Вы находитесь на странице: 1из 1

PL05-051-QD-07 A Revision

Pipeline & Specialty Services


Pressurisation Report (Air Inclusion Calculation)
PIPELINE REFERENCE:
OPERATION:
SUBCONTRACTOR:
CONTRACTOR:
CLIENT:
THIRD PARTY:
CONTRACT NO.:
LOCATION: To be filled in for each operation

Length: mtrs Volume: m3

Diameter: mm Pump Capacity: Volume/Stroke:


Wall Thickness: mm
Time Press Strokes Stroke Total Time Press Strokes Stroke Total Notes
-2
kg.cm Diff. Volume kg.cm-2 Diff. Volume

AIR INCLUSION CALCULATIONS: AIR INCLUSION =


(A) Actual Volume (m3) 0.000 A-B= C x 100
3
(B) Theoretical Volume (m ) 0.000 D
3
(C) Difference in Volume (m ) 0.000
3
(D) Total Fill Volume (m ) 0.00 #DIV/0! % AIR CONTENT

Subcontractor Contractor Client Third Party


WTFD TBA
Name:
Sign:
Date:

Rev. A, July 2005 Page 1 of 1 Print Date: 12/21/2006