Академический Документы
Профессиональный Документы
Культура Документы
A0810 Allotment of land for B/Plant, Camp, Lab, Office, 40 05-Jan-16 16-Feb-16 Allotment of land for B/Plant, Camp, Lab, Office, Working area
Working area
A0820 Allotment of earth disposal land 40 05-Jan-16 16-Feb-16 Allotment of earth disposal land
A0825 Approval from Mining Department 40 05-Jan-16 16-Feb-16 Approval from Mining Department
A0830 GFC for the Raft 30 05-Jan-16 05-Feb-16 GFC for the Raft
A0840 GFC for Basement Slab 30 05-Feb-16 09-Mar-16 GFC for Basement Slab
A0850 GFC for Tower 1- Structural (Floor wise) 30 09-Mar-16 09-Apr-16 GFC for Tower 1- Structural (Floor wise)
A0860 GFC for Tower 2- Structural 30 09-Apr-16 12-May-16 GFC for Tower 2- Structural
A0865 GFC for Tower 1- Finishing/Plumbing/FF 60 09-Apr-16 13-Jun-16 GFC for Tower 1- Finishing/Plumbing/FF
A0875 GFC for Tower 2- Finishing/Plumbing/FF 60 12-May-16 15-Jul-16 GFC for Tower 2- Finishing/Plumbing/FF
A0880 GFC for External Development 30 15-Jul-16 16-Aug-16 GFC for External Development
A1000 Excavation till formation lvl except RAMP area 135 16-Feb-16 09-Jul-16 Excavation till formation lvl except RAMP area
A1130 Construction of Retaining Wall Ist Stage 150 30-Jul-16 07-Jan-17 Construction of Retaining Wall Ist Stage
Basement Slab Casting at -1 230 09-Jul-16 13-Mar-17 13-Mar-17, Basement Slab Casting at -1
A1190 Column Footing Pedestals 150 09-Jul-16 16-Dec-16 Column Footing Pedestals
A1210 C/o of Outer retaining Wall IInd Stage 150 30-Jul-16 07-Jan-17 C/o of Outer retaining Wall IInd Stage
A1220 Casting of Slab at -1 Lvl 190 22-Aug-16 13-Mar-17 Casting of Slab at -1 Lvl
Basement Ground Slab Casting 275 22-Sep-16 13-Jul-17 13-Jul-17, Basement Ground Slab Casting
A1160 C/o of Outer retaining Wall 200 22-Sep-16 24-Apr-17 C/o of Outer retaining Wall
Actual Work Critical Remaining Work Summary Page 1 of 3 TASK filter: All Activities
A1240 Casting of Ist Floor Slab 40 28-Dec-16 08-Feb-17 Casting of Ist Floor Slab
A1250 Casting of 2nd Floor Slab 30 08-Feb-17 13-Mar-17 Casting of 2nd Floor Slab
A1260 Casting of 3rd Floor Slab 30 13-Mar-17 13-Apr-17 Casting of 3rd Floor Slab
A1270 Casting of 4th Floor Slab 30 13-Apr-17 16-May-17 Casting of 4th Floor Slab
A1280 Casting of 5th Floor Slab 30 16-May-17 16-Jun-17 Casting of 5th Floor Slab
A1290 Casting of 6th Floor Slab 30 16-Jun-17 19-Jul-17 Casting of 6th Floor Slab
A1300 Casting of 7th Floor Slab 25 19-Jul-17 15-Aug-17 Casting of 7th Floor Slab
A1310 Casting of 8th Floor Slab 25 15-Aug-17 11-Sep-17 Casting of 8th Floor Slab
A1320 Casting of 9th Floor Slab 25 11-Sep-17 07-Oct-17 Casting of 9th Floor Slab
A1330 Casting of 10th Floor Slab 25 07-Oct-17 02-Nov-17 Casting of 10th Floor Slab
A1340 Casting of 11th Floor Slab 25 03-Nov-17 29-Nov-17 Casting of 11th Floor Slab
A1350 Casting of 12th Floor Slab 25 29-Nov-17 26-Dec-17 Casting of 12th Floor Slab
A1360 Casting of 13th Floor Slab 25 26-Dec-17 22-Jan-18 Casting of 13th Floor Slab
A1370 Casting of 14th Floor Slab 25 22-Jan-18 17-Feb-18 Casting of 14th Floor Slab
A1380 Casting of 15th Floor Slab 25 17-Feb-18 16-Mar-18 Casting of 15th Floor Slab
A1390 Casting of 16th Floor Slab 25 16-Mar-18 12-Apr-18 Casting of 16th Floor Slab
A1400 Casting of 17th Floor Slab 25 12-Apr-18 09-May-18 Casting of 17th Floor Slab
A1410 Casting of 18th Floor Slab 25 09-May-18 05-Jun-18 Casting of 18th Floor Slab
A1420 Casting of Lift wall and Mumty at Roof Lvl 20 05-Jun-18 26-Jun-18 Casting of Lift wall and Mumty at Roof Lvl
A1450 False Ceiling/ Flooring /Wood work/Al Work/ 525 12-Jun-17 25-Dec-18 False Ceiling/ Flooring /W
Painting
A1460 Elevation- Structural Glazing/Stone 525 12-Jun-17 25-Dec-18 Elevation- Structural Gla
Cladding/facade
Tower 2 Constrcution 512 28-Jun-17 27-Dec-18 27-Dec-18, Tower 2 Constrcution
A1480 Casting of Ist Floor Slab 60 28-Jun-17 30-Aug-17 Casting of Ist Floor Slab
A1490 Casting of 2nd Floor Slab 40 31-Aug-17 12-Oct-17 Casting of 2nd Floor Slab
Actual Work Critical Remaining Work Summary Page 2 of 3 TASK filter: All Activities
A1510 Casting of 4th Floor Slab 25 14-Nov-17 11-Dec-17 Casting of 4th Floor Slab
A1520 Casting of 5th Floor Slab 25 11-Dec-17 05-Jan-18 Casting of 5th Floor Slab
A1530 Casting of 6th Floor Slab 25 06-Jan-18 01-Feb-18 Casting of 6th Floor Slab
A1540 Casting of 7th Floor Slab 25 01-Feb-18 28-Feb-18 Casting of 7th Floor Slab
A1580 Casting of Lift wall and Mumty at Roof Lvl 25 28-Feb-18 27-Mar-18 Casting of Lift wall and Mumty at Roof Lvl
A1560 False Ceiling/ Flooring /Wood work/Al Work/ 350 15-Dec-17 25-Dec-18 False Ceiling/ Flooring /W
Painting
A1570 Elevation- Structural Glazing/Stone 270 13-Mar-18 27-Dec-18 Elevation- Structural Gla
Cladding/facade
Plumbing Work 485 13-Jul-17 14-Dec-18 14-Dec-18, Plumbing Work
A1590 Plumbing work Tower 1 450 13-Jul-17 07-Nov-18 Plumbing work Tower 1
A1600 Plumbing work Tower 2 350 14-Nov-17 22-Nov-18 Plumbing work Tower 2
A1610 External Plumbing work 250 22-Mar-18 14-Dec-18 External Plumbing work
Fire Fighting work 455 15-Aug-17 14-Dec-18 14-Dec-18, Fire Fighting work
A1620 Fire Fighting work Tower 1 375 15-Aug-17 19-Sep-18 Fire Fighting work Tower 1
A1630 Fire Fighting work Tower 2 275 15-Dec-17 05-Oct-18 Fire Fighting work Tower 2
A1640 External Fire Fighting work 250 22-Mar-18 14-Dec-18 External Fire Fighting work
Actual Work Critical Remaining Work Summary Page 3 of 3 TASK filter: All Activities