DBQ 2324 UKUR BINAAN II

MEASUREMENT 1 – PILING WORKS

Types of piles:

1. Driven pile
a. Bakau
b. Timber/tanalised timber
c. Precast concrete
d. Steel - H pile

2. Bored pile
Normally concrete based.

3. Sheet pile
a. Steel sheet pile
b. Concrete sheet pile
NOTE:
All piling works are classified as PROVISIONAL due to the
uncertainty in determining the ‘extent of work’ i.e the depth of
penetration of pile.

Therefore, the quantities measured in the bill will be subject to


remeasurement after completion of the piling works. This will be
done using the piling records prepared during the execution of the
works.

SECTION E – PILING AND DIAPHRAGM WALLING

Piling
E.1 Information
1. Drawing shall be supplied with the bill of quantities which
shows:
a. The general piling layout
b. The positioning of different types of pile
c. The position of the work within the site and of
existing services
E.2 Soil description
1. The nature of the ground shall be given in accordance
with clause D.1.1.
2. Where work is to be carried out near canals, rivers etc.
level of ground in relation to the water level shall be
stated.

E.3 Starting levels


1. The levels from which the work is expected to begin
and from which measurements have been taken shall
be stated. Irregular ground shall be so described.

E.4 Plant
1. The following items shall be given separately for each
type of pile identified in accordance with clause E.5.1:
a. An item shall be given for bringing to site and
removing from site all plants required for this
section of work.
b. An item shall be given for maintaining on site all
plants required for this section of the work.
Example of description:
Allow for the provision of all necessary piling equipment, plants
and tools and for their transportation to the site, handling ,
erecting, assemblying and removal off the site after completion
of piling operations - ITEM

Example of description:
Allow for moving and handling of piling equipment about the
site as often as and when necessary anf for the whole operation
including all maintanence and idling time - ITEM

Normally, another additional item is provided for the provision of


piling records to be prepared by the Contractor during the
execution of piling works.

Example of description:
Allow for the submission of piling records of all piles in
triplicate copy duly signed by the Contractor and the S.O as the
work proceeds - ITEM
E.5 Piling description and measurement
1. The following types of piling operation shall each be
given under a separate heading together with all
ancillary work:
a. Bored cast-in-place concrete piles
b. Driven shell cast-in-place concrete piles
c. Pre-formed concrete piles
d. Pre-formed prestressed concrete pile
e. Pre-formed concrete sheet piles
f. Timber piles
g. Isolated steel piles
h. Interlocking steel piles
i. Other piles

Within the classification, the following shall each be


given separately:

i) Preliminary piles
ii) Test piles
iii) Contiguous bored pile
iv) Raking pile according to angle of rake in
increments of 10.
v) Piles to be extracted shall be identified and given
separately.

2. Within the classification provided in accordance with


clause E.5.1, items shall be given in accordance with
clauses E.5.3 – 5 grouped under subheadings which state
the following:
a. nominal cross sectional size
b. the materials of which the piles are composed
and in the case of steel pile, the nominal
weight per metre.
 concrete - concrete mix
 steel – grade of steel

3. For piles other than cast-in-place concrete and


interlocking steel piles (i.e timber, precast concrete) items
shall be given for:
a. The total number of piles stating the
specified length. The size and weight of heads
and shoes shall be stated in the description.
( This is for the item of ‘Supply of pile’).
b. The total driven depth given in metres.
( This is for the item of ‘Driving of pile’ ).
7. In the case of pile extensions, items shall be given for:
a. The total number of pile extensions.
b. The total length of pile extensions given in metres
classified into the following ranges of pile length:
Not exceeding 3.00 m
Exceeding 3.00 m

8. The following shall be ENUMERATED:


a. Cutting off tops of isolated piles to required levels
which shall be deemed to include provision and
backfilling of any working space required.
b. Preparing concrete pile heads and reinforcement for
capping.

E.7 Tests
Items shall be given for test of piles stating the details.
Provision and maintanence of all necessary equipment,
instruments and record keeping shall be deemed to be
included. Measured as ITEM or NUMBER.
ITEMS TO BE MEASURED

Timber pile

1. Preparation of Preamble of works:


- Nature of ground (E.2.1)
- Difference between ground and
water level if work is near river,
canals etc. ( E.2.2 )
- Starting level for the works (E.3.1 )

2. Provision of plant and equipments ( E.4.1.a )


3. Provision for moving, maintanence of plant ( E. 4.1.b )
4. Provision for piling records

5. Supply of initial piles stating the cross sectional size and


specified length and measured in NUMBER. The description
must include size and weight of pile heads and shoes (if any).

6. Supply of extension pile (if any) stating the cross sectional size
and classified into ranges according E.5.7.b and measured in
LINEAR METRE.
7. Driving of piles including initial and extension piles and
measured in LINEAR METRE ( E.5.3.b and E.8.1.b).

8. Pile extensions measured in NUMBER ( E.5.7.a ).

9. Cutting of pile head measured in NUMBER ( E.5.9.a ).

10. Testing ( E.7).

Supply of pile

Supply, deliver and unload on site 150 mm x 150 mm ‘Kempas’ or


other SIRIM approved tanalised timber initial piles not exceeding
5.0 m long including all necessary and approved piles shoes.

24 (F 1) Measured in NUMBER
Supply ,deliver and unload on site 150 mm x 150 mm ‘Kempas’ or
other SIRIM approved tanalised timber extension piles exceeding
3.0 m long ( or not exceeding 3.0 m long depending on the
situation ).

24
5.00 (F 1) Measured in LINEAR METRE

Driving of piles

Drive 150 mm x 150 mm tanalised timber piles (initial and


extension).

24
15.00 (F 1) Measured in LINEAR METRE
Pile extensions

Extension sleeve joint 163 mm x 163 mm x 6 mm thick mild steel


hollow section sleeve 450 mm long with a 150 mm x 150 mm x 4
mm thick mild steel plate cut to shape and welded midway in
sleeve including shaving ends of timber pile to fit into sleeve,
painting sleeve with two coats of bituminous paint inside and
outside.

24 (F 1) Measured in NUMBER

Cutting of pile heads

Cutting heads of 150 mm x 150 mm tanalised timber pile including


disposal of surplus pile head from site.

24 (F 1) Measured in NUMBER
Testing

Allow for first testing of 150 mm x 150 mm tanalised timber pile


to twice the working load as described.

ITEM Measured as ITEM

Allow for subsequent testing of 150 mm x 150 mm tanalised


timber piles as before described.

ITEM