NOIDA OFFICE BUILDING PROJECT AT SEC 96, INITIAL WORK PROGRAM


Activity ID Activity Name Original Start Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019
Duration
N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr MJun
NdOffBldg 1020 05-Jan-16 31-Dec-18 31-Dec-18, NdOffBldg

Client Deliverables 210 05-Jan-16 16-Aug-16 16-Aug-16, Client Deliverables

A0800 Date of Comencement of Project 0 05-Jan-16 05-Jan-16 Date of Comencement of Project

A0810 Allotment of land for B/Plant, Camp, Lab, Office, 40 05-Jan-16 16-Feb-16 Allotment of land for B/Plant, Camp, Lab, Office, Working area
Working area
A0820 Allotment of earth disposal land 40 05-Jan-16 16-Feb-16 Allotment of earth disposal land

A0825 Approval from Mining Department 40 05-Jan-16 16-Feb-16 Approval from Mining Department

A0830 GFC for the Raft 30 05-Jan-16 05-Feb-16 GFC for the Raft

A0840 GFC for Basement Slab 30 05-Feb-16 09-Mar-16 GFC for Basement Slab

A0850 GFC for Tower 1- Structural (Floor wise) 30 09-Mar-16 09-Apr-16 GFC for Tower 1- Structural (Floor wise)

A0860 GFC for Tower 2- Structural 30 09-Apr-16 12-May-16 GFC for Tower 2- Structural

A0865 GFC for Tower 1- Finishing/Plumbing/FF 60 09-Apr-16 13-Jun-16 GFC for Tower 1- Finishing/Plumbing/FF

A0875 GFC for Tower 2- Finishing/Plumbing/FF 60 12-May-16 15-Jul-16 GFC for Tower 2- Finishing/Plumbing/FF

A0880 GFC for External Development 30 15-Jul-16 16-Aug-16 GFC for External Development

Excavation Basement 175 16-Feb-16 22-Aug-16 22-Aug-16, Excavation Basement

A1000 Excavation till formation lvl except RAMP area 135 16-Feb-16 09-Jul-16 Excavation till formation lvl except RAMP area

A1010 Excavation of Ramp 40 09-Jul-16 22-Aug-16 Excavation of Ramp

Basement Construction 395 17-May-16 13-Jul-17 13-Jul-17, Basement Construction

Raft Construction 220 17-May-16 07-Jan-17 07-Jan-17, Raft Construction

A1100 PCC 120 17-May-16 22-Sep-16 PCC

A1110 Waterproofing at bottom 125 27-May-16 08-Oct-16 Waterproofing at bottom

A1120 Base Slab 175 23-Jun-16 28-Dec-16 Base Slab

A1130 Construction of Retaining Wall Ist Stage 150 30-Jul-16 07-Jan-17 Construction of Retaining Wall Ist Stage

Basement Slab Casting at -1 230 09-Jul-16 13-Mar-17 13-Mar-17, Basement Slab Casting at -1

A1190 Column Footing Pedestals 150 09-Jul-16 16-Dec-16 Column Footing Pedestals

A1200 Casting of Column 150 15-Jul-16 22-Dec-16 Casting of Column

A1210 C/o of Outer retaining Wall IInd Stage 150 30-Jul-16 07-Jan-17 C/o of Outer retaining Wall IInd Stage

A1220 Casting of Slab at -1 Lvl 190 22-Aug-16 13-Mar-17 Casting of Slab at -1 Lvl

Basement Ground Slab Casting 275 22-Sep-16 13-Jul-17 13-Jul-17, Basement Ground Slab Casting

A1150 Casting of Column 200 22-Sep-16 24-Apr-17 Casting of Column

A1160 C/o of Outer retaining Wall 200 22-Sep-16 24-Apr-17 C/o of Outer retaining Wall

Actual Work Critical Remaining Work Summary Page 1 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


08-Feb-16 15:06
NOIDA OFFICE BUILDING PROJECT AT SEC 96, INITIAL WORK PROGRAM
Activity ID Activity Name Original Start Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019
Duration
N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr MJun
A1170 Casting of Slab at Ground Lvl 200 12-Dec-16 13-Jul-17 Casting of Slab at Ground Lvl

Tower 1 Construction 680 28-Dec-16 25-Dec-18 25-Dec-18, Tower 1 Construction

Tower 1 Structural 510 28-Dec-16 26-Jun-18 26-Jun-18, Tower 1 Structural

A1240 Casting of Ist Floor Slab 40 28-Dec-16 08-Feb-17 Casting of Ist Floor Slab

A1250 Casting of 2nd Floor Slab 30 08-Feb-17 13-Mar-17 Casting of 2nd Floor Slab

A1260 Casting of 3rd Floor Slab 30 13-Mar-17 13-Apr-17 Casting of 3rd Floor Slab

A1270 Casting of 4th Floor Slab 30 13-Apr-17 16-May-17 Casting of 4th Floor Slab

A1280 Casting of 5th Floor Slab 30 16-May-17 16-Jun-17 Casting of 5th Floor Slab

A1290 Casting of 6th Floor Slab 30 16-Jun-17 19-Jul-17 Casting of 6th Floor Slab

A1300 Casting of 7th Floor Slab 25 19-Jul-17 15-Aug-17 Casting of 7th Floor Slab

A1310 Casting of 8th Floor Slab 25 15-Aug-17 11-Sep-17 Casting of 8th Floor Slab

A1320 Casting of 9th Floor Slab 25 11-Sep-17 07-Oct-17 Casting of 9th Floor Slab

A1330 Casting of 10th Floor Slab 25 07-Oct-17 02-Nov-17 Casting of 10th Floor Slab

A1340 Casting of 11th Floor Slab 25 03-Nov-17 29-Nov-17 Casting of 11th Floor Slab

A1350 Casting of 12th Floor Slab 25 29-Nov-17 26-Dec-17 Casting of 12th Floor Slab

A1360 Casting of 13th Floor Slab 25 26-Dec-17 22-Jan-18 Casting of 13th Floor Slab

A1370 Casting of 14th Floor Slab 25 22-Jan-18 17-Feb-18 Casting of 14th Floor Slab

A1380 Casting of 15th Floor Slab 25 17-Feb-18 16-Mar-18 Casting of 15th Floor Slab

A1390 Casting of 16th Floor Slab 25 16-Mar-18 12-Apr-18 Casting of 16th Floor Slab

A1400 Casting of 17th Floor Slab 25 12-Apr-18 09-May-18 Casting of 17th Floor Slab

A1410 Casting of 18th Floor Slab 25 09-May-18 05-Jun-18 Casting of 18th Floor Slab

A1420 Casting of Lift wall and Mumty at Roof Lvl 20 05-Jun-18 26-Jun-18 Casting of Lift wall and Mumty at Roof Lvl

Tower 1 Finishing 575 19-Apr-17 25-Dec-18 25-Dec-18, Tower 1 Finishing

A1430 Brickwork/Plaster 450 19-Apr-17 13-Aug-18 Brickwork/Plaster

A1450 False Ceiling/ Flooring /Wood work/Al Work/ 525 12-Jun-17 25-Dec-18 False Ceiling/ Flooring /W
Painting
A1460 Elevation- Structural Glazing/Stone 525 12-Jun-17 25-Dec-18 Elevation- Structural Gla
Cladding/facade
Tower 2 Constrcution 512 28-Jun-17 27-Dec-18 27-Dec-18, Tower 2 Constrcution

Tower 2 Structural 255 28-Jun-17 27-Mar-18 27-Mar-18, Tower 2 Structural

A1480 Casting of Ist Floor Slab 60 28-Jun-17 30-Aug-17 Casting of Ist Floor Slab

A1490 Casting of 2nd Floor Slab 40 31-Aug-17 12-Oct-17 Casting of 2nd Floor Slab

Actual Work Critical Remaining Work Summary Page 2 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


08-Feb-16 15:06
NOIDA OFFICE BUILDING PROJECT AT SEC 96, INITIAL WORK PROGRAM
Activity ID Activity Name Original Start Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019
Duration
N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D Jan F M Apr MJun
A1500 Casting of 3rd Floor Slab 30 12-Oct-17 14-Nov-17 Casting of 3rd Floor Slab

A1510 Casting of 4th Floor Slab 25 14-Nov-17 11-Dec-17 Casting of 4th Floor Slab

A1520 Casting of 5th Floor Slab 25 11-Dec-17 05-Jan-18 Casting of 5th Floor Slab

A1530 Casting of 6th Floor Slab 25 06-Jan-18 01-Feb-18 Casting of 6th Floor Slab

A1540 Casting of 7th Floor Slab 25 01-Feb-18 28-Feb-18 Casting of 7th Floor Slab

A1580 Casting of Lift wall and Mumty at Roof Lvl 25 28-Feb-18 27-Mar-18 Casting of Lift wall and Mumty at Roof Lvl

Tower 2 Finishing 412 12-Oct-17 27-Dec-18 27-Dec-18, Tower 2 Finishing

A1550 Brickwork/Plaster 300 12-Oct-17 29-Aug-18 Brickwork/Plaster

A1560 False Ceiling/ Flooring /Wood work/Al Work/ 350 15-Dec-17 25-Dec-18 False Ceiling/ Flooring /W
Painting
A1570 Elevation- Structural Glazing/Stone 270 13-Mar-18 27-Dec-18 Elevation- Structural Gla
Cladding/facade
Plumbing Work 485 13-Jul-17 14-Dec-18 14-Dec-18, Plumbing Work

A1590 Plumbing work Tower 1 450 13-Jul-17 07-Nov-18 Plumbing work Tower 1

A1600 Plumbing work Tower 2 350 14-Nov-17 22-Nov-18 Plumbing work Tower 2

A1610 External Plumbing work 250 22-Mar-18 14-Dec-18 External Plumbing work

Fire Fighting work 455 15-Aug-17 14-Dec-18 14-Dec-18, Fire Fighting work

A1620 Fire Fighting work Tower 1 375 15-Aug-17 19-Sep-18 Fire Fighting work Tower 1

A1630 Fire Fighting work Tower 2 275 15-Dec-17 05-Oct-18 Fire Fighting work Tower 2

A1640 External Fire Fighting work 250 22-Mar-18 14-Dec-18 External Fire Fighting work

External Development 142 31-Jul-18 31-Dec-18 31-Dec-18, External De

A1650 Outside Plumbing/FF 130 31-Jul-18 18-Dec-18 Outside Plumbing/FF

A1660 Road and Foothpath 67 19-Oct-18 31-Dec-18 Road and Foothpath

Project Completion & Handingover 13 17-Dec-18 31-Dec-18 31-Dec-18, Project Com

A1670 Completion of Tower 1 1 24-Dec-18 25-Dec-18 Completion of Tower 1

A1680 Completion of Tower 2 1 17-Dec-18 18-Dec-18 Completion of Tower 2

A1690 Completion of External Development 1 29-Dec-18 31-Dec-18 Completion of External

Actual Work Critical Remaining Work Summary Page 3 of 3 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation