Вы находитесь на странице: 1из 58

PROJECT TITLE: Pandi Village 1(NHA row House)

LOCATION: Pandi, Bulacan

OWNER: NHA Project


ENGINEER:
CONTRACTOR: Atlantica Realty Development Corp
EXCAVATION

Footing

Length of footing = 0.60 m


Width of footing = 0.60 m
Height of Excavation = 0.80 m
Total of Footings = 9 pcs

Total Volume of Excation = 2.592 cu.m

Concrete Footing of CHB Walls

Height of Excavation 0.4 m Length of Column = 0.15


Width of Column = 0.2 m
Length of footing row 1 = 6 m No. of columns along row 1
Length of footing row 3 = 6 m
Length of footing row A = 6 m No. of columns along row A
Length of footing row C = 6 m
Total Length of all CHB Wall footings

Total Volume of Excavation = 3.92 cu.m

FOUNDATION FILL

Footing

Length of footing = 0.60 m


Width of footing = 0.60 m
Height of Foundation Fill = m
Total of Footings = 9 pcs

Total Volume of Excation = 0 cu.m

Concrete Footing of CHB Walls

Height of Foundation Fill 0.2 m


Width of Column = 0.2 m
Length of footing row 1 = 4 m No. of columns along row 1
Length of footing row 3 = 4 m
Length of footing row A = 6.7 m No. of columns along row A
Length of footing row C = 6.7 m
Total Length of all CHB Wall footings

Total Volume of Excavation = 1.79 cu.m


EMBANKMENT

Height of Embankment = m
Length to be Embankment = m
Width to be Embankment = m
Volume of Embankment = 0 cu.m

Total Vol. to be Embankment = 0 cu.m

A B
1

= 3 5.55
4 5.4 2
= 3 5.4
3 5.4
= 21.75

3
= 1 3.85
1 3.85
= 3 6.1
3 6.1
= 19.9
C
Ground Floor Slab Second (2nd) Floor Slab

Length of concrete slab = 6m 5.7


Width of concrete slab = 6m 5.7
Thickness of slab = 0.125 m

Volume of Concrete = 4.06125 cu.m.


10% wastage = 0.406125 cu.m.
Total Concrete Volume = 4.467375 cu.m.

Class C concrete mix Class A concrete mi


4.467375 5.49 = 24.52589 Bags of Cement 0
4.467375 0.44 = 1.965645 cu.m Sand 0
4.467375 0.89 = 3.975964 cu.m Gravel 0

Column Footing Column

Length of footing = 0.8 m


Width of footing = 0.8 m
Thickness of footing = 0.2 m
Total of Footings = 2 pcs

Volume of Concrete = 0.256 cu.m.


10% wastage = 0.0256 cu.m.
Total Concrete Volume = 0.2816 cu.m.

Class B concrete mix Class B concrete mi


0.2816 7.5 = 2.112 Bags of Cement 1.28625
0.2816 0.5 = 0.1408 cu.m Sand 1.28625
0.2816 1= 0.2816 cu.m Gravel 1.28625

Column 2 ( if there's a diff. size of column) Concrete Footing of CHB

Total Length of Column = m


Width of column = m
Thickness of column = m
Total of No. Column = pcs

Volume of Concrete = 0 cu.m.


5% wastage = 0 cu.m.
Total Concrete Volume = 0 cu.m.
Class B concrete mix Class A concrete mi
0 6.49 = 0 Bags of Cement 1.8711
0 0.44 = 0 cu.m Sand 1.8711
0 0.87 = 0 cu.m Gravel 1.8711

Beams

Length of Beam = 33.8 m


Width of Beam = 0.2 m
Thickness of Beam = 0.15 m
Total of No. of Same Beams = 1 pcs

Volume of Concrete = 1.014 cu.m.


5% wastage = 0.0507 cu.m.
Total Concrete Volume = 1.0647 cu.m.

Class A concrete mix


1.0647 9= 9.5823 Bags of Cement
1.0647 0.5 = 0.53235 cu.m Sand
1.0647 1= 1.0647 cu.m Gravel
Second (2nd) Floor Slab

Length of concrete slab = m -0.3


Width of concrete slab = m -0.3
Thickness of slab = m

Volume of Concrete = 0 cu.m.


10% wastage = 0 cu.m.
Total Concrete Volume = 0 cu.m.

Class A concrete mix


7.85 = 0 Bags of Cement
0.42 = 0 cu.m Sand
0.84 = 0 cu.m Gravel

Column

Total Length of Column = 1.4 m


Width of column = 0.25 m
Thickness of column = 0.25 m
Total No. of Column = 14 pcs

Volume of Concrete = 1.225 cu.m.


5% wastage = 0.06125 cu.m.
Total Concrete Volume = 1.28625 cu.m.

Class B concrete mix


9 = 11.57625 Bags of Cement
0.5 = 0.643125 cu.m Sand
1 = 1.28625 cu.m Gravel

Concrete Footing of CHB Walls


Add
Length of footing row 1 = 6 m No. of columns along row 1 = 1
Length of footing row 3 = 6 m 1
Length of footing row A = 6 m No. of columns along row A = 3
Length of footing row C = 6 m 3
Total Length of all CHB Wall footings =
Volume of Concrete = 1.701 cu.m.
10% wastage = 0.1701 cu.m. Thickness = 0.2 m
Total Concrete Volume = 1.8711 cu.m. width = 0.4 m
Class A concrete mix Thickness = 0.2 m
9= 16.8399 Bags of Cement width = 0.3 m
0.5 = 0.93555 cu.m Sand
1= 1.8711 cu.m Gravel
Column

Total Length of Column = 5.8 m


Width of column = 0.2 m
Thickness of column = 0.15 m
Total No. of Column = 2 pcs

Volume of Concrete = 0.348 cu.m.


5% wastage = 0.0174 cu.m.
Total Concrete Volume = 0.3654 cu.m.

Class B concrete mix


0.3654 7.5 = 2.7405 Bags of Cement
0.3654 0.5 = 0.1827 cu.m Sand
0.3654 1= 0.3654 cu.m Gravel

2.85
5.75
5.75
5.25
5.25
10.5
14.35
CHB 5" (150mm X 400) Wall PLASTERING for CHB WALL
Length Height
Area of Wall = 6.1 4.2 29.52
0.3 6.5 29.52
No. of CHB needed = 369 pieces 1/2"mm thick Class A mortar mi
Mortar Cell Filler 29.52
29.52 1.018 = 30.05136 Bags of Cement 29.52
29.52 0.0844 = 2.491488 cu.m Sand

CHB 4" (100mm X 400) Wall PLASTERING for CHB WALL


Length Height
Area of Wall = 8.4 3.85 30.4975
2.95 2.85 40.7475
No. of CHB needed = 381.2188 pieces 1/2"mm thick Class A mortar mi
Mortar Cell Filler 30.4975
30.4975 0.522 = 15.9197 Bags of Cement 30.4975
30.4975 0.0438 = 1.335791 cu.m Sand

CEMENT MORTAR for Floor Tiles


Length Width CHB 5" (150mm X 400) Wall
Area of Floor = 0 Area of Doors and Windows

20mm thick Class A mortar mix


0 0.3480 = 0 Bags of Cement
0 0.0186 = 0 cu.m Sand

CHB 4" (100mm X 400) Wall


Area of Doors and Windows
ERING for CHB WALL
Length Height Total
Plaster Area = 6.1 4.2 29.52 Area of Drs &Win = 0 sq.m
0.3 6.5 29.52
m thick Class A mortar mix
0.2088 = 6.163776 Bags of Cement Mag Times 2 ka dahil baliktaran
0.0112 = 0.330624 cu.m Sand Mag Times 2 ka dahil baliktaran

ERING for CHB WALL Total


Length Height Area of Drs &Win = 10.25 sq.m
Plaster Area = 8.4 3.85 30.4975
2.95 2.85 40.7475
m thick Class A mortar mix
0.2088 = 6.367878 Bags of Cement Mag Times 2 ka dahil baliktaran
0.0112 = 0.341572 cu.m Sand Mag Times 2 ka dahil baliktaran

5" (150mm X 400) Wall


f Doors and Windows Length Height Pieces = Answer
D1 = 0 sq.m D1 =
D2 = 0 sq.m W5 =
W1 = 0 sq.m
W2 = 0 sq.m
W3 = 0 sq.m
W4 = 0 sq.m
0 sq.m

4" (100mm X 400) Wall


f Doors and Windows Length Height Pieces = Answer
D1 = 0.9 2.15 1 = 1.935 sq.m
D2 = 0.7 2.15 1 = 1.505 sq.m
D3 = 0.6 2.15 1 = 1.29 sq.m
W1 = 1.2 1.25 1 = 1.5 sq.m
W2 = 1.2 0.6 2 = 1.44 sq.m
W3 = 1.2 0.95 1 = 1.14 sq.m
W4 = 0.5 0.6 1 = 0.3 sq.m
W5 = 1 0.6 1 = 1.14 sq.m
10.25 sq.m
HEIGHT WIDTH
ADD:FOR TRIANGLE 0.6 6.5
sq.m

sq.m

0
0
CHB 6" (150mm X 400) Wall
Perimeter Height
Area of Wall = 16.55 3.2 52.96

No. of CHB needed = 662 pieces


Mortar Cell Filler
52.96 1.018 = 53.91328 Bags of Cement
52.96 0.0844 = 4.469824 cu.m Sand

CHB 4" (100mm X 400) Wall


Perimeter Height
Area of Wall = 2.4 2.6 4.77

No. of CHB needed = 62.01 pieces


Mortar Cell Filler
4.77 0.522 = 2.48994 Bags of Cement
4.77 0.0435 = 0.207495 cu.m Sand

CEMENT MORTAR for Floor Tiles (0.20m x 0.20m)


Length Width
Area of Floor = 6 6 29.89

Number of Tiles = 747.25 pcs


20mm thick Class B mortar mix
29.89 0.2250 = 6.72525 Bags of Cement
29.89 0.0188 = 0.561932 cu.m Sand

CEMENT MORTAR for Floor Tiles (0.30m x 0.30m)


Length Width
Area of Floor = 0

Number of Tiles = 0 pcs


20mm thick Class B mortar mix
0 0.2250 = 0 Bags of Cement
0 0.0188 = 0 cu.m Sand

CEMENT MORTAR for Floor Tiles (0.40m x 0.40m)


Length Width
Area of Floor = 0
Number of Tiles = 0 pcs
20mm thick Class B mortar mix
0 0.2250 = 0 Bags of Cement
0 0.0188 = 0 cu.m Sand

WALL TILES
Length of Wall = 0
Width of Wall =
Length of Door = 0
Height of Wall =
Total Lateral Area = 0

0.20 x 0.20 Number of Tiles = 0.00 pcs


0.30 x 0.30 Number of Tiles = 0.00 pcs
20mm thick Class B mortar mix
0 0.2250 = 0 Bags of Cement
0 0.0188 = 0 cu.m Sand
PLASTERING for CHB WALL (2 faces)
Length Height
Plaster Area = 16.55 3.2 105.92

16mm thick Class B mortar mix


105.92 0.1920 = 20.33664 Bags of Cement
105.92 0.016 = 1.69472 cu.m Sand

PLASTERING for CHB WALL (2 faces)


Length Height
Plaster Area = 2.4 2.6 12.48

16mm thick Class B mortar mix


12.48 0.1920 = 2.39616 Bags of Cement
12.48 0.016 = 0.19968 cu.m Sand

CHB 6" (150mm X 400) Wall


Area of Doors and Windows Length Height Pieces = Answer
D1 = 0
D2 = 0
D3 = 0
W1 = 0
W2 = 0
W3 = 0
W4 = 0
0

CHB 4" (100mm X 400) Wall


Area of Doors and Windows Length Height Pieces = Answer
D1 = = 0
D2 = = 0
W1 = = 0
= = 0
= = 0
= = 0
0
Total
Area of Drs &Win = 0 sq.m

Total
Area of Drs &Win = 0 sq.m

sq.m
sq.m
sq.m
sq.m
sq.m
sq.m
sq.m
sq.m

sq.m
sq.m
sq.m
sq.m
sq.m
sq.m
sq.m
PARTICULARS
One Span Beam Continous Beam
No. of beams to be constructed = pcs. pcs.
Overall length of each beams = m. m.
No. and size of longitudinal bars = dia. mm dia. mm
Length of bars to be ordered = m. 6 m.

Formula:
Straight length of each Overall Length of each beams +
longitudinal bar = Diameter of Longitudinal bars

One Span Beam


Straight length of each No. of Full Length bars reqd.= #DIV/0!
= 0.45
longitudinal bar say =
at __ dia. By __ m.
Continous Beam
Straight length of each No. of Full Length bars reqd.= 0.00
= 0.35
longitudinal bar say =
at __ dia. By __ m.

*SABI SA LIBRO, ANG STIRRUPS DAW AY BILANGIN ANG ACTUAL SA ACTUAL PLAN

Part 2
PARTICULARS
One Span Beam Continous Beam
No. of beams to be constructed = pcs. pcs.
Overall length of each beams = m. m.
No. and size of longitudinal bars = dia. mm 16 dia. mm
Length of bars to be ordered = m. 6 m.

Formula:
Straight length of each Overall Length of each beams +
longitudinal bar = Diameter of Longitudinal bars

One Span Beam


Straight length of each No. of Full Length bars reqd.= #DIV/0!
= 0.45
longitudinal bar say =
at __ dia. By __ m.
Continous Beam
Straight length of each No. of Full Length bars reqd.= 0.00
= 0.35
longitudinal bar say =
at __ dia. By __ m.

Part 3
PARTICULARS
One Span Beam Continous Beam
No. of beams to be constructed = pcs. pcs.
Overall length of each beams = m. m.
No. and size of longitudinal bars = dia. mm dia. mm
Length of bars to be ordered = m. m.

Formula:
Straight length of each Overall Length of each beams +
=
longitudinal bar Diameter of Longitudinal bars

One Span Beam


Straight length of each No. of Full Length bars reqd.= #DIV/0!
= 0.45
longitudinal bar say =
at __ dia. By __ m.
Continous Beam
Straight length of each No. of Full Length bars reqd.= #DIV/0!
= 0.35
longitudinal bar say =
at __ dia. By __ m.

COLUMS
Column Diameter of
No. of colums to be constructed = pcs. Longitudinal bars
Overall length of each column = m. 12mm (1/2") 0.30
No. and size of longitudinal bars = 16 dia. mm 16mm(5/8") 0.35
Length of bars to be ordered = m. 20mm(3/4") 0.45
25mm (1") 0.55
Formula:
Straight length of each Overall Length of each beams +
=
longitudinal bar Diameter of Longitudinal bars
Columns
Straight length of each No. of Full Length bars reqd.= #DIV/0!
= 0.35
longitudinal bar say =
at __ dia. By __ m.

FOOTING
GO TO PAGE D.14

Total No. of Footings = pcs

IF THE FOOTING IS 1m X 1m
No. of F/L bars reqd. = 0.00 pcs at 16mm dia. By 6m.

REINFORCING BARS FOR CONTINOUS CONCRETE FOOTINGS

Number and size of long. Bars = 3 pcs of 12 mm dia.


Size and spacing & transverse = 10mm dia @ 0.30m O.C.
Width of continous footing = 0.40 m
Size of Deformed bars = 6 dia. mm
Total Length of perimeter walls = 2 0m
= 2 0m
0m
Transverse bars required = 0.00 pcs 10mm dia. X 6m
Longitudinal bars required = 0.00 pcs 12mm dia. X 6m

COLUMN STIRRUPS for (0.30m x 0.30m)

O.C = 0.20 mm
Total Height of Column = m
No. of Same Columns = pcs
Length of Stirrups = 1.20 m

10mm dia. Stirrups = 0 pcs

SLAB
Diameter of Short Bars over For Short Bars Only
Longitudinal bars the End Supports
12mm (1/2") 0.30 0.15 Column Width =
16mm(5/8") 0.35 0.20 One Span Beam & Girders =
20mm(3/4") 0.45 0.25
25mm (1") 0.55 0.30 Length of =
Continous Span Beams =
Formula: and Girders
Short Bar Length Column Width +
= L/4 + Dia. Of Short Bar

Short Bars in One Span Top of End Support =


=
pcs Beams and Girders Bottom Bar =
Total of Short Bars per beam =

Short Bars in Cont. Top of End Support =


=
pcs Beams and Girders Bottom Bar =
Continous Top Bar =
Continous Bottom Bar =
Top of End Support =
Total of Short Bars per beam =
=

Diameter of Short Bars over For Short Bars Only


Longitudinal bars the End Supports
12mm (1/2") 0.30 0.15 Column Width =
16mm(5/8") 0.35 0.20 One Span Beam & Girders =
20mm(3/4") 0.45 0.25
25mm (1") 0.55 0.30 Length of per =
Continous Span Beams =
Formula: and Girders =
Short Bar Length Column Width +
= L/4 + Dia. Of Short Bar

Short Bars in One Span Top of End Support =


=
pcs Beams and Girders Bottom Bar =
Total of Short Bars per beam =

Short Bars in Cont. Top of End Support =


=
=
pcs Beams and Girders Bottom Bar =
Continous Top Bar =
Continous Bottom Bar =
Continous Top Bar 2 =
Continous Bottom Bar 2 =
Top of End Support =
Total of Short Bars per beam =
=

Diameter of Short Bars over For Short Bars Only


Longitudinal bars the End Supports
12mm (1/2") 0.30 0.15 Column Width =
16mm(5/8") 0.35 0.20 One Span Beam & Girders =
20mm(3/4") 0.45 0.25
25mm (1") 0.55 0.30 Continous Span Beams =
and Girders =
=
Formula: =
Short Bar Length Column Width +
= L/4 + Dia. Of Short Bar

pcs Short Bars in One Span Top of End Support =


=
Beams and Girders Bottom Bar =
Total of Short Bars per beam =

pcs Short Bars in Cont. Top of End Support =


=
Beams and Girders Bottom Bar =
Continous Top Bar =
Continous Bottom Bar =
Continous Top Bar 2 =
Continous Bottom Bar 2 =
Continous Top Bar 3 =
Continous Bottom Bar 3 =
Top of End Support =
Total of Short Bars per beam =
=

REINFORCING STEEL BARS FOR CHB

Total Height of Wall = 4.20 m


Total Length of Wall = m
pcs Net Height of Wall = 3.00 m
For Single Wall Net Length of Wall = m

For Cont. Wall Net Length of Wall A = m


Net Length of Wall B = m
Net Length of Wall D = m
Net Length of Wall C = m

Length of bar to be ordered = 6.00 m


Length of bar to be ordered 2 = 7.50 m

For Horizontal Bars


= 3.75 pcs
= 0m
= 0.00 pcs say :

For Vertical Bars


Wall A = 0 pcs say :
Wall B = 0 pcs say :
Wall D 0 pcs say :
Wall C = 0 pcs say :
Total No. of Vertical Bars = 0 pcs say :
= 63 m
= 12.6 pcs say :

Part 2
REINFORCING STEEL BARS FOR CHB

Total Height of Wall = m


Total Length of Wall = m

Net Height of Wall = 3.00 m


For Single Wall Net Length of Wall = m

For Cont. Wall Net Length of Wall A = m


Net Length of Wall B = m
Net Length of Wall D = m
Net Length of Wall C = m
Length of bar to be ordered = 6.00 m
Length of bar to be ordered 2 = 7.50 m

For Horizontal Bars


= 3.75 pcs
= 0m
= 0.00 pcs say :

For Vertical Bars


Wall A = 0 pcs say :
Wall B = 0 pcs say :
Wall D 0 pcs say :
Wall C = 0 pcs say :
Total No. of Vertical Bars = 0 pcs say :
= 0 m
= 0 pcs say :
0.3 m
m

m
m

0.50
0.00
0.50 m

0.50
0.00
0.90
0.00
0.50
0.00 m
0.00 pcs

0.3 m
m

m
m
m

0.50
0.00
0.50 m

0.50
0.00
0.30
0.00
0.30
0.00
0.50
0.00 m
0.00 pcs

0.35 m
m

m
m
m
m

0.55
0.00
0.55 m

0.55
0.00
0.35
0.00
0.35
0.00
0.35
0.00
0.55
0.00 m
0.00 pcs
pcs

X2 yung final
answer dahil
magkabilaan

15 pcs

pcs
pcs

X2 yung final
answer dahil
magkabilaan

8 pcs

pcs
Reinforcing Bars for CHB Wall
Length Height
Area of Wall = 16.55 3.2 61.16

Vertical spacing 0.8m, Horizontal spacing at every 3 layers


10mm dia of steel bars
Vertical = 130.2708 meters long
Horizontal = 131.494 meter long
Total = 261.76 meter long
Number of Bars = 34.90197 pcs
say = 35 pcs 161.7 kg
Tie Wires = 1.47 kg # 16 - G.I. wire

Reinforcing Bars for CHB Wall


Length Height
Area of Wall = 2.4 2.6 4.77

Vertical spacing 0.8m, Horizontal spacing at every 3 layers


10mm dia of steel bars
Vertical = 10.1601 meters long
Horizontal = 10.2555 meter long
Total = 20.42 meter long
Number of Bars = 3.4026 pcs
say = 4 pcs 14.784 kg
Tie Wires = 0.11 kg # 16 - G.I. wire

COLUMN FOOTING

Length = 0.6 m
Width = 0.6 m
Total Number of Footings = 9.00 pcs
L of cut bar = 0.45 m
Total Number of cut bars = 54 pcs
16mm Steel bars at 6m long = 13.5 pcs
say = 14 pcs
= 132.58 kg
Tie Wires = 5.09434 kg

ONE WAY SLAB


Length Width
Floor Area = 6 6 36
Use Table 2 - 15cm spacing distance
12mm Steel bars at 6m long = 71.28 pcs
say = 22 pcs
= 117.26 kg
Tie Wires = 8.21 kg

TWO WAY SLAB


Length Width
Floor Area = 0
Use Table 3 - 10cm spacing distance
12mm Steel bars at 6m long = 0.00 pcs
say = pcs
= 0 kg
Tie Wires = 0.00 kg

LATERAL TIES of COLUMN for( 0.30m x 0.30m column)

Height of Column = 3.2 m


Spacing of Lat. ties = 0.175 m
# Same of Columns = 4 pcs

# of Lateral ties in one column = 19.28571


Total Ties = 77.14286
10mm # of Steel bars to be ordered = 14.15465 pcs
say = 11 pcs
= 40.7 kg
Tie Wires = 4.66 kg
G/F SLAB, CHB REINFORCEMENT
Spacing Vertical Spacing of Horizontal
in cm Reinforcement CHB Layer Reinforcement
40 2.93 2 3.3
50 2.53 2.5 2.725
60 2.13 3 2.15
80 1.60 4 1.72

Table 2 ONE WAY SLAB


Bar Spacing Number of steel Bars per Square Meter
in cm 6m 7.5m 9m
10.00 3.764 2.937 2.421
12.50 3.062 2.381 1.934
15.00 2.584 2.004 1.636
17.50 2.232 1.726 1.407
20.00 1.980 1.528 1.258
22.50 1.786 1.369 1.109
25.00 1.627 1.250 1.014

Table 3 TWO WAY SLAB


Bar Spacing Number of steel Bars per Square Meter
in cm 6m 7.5m 9m
10.00 4.369 3.337 2.772
12.50 3.603 2.662 2.245
15.00 3.221 2.296 1.921
17.50 2.647 2.025 1.65
20.00 2.300 1.775 1.461
22.50 2.168 1.601 1.312
25.00 1.977 1.466 1.217

RSB Ground Floor Slab


Width Length
Area of slab = 3.85 2.95 20.3325
0.9 1.65
0.65 3.85
Vertical = 59.574225 meters long
Horizontal = 67.09725 meter long
Total = 126.67 meter long
Number of Bars = 16.88953 pcs 10mm dia of steel bars
say = 17 pcs 62.832 kg
Tie Wires = 0.49 kg # 16 - G.I. wire
ONE WAY SLAB
Length Width
Floor Area = 0
Use Table 2 - 15cm spacing distance
12mm Steel bars at 6m long = 0.00 pcs
= pcs
= 0 kg
Tie Wires = 0.00 kg

TWO WAY SLAB


Length Width
Floor Area = 0
Use Table 3 - 10cm spacing distance
12mm Steel bars at 6m long = 0.00 pcs
= pcs
= 0 kg
Tie Wires = 0.00 kg

STIRRUPS FOR BEAM and GIRDERS

Length of Beams or Girders = m


Spacing of stirrups = 0.15 m
# Same of Beams or Girders = pcs

# of stirrups in one beam/gir = 0


Total Ties = 0
10mm # of Steel bars to be order = 0 pcs
= pcs
= 0 kg
Tie Wires = 0.00 kg
0

Width Length
2.85 1.75
Column Beam and Girde

Total Length of Column = m


Width of column = 0.3 m
Thickness of column = 0.3 m
Total No. of Column = pcs

Lateral Perimeter = 1.4 m


Area = 0 sq.m.
Number of 1/2"Plywood = 0.00 pcs
say = pcs
2" x 2" Lumber = 0 bd.ft.
2" x 3" Lumber = 0 bd.ft.

Column Beam and Girde

Total Length of Column = m


Width of column = 0.3 m
Thickness of column = 0.3 m
Total No. of Column = pcs

Lateral Perimeter = 1.4 m


Area = 0 sq.m.
Number of 1/2"Plywood = 0.00 pcs
say = pcs
2" x 2" Lumber = 0 bd.ft.
2" x 3" Lumber = 0 bd.ft.

Scaffolding for Column Floor Slab Form

Total Length of Column = m


Total No. of Column = pcs

Area = 0 sq.m.
2" x 2" Lumber = 0 bd.ft. Horizontal Support
2" x 2" Lumber = 0 bd.ft. Diagonal Braces
2" x 3" Lumber = 0 bd.ft. Vertical Support

Scaffolding for Column Scaffolding for Beams an


Total Length of Column = 3m
Total No. of Column = 10 pcs

Area = 30 sq.m.
2" x 2" Lumber = 630 bd.ft. Horizontal Support
2" x 2" Lumber = 351 bd.ft. Diagonal Braces
2" x 3" Lumber = 210 bd.ft. Vertical Support
Beam and Girders

Total Length of beam = 62 m


Width of beam = 0.05 m
Thickness of beam = 0.15 m
Total No. of Beam = 1 pcs

Lateral Perimeter = 0.35 m


Area = 21.7 sq.m.
Number of 1/2"Plywood = 7.53 pcs
say = 8 pcs
2" x 2" Lumber = 149.28 bd.ft.
2" x 3" Lumber = 224 bd.ft.

Beam and Girders

Total Length of beam = m


Width of beam = 0.4 m
Thickness of beam = 0.2 m
Total No. of Beam = pcs

Lateral Perimeter = 1.1 m


Area = 0 sq.m.
Number of 1/2"Plywood = 0.00 pcs
say = pcs
2" x 2" Lumber = 0 bd.ft.
2" x 3" Lumber = 0 bd.ft.

Floor Slab Forms

Total Length = m
Total Width = m

Area = 0 sq.m.
Number of 1/2"Plywood = 0.00 pcs
say = pcs
2" x 3" Lumber = 0 bd.ft.

Scaffolding for Beams and Girders


Total Length of Beams = 8.5 m
Total No. of Beams = 6 pcs

Area = 51 sq.m.
2" x 2" Lumber = 239.7 bd.ft. Horizontal Support
2" x 3" Lumber = 306 bd.ft. Vertical Support
CEILING AND PARTITION BOARDS

Size of Ceiling/Partition Board = 4' x 8'

CEILING BOARDS WALL PANELS


Length of Ceiling = m Area of all partitions
Width of Ceiling = m Height of Wall
Area of the Ceiling = 0 sq.m Width of Wall
Area of the Ceiling
No. of Ceiling Board required = 0 pcs
say = 0 pcs
Total area of wall openings
Length
Width
Area of the Ceiling

No. Part. Brd. Reqd.

WALL STUDS

Length of Wall A = m
Length of Wall B = m
Length of Wall C = m
Spacing of Vertical Studs = 0.60 m Height of Wall

A = 1 say: pcs Horizontal Studs


B = 1 say: pcs Total Width of Wall
C = 1 say: pcs
TOTAL = 0 pcs
0 say: feet
(2"x2"12")

CEILING JOISTS
Length of Ceiling = 0m
Width of Ceiling = 0m

No. of Traverse Ceiling Joist = 1 say: pcs Longitudinal Ceiling Joist


0 say: feet Total Length of all
(2"x2"20") Longitudinal joist
NAILS

WALL STUDS = 0
CEILING JOIST = 0
QTY of 10d CW Nail = 0 say: kilos

AREA METHOD CEILING and PARTITION

CEILING JOISTS
Length of Ceiling = 0m
Width of Ceiling = 0m
Area = 0 sq.m.

2" x 2" at 0.40m x 0.40m = - bd.ft.

WALL PARTITION
Length of Wall = m
Width of Wall = m
Area = 0 sq.m.

2" x 3" at 0.40m x 0.60m = - bd.ft.


A B C
Height of Wall = m
Width of Wall = m
Area of the Ceiling = 0 0 0 sq.m
Total = 0 sq.m

a of wall openings Doors W-1 W-2


= m
= m
Area of the Ceiling = 0 0 0 sq.m
Total = 0 sq.m

Area = 0 sq.m
No. Part. Brd. Reqd. = 0 pcs
say = pcs

Height of Wall = 0m

Horizontal Studs = 1.00 say: pcs


Total Width of Wall = 0.00 feet m
= 0.00 feet
= 0 say: pcs

nal Ceiling Joist = 1 say: pcs


Total Length of all
Longitudinal joist = m
= 0m
= 0 feet
= 0 say: pcs
(2"x2"20")
Gutter Painting (2 coats)

Total Length of Roofing = m Area of masonry surface


Number of Pieces of Gutter = 0 pcs Interior surface =
Both Sides = 0 pcs Exterior surface =
Total of masonry surface =
Corrugated G.I. Sheets (32" x 8')
Number of Pieces of Roofing = 0 pcs Area of wood surface
Both Sides = 0 pcs Interior surface =
Exterior surface =
Ridge Roll Total of wood surface =
Number of Pcs of Ridge Roll = 0 pcs
Masonry
Plain G.I. Flashing for Firewalls Primer required =
Length of affected area = m Topcoat Paint =
No. of Plain G.I. sheets reqd. = 0 pcs
Wood
Primer required =
Topcoat Paint =
sq.m
sq.m
0 sq.m

sq.m
sq.m
0 sq.m

0 liters
0 liters

0 liters
0 liters
Name of Project: CONSTRUCTION / COMPLETION OF SCHOOL
BUILDING @ SAN MARCOS E/S TWO ( 2 ) STOREY
Back - up Computations 1 0f 2

NOTE : Construction/Completion of School Building @ San Marcos E/S, Two (2) Storey,
complete as per plan and specification minus the following :

1 Toilet with Septic Vault


2 Ceiling ( 2nd Floor ) inside/outside
3 CHB Walls and Partition in 2nd Floor ( portion of room )
4 Electrical in 2nd Floor
5 Doors and Windows in 2nd Floor
6 Railing ( G.I. Pipe ) in Stair
7 Painting of the whole building

Item No. Description Qty.

103-3b Foundation Fill


303.40 m² x 0.10m = 1.79

403 Metal Structure


Top & Bot. Chords : Angle Bar 2" x 2" x 6mm ( thk )
22.50m x 2L X 6sets ÷ 6m / pc. X 28.90 kg/pc =
Cleats Angle Bar 2 1/2" x 2 1/2" x 6mm ( thk )
2 pcs. X 37.20 kg/pc =
Web Members Angle Bar 2" x 2" x 5mm ( thk )
24.57 x 2L x 6 ÷ 6m/pc x 22.10 kg/pc =

LC ( C-Purlins ) 2" x 6" x 2.0 mm


16pcs. X 24.90m ÷ 6m/pc x 25.905 kg/pc =
Cross Bracings 12mm Dia. Plain Round Bar
7.50m x 12pcs. ÷ 6m/pc X 5.40 kg/pc =

Sag Rod 10mm dia. Plain Round Bar


8.50m x 10pcs. ÷ 6m/pc x 3.80 kgs/pc =
Steel Plate 1.20m x 2.40m x 9mm
203.47 kg/sheet x 1.25 sheet =

Steel Plate 1.20m x 2.40m x 6mm


135.64 kg/sheet x 2.50 sheets =

0.00 say 0.00

704 Masonry Works ( see attached plan )


69.69 m x 6.00m + 0.01m² ( less of openings ) = 418.15 sq.m 60.02
418.15 sq.m - 95.20 sq.m ( 2nd Floor CHB Walls and Partition )
NOTE :

Less CHB Walls and partition in 2nd floor

802 Excavation
F1: 1.40m X 1.40m X 1.50m =
F2: 2.30m x 2.30m x 1.50m =
F3: 2.10m x 2.10m x 1.50m =
TB 105.50 m x 0.40 x 0.80m =
WF 170.78m x 0.30m x 0.60m =
SPT 4.70m X 2.80m X 2.50m =
0.00 6.51
804 Embankment
22.50m x 9.50m x 0.225m = 0.00
Unit cleats

cu.m.

kg.

sq.m.
cu.m.

cu.m.
Concrete Proportion
Cement in Bag Sand Gravel
mixture class Proportion 40 Kg. 50 Kg. cu.m. cu.m.
AA 1:3/2:3 12 9.5 0.5 1
A 1:02:04 9 7 0.5 1
B 1:5/2:5 7.5 6 0.5 1
C 1:03:06 6 5 0.5 1

QUANTITY OF CEMENT AND SAND FOR CHB MORTAR


PER SQUARE METER
Bags Cement
Mixture
Size of CHB Number Sand
in cm. per sq. m. A B C D cu.m.
10 x 20 x 40 12.5 0.792 0.522 0.394 0.328 0.0438
15 x 20 x 40 12.5 1.526 1.018 0.763 0.633 0.0844
20 x 20 x 40 12.5 2.26 1.5 1.125 0.938 0.125

QUANTITY OF CEMENT AND SAND FOR MORTAR


AND PLASTER IN CUBIC METER

CLASS PROPORTION Cement in Bags Sand


MIXTURE 40 Kg. 50 Kg. cu.m.
A (1 : 2) 18 14.5 1
B (1 : 3) 12 9.5 1
C (1 : 4) 9 7 1
D (1 : 5) 7.5 6 1

QUANTITY OF CEMENT AND SAND FOR PLASTER


PER SQUARE METER AREA

Cement in Bags
Thickness of Plaster
Mixture
Class 8 mm 12 mm 16 mm 20 mm 25 mm
A 0.144 0.216 0.288 0.36 0.45
B 0.096 0.144 0.192 0.24 0.3
C 0.072 0.108 0.144 0.18 0.225
D 0.06 0.09 0.12 0.15 0.188
Sand 0.008 0.012 0.016 0.02 0.025
QUANTITY OF CEMENT, SAND AND GRAVEL FOR SLAB
AND WALLS PER SQUAE METER

Slab Mixture Class Sand


Thickness 40 Kg. Cement 50 Kg. Cement
cm. A B C A B C cu.m.
5.0 0.450 0.375 0.300 0.350 0.300 0.250 0.0250
7.5 0.675 0.563 0.450 0.525 0.450 0.375 0.0375
10.0 0.900 0.750 0.600 0.700 0.600 0.500 0.0500
12.5 1.125 0.938 0.750 0.875 0.750 0.625 0.0630
15.0 1.350 1.125 0.900 1.050 0.900 0.750 0.0750
17.5 1.575 1.313 1.050 1.225 1.050 0.875 0.0880
20.0 1.800 1.500 1.200 1.400 1.200 1.000 0.1000
22.5 2.03 1.668 1.350 1.575 1.350 1.125 0.1125
25.0 2.250 1.875 1.500 1.750 1.500 1.250 0.1250
27.5 2.475 2.063 1.650 1.925 1.650 1.375 0.1380
30.0 2.700 2.250 1.800 2.100 1.800 1.500 0.1500

LENGTH OF REINFORCING BARS FOR CHB IN METERS

Vertical Reinforcement Horizontal Reinforcement


Spacing Length of bars in meter Spacing Length of bars in meter
cm. Per Block Per Sq. M. Layer Per Block Per Sq. M.
40 0.235 2.93 2 0.264 3.3
60 0.171 2.13 3 0.172 2.15
80 0.128 1.6 4 0.138 1.72

THE PHILIPPINES METRIC REINFORCING BARS

NOMINAL DIMENSIONS
BAR SIZE AREA MASS DIA.
DESIGNATION SQ. MM. KG/M MM
#8 50.3 0.394 8
#10 78.5 0.616 10
#12 113.1 0.888 12
#16 201.1 1.578 16
#20 314.2 2.466 20
#25 490.9 3.853 25
#28 615.8 4.834 28
#32 804.3 6.313 32
#36 1017.9 7.99 36
#40 1256.6 9.865 40
#50 1963.5 15.413 50
GraveL

cu.m.
0.050
0.075
0.100
0.125
0.150
0.175
0.200
0.225
0.250
0.275
0.300
Name of Project:

Back - up Computations

Item No. Description T.Qty.

900 Reinforced Concrete


Column Footings
F-1: 6 ( 1.40m x 1.40m x 0.30m ) = 3.528
F-2: 6 ( 2.30m x 2.30m x 0.30m ) = 9.522
F-3: 6 ( 2.10m x 2.10m x 0.30m ) = 7.938
20.988 20.988
Tie Beams
105.53m x 0.30m x 0.50m = 15.829

Wall Footing
17.50m x 0.20m x 0.40m = 1.400

Columns
18 ( 0.35m x 0.35m x 8.34m ) = 18.389
Beams and Girders 14.580
Suspended Slab
22.50m x 9.50m x 0.10m - 2.305 = 19.070
Roof Beams
RG1: 82.50m x 0.20m x 0.40m = 6.60
RG 2: 42.00m x 0.20m x 0.50m = 4.20
10.80 10.800

Stairs 4.860
Slab on Grade
22.50m x 9.50m x 0.10m = 21.375
Ramp on Fill
1.00m x 10.00m x 0.10m = 1.000
Media Agua 1.500
129.791 say 129.80
Portland Cement (40 Kg.): 129.80 cu.m. x 9.05bags/cu.m. = 1,174.69 bags
Washed Sand: 129.80 cu.m x 0.50 x 1.05 = 68.14 cu.m.
Washed Gravel 3/4": 129.80cu.m. x 1.00 x 1.05 = 136.29 cu.m.
RSB
Column Footing 1,189.74
Tie Beams 2,061.45
Wall Footing 59.14
Columns 5,737.22
Beams and Girders 2,930.46
Suspended Slab 1,495.11
Roof Beams 1,448.18
Stairs 276.64
Slab on Grade 820.30
Ramp on Fill 42.09
Media Agua 110.90
Total Wt. of RSB ( Grade 40 ) 16,171.23 kgs.
G.I. Tie Wire 324 kgs.

1001 Storm Drainage and Sewerage System 1.00


1003 Carpentry and Joinery Works ( 2 sets Blackboard )
2 ( 4.80m x 1.20m ) = 11.52
1009 Jalousie Windows 1st Floor
W1 5 sets 2.60m x 1.60m = 20.80
W2 4 sets 1.50m x 1.60m = 9.60
W3 1 set 0.70m x 2.60m = 1.82
32.22 32.22
1010 Wooden Doors
D1 4 sets 0.90m x 2.10m = 7.56
1014 Prepainted Metal Sheet
13.00m x 23.70m = 308.10
1021 Cement Floor Finish
95.345m² x 2 = 190.69

1027 Cement Plaster Finish `


418.155m² x 2 = 836.31

1100 Conduits, Boxes, & Fittings 1.00

1101 Wires and Wiring Devices 1.00

Spcl Construction Safety and Health 1.00

PREPARED BY : CHECKED & SUBMITTED BY : REVIEWED BY :

ENGR. REYMOND IGAYA


ENGINEER
2 0f 2

Unit

cu.m.
l.s.

sq.m.

sq.m.

sq.m.

sq.m.

sq.m.

sq.m.

l.s

l.s

l.s

Вам также может понравиться