3900 Series NodeB

Commissioning

www.huawei.com

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Objectives
 Upon completion of this course, you will be able to:
 Describe the procedure of NodeB commissioning

 Perform NodeB commissioning

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

1
References
 《NodeB LMT User Guide》
 《NodeB Commissioning Guide》
 《DBS3900 Hardware Description》
 《BTS3900 Hardware Description》

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Contents
1. Preparation for NodeB Commissioning

2. Procedure for NodeB Commissioning

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

2
Contents
1. Preparation for NodeB Commissioning

2. Procedure for NodeB Commissioning

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Preparation for NodeB


Commissioning
 Prerequisites at NodeB side
 The NodeB hardware passes the installation check

 Checking the DIP switch setting of WMPT, WTRP

 The NodeB is powered on

 The data configuration file is ready

 Prerequisites at RNC side


 The RNC connected to the NodeB works well

 The data of the NodeB to be commissioned has been


configured in RNC

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

3
Preparation for NodeB
Commissioning
 Selecting commissioning modes
 Local commissioning
 The transmission is unavailable

 Perform NodeB commissioning on site with LMT

 Remote commissioning
 The transmission is available

 The O&M channel between RNC and NodeB works properly

 Perform NodeB commissioning remotely through M2000

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Contents
1. Preparation for NodeB Commissioning

2. Procedure for NodeB Commissioning

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

4
Procedure for NodeB Commissioning
 Step 1: Logging in to NodeB through the LMT
 Set the IP address of the LMT PC
 The default NodeB local maintenance IP address is 17.21.2.15

 Connect the LMT PC to the Ethernet Port on WMPT board

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Procedure for NodeB Commissioning


 Step 2: Checking the current NodeB BootRom and software
version
 A, if NodeB BootRom and software in active directory are the
right version to be used, then keep the software

 B, If the right BootRom version is stored in the standby


directory, activate it. Otherwise download the right BootRom
version and activate it

 C, if the right software version is stored in the standby directory,


activate it. Otherwise download the right software version and
activate it

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

5
Procedure for NodeB Commissioning
 Step 3: Downloading the NodeB data configuration file
 The file name of the NodeB data configuration file must be
NodeBCfg.xml

 After the download is finished, reset the NodeB to make the


configuration file work

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Procedure for NodeB Commissioning


 Step 4: Handling alarms during NodeB commissioning

 Step 5: Checking the running state of the NodeB


 Checking SNTP (Simple Network Time Protocol)

 Checking the status of a cell

 Measuring RTWP

 Monitoring the output power of the NodeB

 Step 6: Initially activating the NodeB license

 Step 7: Recording NodeB information in data sheet

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

6
Procedure for NodeB Commissioning
 Step 8: Commissioning the NodeB RET antenna (If RET is
used)
 Preparation for the RET antenna commissioning
 Data configuration file of the RET antenna

 Vendor code and type of the NodeB RET antenna

 Tilt of the RET antenna to be commissioned

 Step 9: Commissioning the TMA (If TMA is used)

Copyright © 2008 Huawei Technologies Co., Ltd. All rights reserved.

Thank you
www.huawei.com