Вы находитесь на странице: 1из 9

Journal of

Journal of Mining and Metallurgy, 45 A (1) (2009) 49 - 57 Mining and

Metallurgy

TUNNEL ANALYSIS IN FAULT ZONES AND THE EFFECTS OF STRESS


DISTRIBUTION ON THE SUPPORT

Milenko Ljubojev*#, Mevludin Avdić**, Mile Bugarin*,


Ratomir Popović* and Dragan Ignjatović*

*
Mining and Metallurgy Institute Bor, Zeleni bulevar 35, 19210 Bor, Serbia
**
University of Tuzla, Mining, Geology and Faculty of Civil Engineering,
Univerzitetska 2, 75000 Tuzla, Bosnia and Herzegovina

(Received 27 August 2009; accepted 16 November 2009)

Abstract

Tunnel or any other underground room construction in general is a complex problem. The
complexity of the problem is reflected in the spatial position of underground room, which may
be close to the surface terrain and environment in which the object is located. In many cases
environment is heterogeneous, and special attention in this work is given to the fault zone
impact on distribution of the stress and deformation states around the room.
The calculations is performed in steps of load increasing, and in this work are given the
views of vertical shifts allocation, the appearance of plasticity in the massif and the position of
occurrence of cracks in the tunnel screening. It also presents a distribution of vertical and
tangential stress of the massif.
Analysis of stress – deformation state was made with the finite element method. Rock
material was modeled as elasticity-plastic material with Mohr-Coulomb fracture condition and
the support material is concrete MB 300 and it was modeled as concrete material.

Key words: rock massif, fault zone, stress - deformation state, finite element method.

1. Introduction high values of safety factors eliminate the


consequences of these approximations.
Design and built tunnels assumed Today we meet with the situation that the
isotropic environment and tunnel routes tunnels that are built under one conditions
are simplified with this assumption. found in the other conditions. These
However, rock massif is expressed with changes are mainly related to the change
greater or less anisotropy. The of the vertical component of the load (the
calculations are taken with less value of construction of embankment above the
geomechanical parameters, which with tunnel). Load changes above underground

#
Corresponding author: milenko.ljubojev@irmbor.co.rs
50 M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57

facility will cause a stress – deformation Flotation tailing dump is bordered with
change in the status of massif, which may dams 1A and 2A, which were projected to
be reflected on the tunnel or its parts. As the level of K+375 m, and with total
the first exposed are areas that are in the capacity of 94,3·106 [m3].
engineering geological terms classified in New flotation tailing dump (field 2) is
the zone of risk. Checking the impact bordered with dams 2A and 3A, which
changes of the vertical components values were projected to the level of K+350 m,
must be made, and in this paper is given and with total capacity of 89,4·106 [m3].
an example of assessment of increasing Considering that the dams were
the amount of deferred mass on the tunnel projected to the level of K+350 m,
construction. including fact that it is possible to store
flotation tailing dump only till the middle
2. Describe of the problem of this year (2008), it is necessary to
ensure increasing level of the dams up to
Necessity of increasing capacity of the K+385 m.
flotation tailing dump, and also increasing Therefore, Krivelj’s river (figure 1) has
overtop of the dams 1A, 2A and 3A to the to be evacuating by:
level of K+385 m has brought along - existing tunnel (zone of the field 1);
evacuation of Krivelj´s river by two D = 3,0 [m] and L = 1.414 [m],
tunnels: the one that already exists, and - new built tunnel; D = 3,0 [m] and
the other one who will be located on the L = 2.400 [m], along the right bank of the
right bank of the flotation tailing dump. flotation tailing dump.
For delay of flotation tailing, open pit Construction of new tunnel on the right
mine “Veliki Krivelj” uses an area, got by bank of the flotation tailing dump makes
partitioning of the Krivelj’s river valley. possible increasing level in the field 2,
In the beginning of the mine work, the which significantly increase capacity of
area near flotation objects was taken (field storage space (approximately 83,3·106
1) for tailing dump. Flotation tailing dump [m3]) [6].
expanded in 1990 by taking extra space of Geomechanic characteristics of the
the Krivelj’s river valley, downstream massif, in which is considered a problem
from field 1. and characteristics of the support material
are given in table 1.

Table 1. Geomechanical parameters


Parameters sandstone marl concrete
Young's Modulus E (MPa) 213 173 24800
Poisson's ratio ν 0.4 0.34 0.15
Cohesion c (MPa) 4.5 3.5 -
Tensile strength σz (MPa) 0.18 0.11 4.1
Friction angle φ (0) 38 26 -
Density  (kg/m3) 2457 2000 2500
M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57 51

3. Calculation of stress-deformation concrete material. Load modeling of the


state dumped mass was carried as balanced
load with the intensity gdyke * Hdyke.
Analysis of stress – deformation state Performed calculating model is shown in
was made with the finite element method. Figure 3, as well as the position of the
Rock material was modeled as elasticity- fault zone, based on engineering-
plastic material with Mohr-Coulomb geological description of the location in
fracture condition and the support material which the elements of fault position in
is concrete MB 300 and it was modeled as space are given.

Figure 1. Model for finite element method analysis


52 M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57

Embankment load activity is simulated calculation is done with two variations of


with increasing of intensity of the the position of layers:
continuous load, where the value 1 shows - Variant 1 with sandstone above and
the current state of dumped mass (TIME - Variant 2 Marlon above (in the ceil-
3) and values over 1 represent increase of ing of the room).
stockpiling height of the masses. The

Time function 1
1.1

1
time function value

0.9

0.8

0.7

0.6

0.5
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
time

Figure 2. Increase load function

4. Analysis of calculation results The end of solution convergence was


after 4th steps, i.e. after increasing the
The calculations is performed in steps amount of 10% compared to the previous
of load increasing, and in this work are level of dumping. The first version of the
given the views of vertical shifts position of the layers observed a large
allocation, the appearance of plasticity in number of cracks in support elements,
the massif and the position of occurrence while in the second variant the number
of cracks in the tunnel screening (Figures and position are quite different. Also, in
3a and 3b for the first variant, and Figures the second variant we have significantly
5a and 5b for the second variant). It also different timing and intensity of plastic
presents a distribution of vertical and deformation. However, common to both
tangential stress of the massif (Figures 4a variants is that increasing of the level over
and 4b and Figures 6a and 6b). 10% presents great risk, compared to the
previous height.
M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57 53

3a)

3b)
Figures 3a and 3b. Vertical displacement, plastic deformations
and cracking for 1st variation of the layers position
54 M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57

4a)

4b)
Figures 4a and 4b. Distribution of the vertical and shearing stress
in massif for 1st variation of the layers position
M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57 55

5a)

5b)
Figures 5a and 5b. Vertical displacement, plastic deformations
and cracking for 2nd variation of the layers position
56 M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57

6a)

6b)
Figures 6a and 6b. Distribution of the vertical and shearing stress
in massif for 2nd variation of the layers position
M. Ljubojev et al. / JMM 45 A (1) (2009) 49 - 57 57

5. Conclusion very important, since dumping material


has to consolidate and hardening, which is
The work indicates the possibility of a positive feature, but on the other side,
applying numerical analysis to assess the under the influence of load screening
conditions of exploitation of underground changes its properties. To obtain better
facilities. The paper gives an example of data it is necessary to check the
applying FEM, and elasticity-plastic characteristics of the tunnel screening and
analysis of the problem of increasing the the parameters of previously dumped
embankment above the tunnel. The mass. If there are observation dates of
validity of the resulting data would be landmark’s points in the tunnel, calcula-
complete if the analysis took into account tion could be making with elasticity –
the time factor. Influence of time factor is viscous - plastic analysis.

6. References 5. Ljubojev M., Popović R., Bugarin M.,


Deformation pressure of support
1. Adina R&D AUI 8.5.2. Brady B. H. stiffness and characteristics of rock
G, Brown E.T., Rock mechanics for massive on "Krivelj’s river”, tunnel
underground mining, Springer Science route, (in Serbian), Mining works
+ Bussiness Media, (2005). journal, 2/2008, Bor, (2008).
2. De Souza Neto E. A., Peric D. and 6. Ljubojev M., Popović R., Ignjatović
Owen D.R.J., Computational methods D., Đurđevac Ignjatović L., Necessity
for plasticity: theory and application, of transposition manifold of Krivelj’s
John Wiley and Sons, LTD Publica- river, 40th International October
tion, (2008). conference on Mining and Metallurgy,
3. Klaus-Jiirgen Bathe, Finite element 5th – 8th October 2008, Sokobanja,
procedures, Prentice-Hall, Inc. ISBN Serbia, (2008).
0-13-301456-4, (1996). 7. Ljubojev M., Popović R., Project of
4. Ljubojev M., Popović R., Geo- geological, physical and mechanical
mechanical basis, (in Serbian), RTB rock researches on tunnel line for
Bor, Copper Institute Bor, (2006). relocation of the Krivelj’s river, (in
Serbian), Bor, (2007).

Вам также может понравиться