1.00 6.80 3.35 91.12
corredor 4.00 1.00 3.35 2.30 30.82
ESCALERA 1.00 1.00 6.80 4.20 28.56
1.00 1.00 4.20 1.35 5.67
1.00 1.00 4.20 2.30 9.66
volado 4.00 1.00 3.76 1.35 20.30

05.08.03 LADRILLO ARCILLA PARA TECHO 15X30X30 CM u 2,702.70


1ER PISO Coef.
aula 4.00 1.00 6.80 3.80 8.33 860.99
4.00 1.00 3.80 2.30 8.33 291.22

2DO PISO
aula 4.00 1.00 6.80 3.35 8.33 759.03
corredor 4.00 1.00 3.35 2.30 8.33 256.73
ESCALERA 1.00 1.00 6.80 4.20 8.33 237.90
1.00 1.00 4.20 1.35 8.33 47.23
1.00 1.00 4.20 2.30 8.33 80.47
volado 4.00 1.00 3.76 1.35 8.33 169.13
05.08.04 ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSA ALIGERADA kg 2,043.71
1ER PISO Traslape long. Coef.
AULAS 1/2" 22.00 1.00 1.20 21.00 1.00 554.40
3/8" 22.00 1.00 1.00 0.56 12.32
1/2" 22.00 1.00 2.70 1.00 59.40
1/2" 22.00 1.00 2.00 1.00 44.00
CORREDOR 3/8" 4.00 1.00 3.00 0.56 6.72

2DO PISO Traslape long. Coef.


AULAS 1/2" 27.00 1.00 1.20 21.00 1.00 680.40
3/8" 27.00 1.00 1.00 0.56 15.12
1/2" 27.00 1.00 2.70 1.00 72.90
1/2" 27.00 1.00 2.00 1.00 54.00
CORREDOR 3/8" 4.00 1.00 3.00 0.56 6.72
TEMPERATURA 1/4" 1.00 70.00 10.00 0.25 175.00

ESCALERA 1/2" 27.00 1.00 4.90 1.00 132.30


3/8" 27.00 1.00 4.90 0.56 74.09
3/8" 27.00 1.00 4.90 0.56 74.09
TEMPERATURA 1/4" 1.00 70.00 4.70 0.25 82.25

05.11 ESCALERAS
05.11.01 ACERO CORRUGADO FY=4200 KG/CM2 EN ESCALERA kg 428.80
Traslape Long. Coef.
acero 1° tramo 1/2" 1.00 1.00 4.00 1.00 4.00
1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 2° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 3° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

acero 3° tramo 1/2" 1.00 1.00 4.00 1.00 4.00


1.00 2.00 2.50 1.00 5.00
1.00 1.00 3.20 1.00 3.20
1.00 1.00 2.00 1.00 2.00
1.00 1.00 3.00 1.00 3.00
acero tranversal 1.00 36.00 2.50 1.00 90.00

ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 63.70


fondo 2.00 2.00 3.00 2.10 25.20
descanzo 2.00 1.00 4.20 2.50 21.00
contrapasos 2.00 20.00 2.50 0.18 17.50

CONCRETO EN ESCALERA CON f'c=210 kg/cm2 m3 23.25


area
pasos 2.00 20.00 0.15 2.50 15.00
descanzo 2.00 1.00 4.20 2.50 0.25 5.25
cimiento 2.00 1.00 2.50 0.50 1.20 3.00