Вы находитесь на странице: 1из 42

Project Management Body Of Knowledge

(PMBOK®) Guide – 5th Edition

February 21, 2013

1
PMBOK 4th Edition PMBOK 5th Edition

Released in 2008 Released in 2013

5 Process Groups 5 Process Groups

9 Knowledge Areas 10 Knowledge Areas

42 Processes 47 Processes

2
PMBOK 5th Edition
PMBOK 4th Edition PMBOK 5th Edition

• Integration Management • Integration Management


• Scope Management • Scope Management
• Time Management • Time Management
• Cost Management • Cost Management
• Quality Management • Quality Management
• Human Resources • Human Resources
Management Management
• Communications Management • Communications Management
• Risk Management • Risk Management
• Procurement Management • Procurement Management
• Stakeholder Management

3
PMBOK 5th Edition
PMBOK4 PMBOK5
Chapter 5 Project Scope Management Chapter 5 Project Scope Management
5.1 Plan Scope Management
5.1 Colect Requirements 5.2 Collect Requirements
5.2 Define Scope 5.3 Define Scope
5.3 Create WBS 5.4 Create WBS
5.4 Verify Scope 5.5 Validate Scope
5.5 Control Scope 5.6 Control Scope

4
PMBOK 5th Edition
5.1 Plan Scope Management

The process of creating a scope management plan that


documents how the project scope will be defined,
validated, and controlled.

The key benefit of this process is that it provides


guidance and direction on how scope will be managed
throughout the project.

5
PMBOK 5th Edition
5.1 Plan Scope Management

6
PMBOK 5th Edition
5.1 Plan Scope Management

7
PMBOK 5th Edition
PMBOK4 PMBOK5
Chapter 6 Project Time Management Chapter 6 Project Time Management
6.1 Plan Schedule Management
6.1 Define Activities 6.2 Define Activities
6.2 Sequence Activities 6.3 Sequence Activities
6.3 Estimate Activity Resources 6.4 Estimate Activity Resources
6.4 Estimate Activity Durations 6.5 Estimate Activity Durations
6.5 Develop Schedule 6.6 Develop Schedule
6.6 Control Schedule 6.7 Control Schedule

8
PMBOK 5th Edition
6.1 Plan Schedule Management

is the process of establishing the policies, procedures,


and documentation for planning, developing, managing,
executing and controlling the project schedule.

The key benefit of this process is that it provides


guidance and direction on how the project schedule will
be managed throughout the project.

9
PMBOK 5th Edition
6.1 Plan Schedule Management

10
PMBOK 5th Edition
6.1 Plan Schedule Management

11
PMBOK 5th Edition
PMBOK4 PMBOK5
Chapter 7 Project Cost Management Chapter 7 Project Cost Management
7.1 Plan Cost Management
7.1 Estimate Costs 7.2 Estimate Costs
7.2 Define Budget 7.3 Determine Budget
7.3 Control Costs 7.4 Control Costs

12
PMBOK 5th Edition
7.1 Plan Cost Management

Is the process that establishes the policies, procedures,


and documentation for planning, managing, expending,
and controlling project costs.

The key benefit of this process is that it provides


guidance and direction on how the project costs will be
managed throughout the project.

13
PMBOK 5th Edition
7.1 Plan Cost Management

14
PMBOK 5th Edition
7.1 Plan Cost Management

15
PMBOK 5th Edition
PMBOK4 PMBOK5
Chapter 10 Project Communications Chapter 10 Project Communications
Management Management
10.1 Identify Stakeholders Moved to 13.1
10.2 Plan Communications 10.1 Plan Communications Management
10.3 Distribute Information
10.2 Manage Communications
New process 10.3 Control Communications
10.4 Manage Stakeholder Expectations Moved to 13.3
10.5 Report Performance Became Tool and Technique of 10.2

16
PMBOK 5th Edition
10.1 Plan Communications Management

The process of developing an appropriate approach and


plan for project communications based on stakeholder’s
information needs and requirements, and available
organizational assets.

The key benefit of this process is that it identifies and


documents the approach to communicate most
effectively and efficiently with stakeholders.

17
PMBOK 5th Edition
10.1 Plan Communications Management

18
PMBOK 5th Edition
10.1 Plan Communications Management

19
PMBOK 5th Edition
10.2 Manage Communications

Is the process of creating, collecting, distributing,


storing, retrieving, and the ultimate disposition of project
information in accordance to the communications
management plan.

The key benefit of this process is that it enables an


efficient and effective communications flow between
project stakeholders.

20
PMBOK 5th Edition
10.2 Manage Communications

Inputs
.1 was Stakeholder register
.2 was Stakeholder management Strategy

21
PMBOK 5th Edition
10.2 Manage Communications

Tools and Techniques


.1 was Communication requirements analysis
.4 is new
.5 was process 10.5 Report Performance

22
PMBOK 5th Edition
10.2 Manage Communications

Outputs:
.3 and .4 are new

23
PMBOK 5th Edition
10.2 Manage Communications

24
PMBOK 5th Edition
10.3 Control Communications

Control Communications is the process of monitoring


and controlling communications throughout the entire
project life cycle to ensure the information needs of the
project stakeholders are met.

The key benefit of this process is that it ensures an


optimal information flow among all communication
participants at any moment in time.

25
PMBOK 5th Edition
10.3 Control Communications

26
PMBOK 5th Edition
10.3 Control Communications

27
PMBOK 5th Edition
Chapter 13 Project Stakeholder Management
13.1 Identify Stakeholders
13.2 Plan Stakeholder Management
13.3 Management Stakeholder Engagement
13.4 Control Stakeholder Engagement

28
PMBOK 5th Edition
13.1 Identify Stakeholders

Identify Stakeholders is the process of identifying the people


groups, or organizations that could impact or be impacted by a
decision, activity, or outcome of the project, analyzing and
documenting relevant information regarding their interests,
involvement, interdependencies, influence, and potential impact on
project success.

The key benefit of this process is that it allows the project manager
to identify the appropriate focus for each stakeholder or group of
stakeholders.

29
PMBOK 5th Edition
13.1 Identify Stakeholders

OUT: Stakeholder Management Strategy

30
PMBOK 5th Edition
13.1 Identify Stakeholders

31
PMBOK 5th Edition
13.2 Plan Stakeholder Management

Is the process of developing appropriate management


strategies to effectively engage stakeholders throughout
the project life cycle, based on the analysis of their
needs, interests, and potential impact on project
success.

The key benefit of the process that it provides a clear,


actionable plan to interact with project stakeholders to
support the project’s interests.

32
PMBOK 5th Edition
13.2 Plan Stakeholder Management

33
PMBOK 5th Edition
13.2 Plan Stakeholder Management

34
PMBOK 5th Edition
13.3 Manage Stakeholder Engagement

Manage Stakeholder Engagement is the process of


communicating and working with stakeholders to meet
their needs/expectations, address issues as they occur,
and foster appropriate stakeholder engagement in
project activities throughout the project life cycle.

The key benefit of this process is that it allows the


project manager to increase support and minimize
resistance.

35
PMBOK 5th Edition
13.3 Manage Stakeholder Engagement

36
PMBOK 5th Edition
13.3 Manage Stakeholder Engagement

37
PMBOK 5th Edition
13.4 Control Stakeholder Engagement

Control Stakeholder Engagement is the process of


monitoring overall project stakeholder relationships and
adjusting strategies and plans for engaging
stakeholders.

The key benefit of the process is that it will maintain or


increase the efficiency and effectiveness of stakeholder
engagement activities as the project evolves and its
environment and its environment changes.

.
38
PMBOK 5th Edition
13.4 Control Stakeholder Engagement

39
PMBOK 5th Edition
13.4 Control Stakeholder Engagement

40
PMBOK 5th Edition
Changes to the Exams
Those taking the Certified Associate in Project
Management (CAPM®) Exam
• Before July 1, 2013 – Use the PMBOK 4th Edition
• After July 1, 2013 – Use the PMBOK 5th Edition

Thos taking the Project Management Professional


(PMP®) Exam
• Before July 31, 2013 – Use the PMBOK 4th Edition
• After July 31, 2013 – Use the PMBOK 5th Edition

41
PMBOK 5th Edition
Questions!!

42
PMBOK 5th Edition

Вам также может понравиться