Berat Beban
Tebal Tinggi Panjang Luas Beban ke
Beban Mati Jenis perluasan
(m) (m) (m) (m2) kolom (kN)
(kN/m3) (kN/m2)
Beban pelat lantai 0.1 24 2.4 18.0625 43.35
Beban Pasir 0.01 16 0.16 18.0625 2.89
Beban spesi 0.03 22 0.66 18.0625 11.92125
Beban Keramik 0.01 22 0.22 18.0625 3.97375
Beban Plafon 0.2 18.0625 3.6125
Beban instalasi
ME 0.25 18.0625 4.515625
Beban Balok
Arah a 4.25 24 0.12 12.24
Beban Balok
Arah b 4.25 24 0.12 12.24
Pasangan 1/2 bata 4 8.5 2.5 85
Σ Beban Mati 109.48
Σ Beban Hidup 2.5 18.0625 45.15625
= 56161,8 𝑚𝑚2
= √56161,8
= 236,984 𝑚𝑚
𝑏𝑝𝑎𝑘𝑎𝑖 = ℎ𝑝𝑎𝑘𝑎𝑖 = 300 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 1851
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 4
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 13 𝑚𝑚
4 × 𝐴perlu
𝑑=√
𝜋
4 × 0,418
𝑑=√
3,14
𝑙 𝑓y
ℎmin = × (0,4 + )
21 700
4,25 400
= × (0,4 + )
21 700
= 19.65986
ℎpakai = 40 𝑐𝑚
2
𝑏min = × ℎpakai
3
2
= × 40
3
= 26.667
𝑏pakai = 30 𝑐𝑚
- Menginput Dimensi Penampang Balok kedalam SAP 2000
- Hasil Running Tulangan Perlu pada SAP 2000 ( arah XZ )
a. Detail lantai 1
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 251
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 124
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 62
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 158
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
b. Detail lantai 2
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 242
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 120
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 60
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 167
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
c. Detail lantai 3
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 235
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 117
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 58
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 177
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
d. Detail lantai 4
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 231
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 114
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 57
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 183
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
e. Detail lantai 5
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 26
𝑛. 𝑑 = √
3,14
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 56
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 ×7
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 79
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
f. Perhitungan Sengkang
4 × 𝐴perlu
𝑑=√
𝜋
4 × 0,252
𝑑=√
3,14
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 201
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
4 × 100
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 50
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 212
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
b. Detail lantai 2
- Tulangan Tumpuan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 193
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 98
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 48
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 223
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
c. Detail lantai 3
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 183
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 111
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 46
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 233
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
d. Detail lantai 4
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 175
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 120
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 43
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 242
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
e. Detail lantai 5
- Tulangan Tumpuan ( Bagian Atas )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 ×8
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
- Tulangan Tumpuan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 71
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 ×5
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 2
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 8 𝑚𝑚
- Tulangan Lapangan ( Bagian Bawah )
4 × 𝐴perlu
𝑛. 𝑑 = √
𝜋
4 × 95
𝑛. 𝑑 = √
3,14
𝑛 ( 𝑗𝑢𝑚𝑙𝑎ℎ 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 1
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 18 𝑚𝑚
f. Perhitungan Sengkang
4 × 𝐴perlu
𝑑=√
𝜋
4 × 0,405
𝑑=√
3,14
𝑑 ( 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑡𝑢𝑙𝑎𝑛𝑔𝑎𝑛 ) = 6 𝑚𝑚