LIST OF OUTSTANDING WORKS

%
NO ACTIVITY/TASK DATE START DATE FINISH COMPLETE

CIVIL, STRUCTURE & BUILDING WORKS


A Wash Water Collection & Sludge Balancing Tank
1 Walkway with 300mm x 400mm Opening at Wall E-F
i To construct walkway with 300mm x 400mm Opening at Wall E-F 0.00%
2 Painting works
i Painting of the surface of walkway & internal wall of drywells 0.00%
ii Cleanup site 25-Apr-18 75.00%
3 Backfilling Works
i To backfill & compact outer perimeter of WWCT & SBT 28-Apr-18 90.00%
B Dewatering Platform (Geotube)
LIST OF OUTSTANDING WORKS
%
NO ACTIVITY/TASK DATE START DATE FINISH COMPLETE
B
1 Geotube
i Installation of geotube and necessarry works 0.00%
ii Cleanup site 0.00%
C Reinstatement Works
1 To reinstate existing V-shape drain from Polymer Building to existing sump
2 To fill up installed culvert with mortar along beneath Polymer building
PIPEWORKS
1 Installation, Cleaning & Testing Works
i Miscellaneous works (not yet done - ss handrailing, catladder & chequered plate cover) 19-Feb-18 80.00%
LIST OF OUTSTANDING WORKS
%
NO ACTIVITY/TASK DATE START DATE FINISH COMPLETE
MECHANICAL WORKS
1 Wash Water Collection & Sludge Balancing Tank
a Procurement & Delivery
i Lifting Davit, High Pressure Rubber Hose 5-Mar-18 75.00%
b Installation Works
i Lifting Davit, High Pressure Rubber Hose 0.00%
4 Miscellaneous
c Installation Works
i Air Compressor Set 50.00%
ELECTRICAL WORKS
1 Switchboard/MCC Panel
i Installation works 50.00%
LIST OF OUTSTANDING WORKS
%
NO ACTIVITY/TASK DATE START DATE FINISH COMPLETE
2 Distribution & Earthing System
i Installation & cabling works 26-Apr-18 70.00%
3 Compound Lighting System
i Installation & cabling works 26-Apr-18 50.00%
4 Miscellaneous
i Any other neccessary works 2-Apr-18 90.00%
INSTRUMENTATION WORKS
1 Procurement & Fabrication
i To procure & fabricate Instrument Panel 22-Nov-18 75.00%
2 Installation Works
i Installation & signal cabling works 0.00%
INFRASTRUCTURE WORKS
1 Roadworks
i Site clearance, levelling & compaction 0.00%
ii Lay of crusher-run & premix 0.00%
SITE HANDOVER WORKS
1 Training, Testing, Commisioning & Maintenance
i Preparation of Testing & Report 7-Jun-18 30.00%
ii Pre-commissioning 0.00%
iii Setting to Work 0.00%
iv Commissioning & Training 0.00%
v Handing Over to Client 0.00%