Вы находитесь на странице: 1из 6

ABSTRACT SHEET

Name Of Work :- Concreting for wall (Quantity per floor )

Quantit
Sr.No. y Description Rate Unit Amount

1 59.73 Concreting in superstructure 4500 Cu.Mtr. 268772


M20 grade.

2 22.67 Slab:- 4500 Cu.Mtr. 102015


(concreting in slab)
M20 grade

3 1.72 Staircase:- 4500 Cu.Mtr. 7722


M20 grade

4 12.67 Concreting in all columns 4500 Cu.Mtr. 57024


M20 grade

5 14.69 Concreting in beams 4500 Cu.Mtr. 66105


(M20 grade)

501638
ABSTRACT SHEET
Name Of Work :- Mivan Formwork (Quantity per floor )

Sr.No. Quantity Description Rate Unit Amount

1 6438.61 Aluminium formwork for 6500 Sq.Mtr. 41850952


walls.

2 14.72 Aluminium formwork for 6500 Sq.Mtr. 95680


lobby wall.

3 35.84 Aluminium formwork for 6500 Sq.Mtr. 232960


stair-case.

4 38.40 Aluminium formwork for 6500 Sq.Mtr. 249600


lift room.

5 153.71 Aluminium formwork for 6500 Sq.Mtr. 999115


slab.

6 42.24 Aluminium formwork for 6500 Sq.Mtr. 274560


columns.

7 195.93 Aluminium formwork for 6500 Sq.Mtr. 1273545


beam
44976412

Note:- The cost of formwork per sq.Mtr. Includes fixtures, joints,


panels etc.
the cost of mivan formwork per sq.mtr. Also includes cost of
transportation as well as octroi tax which are ment for district
transfer during transportation.
ABSTRACT SHEET
Name Of Work :- Steel Calculations (Quantity per floor )

Sr.No. Quantity Description Rate Unit Amount

1 734.05 Mivan Wall (R.C.C. Wall) 46 Kg 33766


8mm bar.

2 Column
297.88 Transverse steel (8mm ) 46 Kg 13702
889.86 Mainbar (16 mm) 44 Kg 39154

3 Beam
3561.85 main steel (10mm) 44 Kg 156721
5998.01 Stirrups-2L- (8mm) 46 Kg 275908

4 Slab
765.22 Main Bottom steel bar and 44 Kg 33670
bent up bar (12mm)
783.02 Distribution steel (8mm) 46 Kg 36019

588941
ABSTRACT SHEET

Sr.No. Quantity Description Rate Unit Amount

1 Grouting
8.00 Material 400 Bags 3200
L/S Labour 4500

2 153.71 Erection of formwork with 1345 Sq. Mt. 206740


removal as well as placing steel
and concrete. And washing of
steel formwork.

3 Painting work
604.20 Internal - Plastic emulsion paint. 151 Sq.Mt. 91234
306.49 External - Texture paint. 452 Sq.Mt. 138533

444208
ABSTRACT SHEET
Name Of Work :- RCC Frame Structure (Quantity per floor )

Sr.No. Quantity Description Rate Unit Amount

1 50.98 Concreting in slab beam and 16350 Cu.Mt. 833523


column with formwork.

2 105.37 1st class brick work in super- 5100 Cu.Mt. 537387


structure with labour

3 Steel
Column
297.88 Transverse steel (8mm ) 46 Kg 13702
889.86 Mainbar (16 mm) 44 Kg 39154
Slab
765.22 Main Bottom steel bar and 44 Kg 33670
bent up bar (12mm)
783.02 Distribution steel (8mm) 46 Kg 36019
Beam
2872.92 main steel (10mm) 44 Kg 126408
3897.00 Stirrups-2L- (8mm) 46 Kg 179262

4 680.74 Internal Plaster 145 Sq.Mt. 98707

5 306.49 External Plaster 160 Sq.Mt. 49038

6 Painting
604.20 Internal- Plastic emulsion paint 151 Sq.Mt. 91234
306.49 External- Apex Ultima paint. 162 Sq.Mt. 49651

2087757

No. Of Repetation Cost with Conventional Cost with Mivan


1 2,087,757 4,65,11,199
10 20877570 60324274
20 41755140 75672136
30 62632710 91019998
40 83510280 106367860
50 104387850 121715723
60 125265420 137063585
70 146142990 152411447
80 167020560 167759309
90 187898130 183107171
100 208775700 198455033
110 229653270 213802895
120 250530840 229150757
130 271408410 244498619
140 292285980 259846481
150 313163550 275194344
Difference in cost 37,969,206