Item No.

Item Description Unit Fata


Excavation in hard rock requiring blasting and disposal
03-12-c upto 25m & dressing : Grade III m3 557.69
Filling, watering and ramming earth under floor with surplus
03-16-a earth from foundation, etc m3 109.80
Excavation in foundation of building, bridges etc complete :
03-23-b In ordinary soil m3 228.18
### Excavation in foundation of building, bridges etc
03-23-d complete : In shingle/gravel m3 287.21
Plain Cement Concrete incl. placing, compacting, finishing
06-05-f & curing (Ratio 1:2:4) m3 7398.32
Plain Cement Concrete incl. placing, compacting, finishing
06-05-h & curing (Ratio 1:3:6) m3 6018.51
Plain Cement Concrete incl. placing, compacting, finishing
06-05-i & curing (Ratio 1:4:8) m3 5385.03
RCC in roof slab, beam, column & other structural
06-06-a-02 members, insitu or precast. Type B (1:1.5:3) m3 11187.12
RCC in roof slab, beam, column & other structural
06-06-a-03 members, insitu or precast. Type C (1:2:4) m3 10094.84
06-06-e Add extra labour for RCC in 2nd & subsequent storeys m3 772.20
Supply & fabricate M.S. reinforcement for cement concrete
06-07-b (Deformed bars) tonne 120459.13
Damp proof of cem. conc. 1:2:4 i/c bitumen coat, 1 layer
06-22-a-02 polythene & 1 coat bitumen (2" thick) m2 602.59
Pacca brick work in foundation and plinth in Cement, sand
07-04-a-05 mortar 1:6 m3 7352.89

07-05-a-03 Pucca brick work in ground floor Cement, sand mortar 1:4 m3 8230.64

07-05-a-05 Pucca brick work in ground floor Cement, sand mortar 1:6 m3 7827.28
Add extra labour on item No.07-05 for brickwork in First
07-06-a floor m3 283.66

07-30 Supplying and filling sand under floor or plugging in wells m3 2664.37
Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1"
09-05 mud plaster on top of RC roof slab m2 945.23
09-15 Khuras on roof 2'x2'x6" Each 525.15
Bottom khuras of brick masonry in c/s mortar 1:6,4'x2'x4.5"
09-16 over 3" cem. concrete 1:4:8 Each 1260.07
Cast iron rain water down pipe fixed in position excl. heads
09-19-a & shoes : 4" dia m 2582.52
Shoes, bends or offsets for cast iron ran water down pipe,
09-21 incl. fixing & painting Each 380.80
Laying 1/2" thick deodar ceiling complete, incl. sawing,
09-23 planing & fixing m2 1555.68
Lay floor of white glazed tile 1/4" thick in white cement 1:2
10-24 over 3/4" thick cement mortar 1:2 m2 1786.66
Provide & lay marble fine dressed stone flooring on surface
10-26-a in white cement complete: 3/4" thick m2 3189.19
Provide & lay marble fine dressed stone dado or skirting in
10-41-b white cement complete : 1/2" thick m2 2952.16
11-09-b Cement plaster 1:4 upto 20' height 1/2" thick m2 201.25
Cement pointing struck joints, on walls, upto 20' height :
11-18-b Ratio 1:3 m2 180.78
MS flat 1/2"x1/8" grill in windows of approved design incl.
12-50 painting 3 coats, complete m2 1589.05
Prepare & Paint new surface, doors & windows Priming
13-06-c-01 coat m2 87.89
Prepare & Paint new surface, doors & windows Each
13-06-c-02 subsequent coat of paint m2 56.34
Preparing surface and painting with emulsion paint : First
13-30-a coat m2 118.66
Item No. Item Description Unit Fata
Preparing surface and painting with emulsion paint : 2nd &
13-30-b each subsequent coat. m2 58.01
P&F glazed earthern ware WC squatting type with built-in
14-03-a foot rests : White Each 3343.73
P&F glazed earthern ware WHB complete Size 22"x16" :
14-05-a-01 White with pedestal Each 3441.90
P&F glazed earthern ware low down flushing cistern 3
14-10-a gallons capacity : White Each 2697.04
14-16-a P&F CP towel rail : 24" long, 3/4" dia Each 580.71
14-17 P&F best quality 5mm mirror 22"x16" size Each 1733.94
14-20-a P&F Plastic soap dish. Each 358.95
14-20-d P&F Plastic shelf 24"x5" with Each 289.65
14-21-b P&F CP pillar-cock, heavy type : 1/2" Each 753.96
14-22-b P&F CP stop-cock, heavy type : 1/2" Each 795.54
14-24-b P&F CP bib-cock, heavy type : 1/2" Each 740.10
P&F CI floor trap incl. CI grating & concrete chamber all
14-31-b round : 4"x3" Each 486.95
14-32-b P&F 'P' trap incl. GI grating & PCC chamber 4" glazed Each 264.31
Providing and fitting CI soil pipe with : Cement caulked
14-34-b-01 joint : 4" dia m 860.45
Providing and fitting CI soil pipe with : Cement caulked
14-34-b-02 joint : 2" dia m 577.57
S&E PVC pipe for wiring purpose complete Recessed in
15-02-b-02 walls incl. chase etc : 3/4" i/d m 131.18
S&E PVC pipe for wiring purpose complete Recessed in
15-02-b-03 walls incl. chase etc : 1" i/d m 141.22
S&E single core PVC insulated copper conductor 250/440
15-05-c V grade cable : 7/0.029" m 44.06
S&E MS sheet box of 16 SWG, 4"deep with 3/16" thick
15-09-a bakelite sheet top etc. complete : 4"x4" Each 238.57
S&E MS sheet box of 16 SWG, 4"deep with 3/16" thick
15-09-e bakelite sheet top etc. complete : 10"x12" Each 711.16
S&E 9" long swan neck plain brass/steel/brass oxidised
15-14 bracket lamp holder, complete Each 127.21
S&E 2'x2'x1/8" copper plate incl. rivetting to copper tape &
15-42 placing in mixture of salt etc Each 6705.20
Wiring of light/fan/call-bell point in 3/0.029 PVC insulated
15-50 bare cable in PVC pipe recessed Each 1200.55
Wiring of 2/3-pin 5-Amp. plug point in 3/0.029 PVC
15-51 insulated bare cable in PVC pipe recessed Each 893.26
S&E fluorescent tube light fitting incl. 4' rod, choke, starter,
15-61-a flexible wire etc : Single Each 1369.14
S&E porch-light fitting round/square type with gallery,
15-62 holder & 40 W bulb Each 1035.52
S&E best quality AC ceiling fan complete with GI rod,
15-68-c canopy, blades & regulator : 56" sweep Each 5375.66
S&E best quality exhaust fan complete with shutter &
15-69-a regulator : 12"sweep Each 3552.09
15-71-a S&E single phase imported auto circuit breaker 6 Amp. Each 1000.87

15-71-d S&E single phase imported auto circuit breaker 30 Amp. Each 1243.42
### S&E cubical type factory fabricated floor/wall mounting
15-75-b steel main board comp. : Recessed Each 23038.32
P&L RCC pipe, moulded with cement concrete 1:1.5:3,
23-01-a incl. cost of reinfcnt, testing etc : 4" m 440.67
P&L RCC pipe, moulded with cement concrete 1:1.5:3,
23-01-b incl. cost of reinfcnt, testing etc : 6" m 592.39
P&L RCC pipe, moulded with cement concrete 1:1.5:3,
23-01-c incl. cost of reinfcnt, testing etc : 9" m 787.52
P&L, cut, joint, test & disinfect GI pipe line Using light
24-16-c-01 quality GI Pipe : 1/2" i/d m 208.01
Item No. Item Description Unit Fata
P&L, cut, joint, test & disinfect GI pipe line Using light
24-16-c-02 quality GI Pipe : 3/4" i/d m 280.11
P&L, cut, joint, test & disinfect GI pipe line Using light
24-16-c-03 quality GI Pipe : 1" i/d m 377.74
P&L, cut, joint, test & disinfect GI pipe line Using light
24-16-c-06 quality GI Pipe : 2" i/d m 531.00
### S/F MS manhole cover of 0.25" thick sheet & angle
24-33 iron frame 2"x2"x0.25" with lock complete m2 6055.79
P&F MS angle iron 1«"x1«"x1/4" edge protector nozing of
25-36 steps of stairs, complete m 435.54
P&F steel windows with openable glazed panels With 22
25-39-b-03 SWG wire gauze : Glass pane 3mm m2 5785.34
P&F angle iron railing, using 2.5"x2.5"x3/8" angle iron post
25-41 4.5'long, 5'to 6" apart, complete m 3497.03
Making notice board 1/2" thick of c/s mortar 1:3 with
26-17 2"x1/2" beading m2 983.25
Excavate well in dry & dispose of soil within 50m In
21-01-a-01 ordinary soil or sand : Upto 1.5 m depth m3 156.64
Excavate well in dry & dispose of soil within 50m In
21-01-a-02 ordinary soil or sand : 1.5 to 3 m depth m3 163.60
Excavate well in dry & dispose of soil within 50m In
21-01-a-03 ordinary soil or sand : 3 to 4.5 m depth m3 184.46
Excavate well in dry & dispose of soil within 50m In hard
21-01-c-01 strata like shingle : Upto 1.5 m depth m3 411.52
Excavate well in dry & dispose of soil within 50m In hard
21-01-c-02 strata like shingle :1.5 to 3 m depth m3 426.28
Excavate well in dry & dispose of soil within 50m In hard
21-01-c-03 strata like shingle : 3 to 4.5 m depth m3 444.41
Spraying anti-termite liquid mixed with water in the ratio of
26-15 1:40 m2/spray 33.29
### P/F Precast Concrete 7000 psi TUFF Tiles over bed of
10-45 2" thick sand & 4" thick brick ballast comp m2 1381.66
S&F aluminium door/window, Premium 4" sect. Hinges
12-53-d-02 window m2 10355.73
### P/F Polyethylene Water Tank (Super Tuff) 1000
14-69-b-04 gallons (Vertical) Each 70856.66
S&E single core PVC insulated copper conductor 250/440
15-05-a V grade cable : 3/0.029" m 38.47
Abstract of Cost Lab's/Resource Room &
Multipurpose Hall, GEC For Girls
S. No. Descriptions Amount (Rs)

1 Main Building 9,085,671

2 Internal Water Supply 250,967

3 Internal Electrification 313,010

4 Septic Tank 98,909

5 Soakage Pit 37,772

Total: 9,786,329

1
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

Lab's/Resource Rooms & Multipurpose Hall, GEC for GIRLS


1 Excavation in foundation of building, bridges etc m3 186.98 557.69 104,276
complete : In shingle gravel

2 Filling, watering and ramming earth under floor with m3 148.13 109.80 16,264
surplus earth from foundation, etc.

3 Plain Cement Concrete incl. placing, compacting, m3 57.12 5,385.03 307,572


finishing & curing (Ratio 1:4:8).

4 Plain Cement Concrete incl. placing, compacting, m3 36.69 7,398.32 271,431


finishing & curing (Ratio 1:2:4).

5 RCC in roof slab, beam, column & other structural m3 73.07 11,187.12 817,496
members, insitu or precast. 3000 PSI.

6 Supply & fabricate M.S. reinforcement for cement tonne 11.09 120,459.13 1,335,529
concrete (Deformed bars)

7 Damp proof of cem. conc. 1:2:4 i/c bitumen coat, 1 m2 5.16 602.59 3,108
layer polythene & 1 coat bitumen (2" thick).

8 Pacca brick work in foundation and plinth in Cement, m3 46.46 7,352.89 341,586
sand mortar 1:6.

9 Pucca brick work in ground floor Cement, sand mortar m3 73.17 7,827.28 572,689
1:6.

10 Supplying and filling sand under floor or plugging in m3 32.92 2,664.37 87,706
wells.

11 Supplying Shingle under floor. m3 32.92 480.09 15,804

12 Single layer of tiles of approved size laid over 4" earth m2 324.07 945.23 306,322
and 1" mud plaster on top of RC roof slab.

13 P&L of polythene sheet on roof. m2 324.07 40.00 12,963

14 P&L of Jumbolon on roof. m2 324.07 807.00 261,525

15 Khuras on roof 2'x2'x6" . Each 7 525.15 3,676

16 Bottom khuras of brick masonry in c/s mortar Each 7 1,260.07 8,820


1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8.

17 Cast iron rain water down pipe/PVC Polyfit fixed in m 100 2,582.52 258,252
position excl. heads & shoes : 4" dia.

2
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

18 Shoes, bends or offsets for cast iron ran water down Each 40 380.80 15,232
pipe, incl. fixing & painting.

19 Provide & lay marble fine dressed stone flooring on m2 370.19 3,189.19 1,180,595
surface cement complete: 3/4" thick.

20 Provide and lay marble fine dressed stone dado or m2 19.01 2,952.16 56,108
skirting in white cement complete: 1/2" thick.

21 Cement plaster 1:4 upto 20' height 1/2" thick. m2 1323.70 201.25 266,395

22 MS flat 1/2"x1/8" grill in windows of approved design m2 54.65 1,589.05 86,836


incl. painting 3 coats, complete or as approved.

23 Prepare & Paint new surface in joinery where required, m2 85.50 87.89 7,514
Priming coat.

24 Prepare & Paint new surface in joinery where required, m2 85.50 56.34 4,817
First coat.

25 Prepare & Paint new surface in joinery where required, m2 85.50 56.34 4,817
2nd coat.

26 Prepare & Paint new surface in joinery where required, m3 85.50 56.34 4,817
3rd coat.

27 Preparing surface and painting with emulsion paint : m1 884.20 118.66 104,919
Priming coat.

28 Preparing surface and painting with emulsion paint : m2 884.20 58.01 51,295
First coat.

29 Preparing surface and painting with emulsion paint : m2 884.20 58.01 51,295
2nd coat.

30 Preparing surface and painting with emulsion paint : m2 884.20 58.01 51,295
3rd coat.

31 Making and fixing deodar doors with frames and lasani m2 42.75 9,146.00 391,000
panels.

32 P&F Aluminium windows m2 54.65 10,355.73 565,908

33 Providing wire mesh. m2 135.87 645.60 87,720

34 Providing and applying Grafiato on exterior wall m2 135.87 538.00 73,100


surfaces.

35 Providing Pre-cast slab. m2 324.07 2,152.00 697,400

3
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

36 Providing and fixing gypsem board false ceiling. m2 324.07 1,555.68 504,152

37 Providing Tuff Tiles as per approved source and m2 58.55 1,381.66 80,897
design.

38 Providing ceramic tiles. m2 35.13 1,786.66 62,766

39 Spraying Anti-termite liquid in foundation. m2 353.72 33.29 11,774

Total: 9,085,671

4
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

Internal Water Supply


1 P&F glazed earthern ware WC squatting type with Each 2 3,343.73 6,687
built-in foot rests : White

2 P&F glazed earthern ware WHB complete Size Each 2 3,441.90 6,884
22"x16" : White with pedestal

3 P&F glazed earthern ware low down flushing cistern 3 Each 2 2,697.04 5,394
gallons capacity : White

4 P&F CP towel rail : 24" long, 3/4" dia Each 2 580.71 1,161

5 P&F best quality 5mm mirror 22"x16" size Each 2 1,733.94 3,468

6 P&F Plastic soap dish. Each 2 358.95 718

7 P&F Plastic shelf 24"x5" with Each 2 289.65 579

8 P&F CP pillar-cock, heavy type : 1/2" Each 5 753.96 3,770

9 P&F CP stop-cock, heavy type : 1/2" Each 4 795.54 3,182

10 P&F CP bib-cock, heavy type : 1/2" Each 5 740.10 3,701

11 P&F CI floor trap incl. CI grating & concrete chamber Each 2 486.95 974
all round : 4"x3"

12 P&F 'P' trap incl. GI grating & PCC chamber 4" glazed Each 2 264.31 529

13 Providing and fitting CI soil pipe with : Cement caulked m 13 860.45 11,186
joint : 4" dia

14 Providing and fitting CI soil pipe with : Cement caulked m 10 577.57 5,776
joint : 2" dia

15 P&L, cut, joint, test & disinfect GI pipe line Using light m 30 208.01 6,240
quality GI Pipe : 1/2" i/d

16 P&L, cut, joint, test & disinfect GI pipe line Using light m 30 280.11 8,403
quality GI Pipe : 3/4" i/d

17 P&L, cut, joint, test & disinfect GI pipe line Using light m 30 377.74 11,332
quality GI Pipe : 1" i/d

5
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

18 Construction of Main Hole 18" Each 4 2,500.00 10,000

19 P&L RCC pipe, moulded with cement concrete 1:1.5:3, m 70 787.52 55,126
incl. cost of reinfcnt, testing etc : 9"

20 P&F Polythylene water tank (super tuff) 1000 Gallons. Each 1 70,856.66 70,857

21 Providing and fixing Muslim shower. Each 5 1,000.00 5,000

22 Water Pump (1 hp) assembly with all accessories Each 2 15,000.00 30,000

23 Providing and fixing sink. Each 0 5000 -

Total: 250,967

6
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

Internal Electrification
1 S&E PVC pipe for wiring purpose complete Recessed m 170 141.22 24,007
in walls incl. chase etc : 1" i/d

2 S&E single core PVC insulated copper conductor m 380 38.47 14,620
250/440 V grade cable : 3/0.029"

3 S&E single core PVC insulated copper conductor m 270 44.06 11,897
250/440 V grade cable : 7/0.029"

4 S&E MS sheet box of 16 SWG, 4"deep with 3/16" thick Each 6 711.16 4,267
bakelite sheet top etc. complete : 10"x12"

5 S&E MS sheet box of 16 SWG, 4"deep with 3/16" thick Each 4 238.57 954
bakelite sheet top etc. complete : 4"x4"

6 S&E 2'x2'x1/8" copper plate incl. rivetting to copper Each 1 6,705.20 6,705
tape & placing in mixture of salt etc

7 Wiring of 2/3-pin 5-Amp. plug point in 3/0.029 PVC Each 12 893.26 10,719
insulated bare cable in PVC pipe recessed

8 Wiring of light/fan/call-bell point in 3/0.029 PVC Each 41 1,200.55 49,223


insulated bare cable in PVC pipe recessed

9 S&E fluorescent tube light fitting incl. 4' rod, choke, Each 18 1,369.14 24,644
starter, flexible wire etc : Single

10 S & E Verandah Light fitting round/square type with Each 9 1,035.52 9,320
gallery , holder and 40 w bulb

11 S&E best quality AC ceiling fan complete with GI rod, Each 14 5,375.66 75,259
canopy, blades & regulator : 56" sweep

12 S&E best quality exhaust fan complete with shutter & Each 2 3,552.09 7,104
regulator : 12"sweep

13 S&E single phase imported auto circuit breaker 6 Amp. Each 10 1,000.87 10,009

14 S&E single phase imported auto circuit breaker 30 Each 1 1,243.42 1,243
Amp.

15 ### S&E cubical type factory fabricated floor/wall Each 1 23,038.32 23,038
mounting steel main board comp. : Recessed

16 PVC 4 Core Cable 25mm m 40 1,000.00 40,000

Total: 313,010

7
Estimate of Lab's/Resource room, GEC For GIRLS
1. Excavation in foundation

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Wall footing section - A 1 64 3.00 3.50 672.00

Wall footing section - B 1 20 1.50 2.50 75.00

Column footing -F1 11 5 4.00 5.00 1100.00

Column footing -F2 7 6 4.00 6.00 1008.00

Column footing -F3 7 7 4.00 7.00 1372.00

Column footing -F4 4 8 4.00 8.00 1024.00

Column footing -F5 3 5 4.00 5.00 300.00


Plinth protection 1 210 0.67 3.00 420.00

Toe wall 1 210 1.25 0.375 98.44

Drain 1 210 1.33 1.50 418.95

Front steps 1 115 0.33 3.00 113.85

6602.24 cft
Total (1):
186.98 m3

2. PCC (1:4:8) in foundation

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Wall footing section - A 1 64 0.75 3.50 168.00

Wall footing section - B 1 20 0.25 2.50 12.50

Column footing -F1 11 5 0.25 5.00 68.75

Column footing -F2 7 6 0.25 6.00 63.00

Column footing -F3 7 7 0.25 7.00 85.75

Column footing -F4 4 8 0.25 8.00 64.00

Column footing -F5 3 5 0.25 5.00 18.75

Plinth protection 1 210 0.25 3.00 157.50

Toe wall 1 210 0.33 0.375 25.99

Drain 1 210 0.33 1.50 103.95

10
Front steps 1 115 0.25 3.00 86.25

854.44 cft
Total (2):
24.20 m3

3. RCC (1:1.5:3) in Foundation

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Column footing -F1 11 5 0.75 5.00 18.75

Column footing -F2 7 6 1.00 6.00 36

Column footing -F3 7 7 1.00 7.00 49

Column footing -F4 4 8 1.25 8.00 80

Column footing -F5 3 5 0.75 5.00 18.75

Plinth Beam 1.00 660.00 1.25 1.00 825

S.Total: 1027.50 cft

Wastage @ 5% 1 51.38 51.38 cft

S.Total: 51.38 cft

1078.88 cft
Total (3):
30.55 m3

4. BB work in CSM (1:6) in Plinth

Brick work No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Wall section - A (1'-10.5" step) 1 64 0.5 1.875 60.00

Wall section - A (1'-6" step) 1 64 0.5 1.500 48.00

Wall section - A (13½" step) 1 64 0.5 1.125 36.00

Wall section - A (9" step) 1 64 2.75 0.75 132.00

Wall section - B (13½" step) 1 20 0.5 1.125 11.25

Wall section - B (9" step) 1 20 0.75 0.75 11.25

Wall section - B (4.5" step) 1 20 2 0.75 30.00

Wall b/w NSL & Plinth level 1 290 2 1.13 652.50

S.Total: 981.00 cft

11
BB work in front Steps No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Step 1 1 115 0.5 3 172.50

Step 2 1 115 0.5 2 115.00

Step 3 1 115 0.5 1 57.50

S.Total: 345.00 cft

BB work in Drain & Toe wall No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Toe wall 1 210 1 0.375 78.75

Drain 2 210 1 0.375 157.50

S.Total: 236.25 cft

Wastage @ 5% 1 78.11 78.11 cft

S.Total: 78.11 cft

1640.36 cft
Total (4):
46.46 m3

5. BB work in CSM (1:6) in Ground Floor (9" thick)

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

External walls 9" thick 1 0 10.00 0.75 0.00

Internal walls 9" thick 1 380 10.00 0.75 2850.00

Internal walls 4.5" thick 1 20 10.00 0.375 75.00

Above bond beam 1 230 1.75 0.375 150.94

S.Total: 3075.94 cft

Wastage @ 5% 1 153.80 153.80 cft

S.Total: 153.80 cft

Parapet wall No Length (ft) Depth (ft) Width (ft) Quantity (cft)

1 310 2 0.75 465.00 cft

S.Total: 465.00 cft

Deductions No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Columns 32 1 10 1 320.00

D1 8 4 10 0.75 240.00

12
D2 2 3.5 10 0.75 52.50

D4 2 2.5 7 0.75 26.25

D3 2 3 7 0.75 31.50

W1 16 6 6 0.75 432.00

Ventilators 2 3 2 0.75 9.00

S.Total: 1111.25 cft

2583.48 cft
Total (5):
73.17 m3

6. RCC (1:1.5:3) in Columns, beams, lintels etc.

Level - 1 No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Column (C1) 20 1 6.0 1 120.00

Column (C2) 8 1 6.0 1 48.00

Column (C3) 4 1 6.0 1 24.00

Level - 2

Column (C1) 20 1 10.0 1 200.00

Column (C2) 8 1 10.0 1 80.00

Column (C3) 4 0.75 10.0 0.75 22.50

Bond Beam (BB1) 1 305 2.0 1 610.00

Bond Beam (BB2) 1 100 1.0 0.75 75.00

Bond Beam (BB3) 1 44 2.0 1 88.00

Projections 1 280 0.58 162.40

S.Total: 1429.90 cft

Wastage @ 5% 1 71.50 71.50 cft

S.Total: 71.50 cft

1501.40 cft
Total (6):
42.52 m3

13
7. Steel Reinforcement
Length of
In foundation No Bar # wt (lb/rft) Quantity (lbs)
bars
Footing - F1 11 95.86 4 0.668 704.36

Footing - F2 7 184.60 4 0.668 863.19

Footing - F3 7 249.00 4 0.668 1164.32

Footing - F4 4 208.25 4 0.668 556.44

Footing - F5 3 95.86 4 0.668 192.10

1 3961 3 0.376 1489.15


Plinth Beam
1 4026 6 1.502 6047.05

S.Total: 11016.61 lbs


Length of
In slabs, beams, columns etc. No Bar # wt (lb/rft) Quantity (lbs)
bars

Level - 1

20 29.17 3 0.376 219.33


Columns - C1
20 28.4543 6 1.502 854.77

8 29.17 3 0.376 87.73

Columns - C2 8 24 4 0.668 128.26

8 24 6 1.502 288.38

3 29.17 3 0.376 32.90


Columns - C3
3 24 6 1.502 108.14

Level - 2

20 47.83 3 0.376 359.71


Columns - C1
20 40 6 1.502 1201.60

8 29.17 3 0.376 87.73

Columns - C2 8 40 4 0.668 213.76

8 40 6 1.502 480.64

3 34.17 3 0.376 38.54


Columns - C3
3 40 6 1.502 180.24

14
1 2876.50 3 0.376 1081.56
Bond beam (BB1)
1 2440 6 1.502 3664.88

1 401 3 0.376 150.78


Bond beam (BB2)
1 400 6 1.502 600.80

1 415.642857 3 0.376 156.28


Bond beam (BB3)
1 352 6 1.502 528.70

Column dowel 1 530 6 1.502 796.06

Projetions 994.70

S.Total: 12255.50 lbs

Wastage @ 5% 1 1163.61 1163.61 lbs

S.Total: 1163.61 lbs

24435.72 lbs
Total (7):
11.09 tonne

8. Filling and compacting of earth under floors

No Length (ft) Width (ft) Depth (ft) Quantity (cft)

Under floor 1 3487 1.50 5230.50

5230.50 cft
Total (8):
148.13 m3

9. Sand Cushion Under floor (4" thick)

No Length (ft) Width (ft) Depth (ft) Quantity (cft)

Under floor 1 3487 0.33 1162.33

1162.33 cft
Total (9):
32.92 m3

10. Brick Ballast under floors (4" thick)

No Length (ft) Width (ft) Depth (ft) Quantity (cft)

Under floor 1 3487 0.33 1162.33

1162.33 cft
Total (10):
32.92 m3

15
11. PCC (1:4:8) under floor 4" thick

No Length (ft) Width (ft) Depth (ft) Quantity (cft)

Under floor 1 3487 0.33 1162.33

1162.33 cft
Total (11):
32.92 m3

12. PCC (1:2:4) under floor 4" thick

No Length (ft) Width (ft) Depth (ft) Quantity (cft)

Under floor 1 3487 0.17 581.17

581.17 cft
Total (12):
16.46 m3
13. Marble Flooring

No Length (ft) Width (ft) Quantity (sft)

Under floor 1 3395 3395.00

S.Total: 3395.00 sft

Front steps No Length (ft) Width (ft) Quantity (sft)

Treads 3 115 1.08 372.60

Risers 4 115 0.46 211.60

Sides of steps 2 1 2 4.00

S.Total: 588.20 sft

3983.20 sft
Total (13):
370.19 m2

14. PCC (1:2:4) filling in doors/windows frames

Ground Floor No Length (ft) Depth (ft) Width (ft) Quantity (cft)

D1 8 18 0.25 0.75 27.00

D2 2 23.5 0.25 0.75 8.81

D3 2 35 0.25 0.75 13.13

D4 2 22.5 0.25 0.75 8.44

W1 16 24 0.25 0.75 72.00

16
Ventilators 2 10 0.25 0.75 3.75

133.13 cft
Total (14):
3.77 m3

15. Plaster in CS mortar (1:4) 1/2 " thick

Sides No. Length (ft) Height (ft) Quantity (sft)

External walls 9" thick 2 1 0 10.00 0

Internal walls 9" thick 2 1 380 10.00 7600

Above bond beam 0 1 380.00 1.75 0

Internal walls 4.5" thick 0 1 0 10.00 0

Wall b/w NSL & Plinth level 1 315 0.75 2 472.5

S.Total: 8073 sft

Columns & beams Sides No. Length (ft) Height (ft) Quantity (sft)

Columns 4 32 1 16 2048.00

Beams 1 1 510 4.00 2040.00

Projections 1 1 280.00 2 560.00

S.Total: 4648.00 sft

Parapet wall Sides No. Length (ft) Width (ft) Quantity (sft)

1 1 310 6.75 2092.50

S.Total: 2092.50 sft

Front steps Sides No. Length (ft) Width (ft) Quantity (sft)

Threads 1 3 115 1.00 452.00

Risers 1 4 115 0.5 339.00

S.Total: 791.00 sft

Drain Sides No. Length (ft) Width (ft) Quantity (sft)

1 1 210 3.5 735.00

S.Total: 735.00 sft

Deductions Sides No. Length (ft) Height (ft) Quantity (sft)

D1 2 8 4 10 640

17
D2 2 2 3.5 10 140

D3 2 2 2.5 7 70

D4 2 2 2.5 7 70

W1 2 16 6 6 1152

Ventilators 2 2 3 2 24

S.Total: 2096.00 sft

14243.00 sft
Total (15):
1323.70 m2
16. Painting of new surfaces

Sides No. Length (ft) Height (ft) Quantity (sft)

External walls 9" thick 1 1 0 10 0

Internal walls 9" thick 2 1 380 10 7600

Internal walls 4.5" thick 2 1 20 10 400

S.Total: 8000 sft

Columns, beams, projections etc Sides No. Length (ft) Height (ft) Quantity (sft)

Columns 4 32 1 10 1280.00

Beams 1 1 510 4 2040.00

Projections 1 145 2.00 1 290.00

S.Total: 3610.00 sft

Deductions Sides No. Length (ft) Height (ft) Quantity (sft)

D1 2 8 4 10 640

D2 2 2 3.5 10 140

D3 2 2 2.5 7 70

D4 2 2 2.5 7 70

W1 2 16 6 6 1152

Ventilators 2 2 3 2 24

S.Total: 2096.00 sft

9514.00 sft
Total (16):

18
Total (16):
884.20 m2

17. P/F wooden Doors

No. Width (ft) Height (ft) Quantity (sft)

D1 8 4 10 320

D2 2 3.5 10 70

D3 2 2.5 7 35

D4 2 2.5 7 35

460.00 sft
Total (17):
42.75 m2

18. P/F Aluminium Windows with wire guaze

No. Width (ft) Height (ft) Quantity (sft)

Windows 16 6 6 576

Ventilators 2 3 2 12

588.00 sft
Total (18):
54.65 m2

19. P/F Steel Windows Grill

No. Width (ft) Height (ft) Quantity (sft)

Windows 16 6 6 576

Ventilators 2 3 2 12

588.00 sft
Total (19):
54.65 m2

20. Painting of doors

Sides No. Width (ft) Height (ft) Quantity (sft)

D1 2 8 4 10 640

D2 2 2 3.5 10 140

D3 2 2 2.5 7 70

D4 2 2 2.5 7 70

920.00 sft
Total (20):

19
Total (20):
85.50 m2

20
21. 1/2" thick marble skirting

No. Length (ft) Height (ft) Quantity (sft)

Science Lab 1 100 0.50 50.00

Computer Lab 1 100 0.50 50.00

Office 2 45 0.50 45.00

Store 2 33 0.50 33.00

Verandah 12 ft 1 36 0.50 18.00

Verandah 9 ft 2 33 0.50 33.00

S.Total: 229.00 sft

Deductions No. Length (ft) Height (ft) Quantity (sft)

D1 8 4 0.50 16.00

D2 2 3.5 0.50 3.50

D3 2 2.5 0.50 2.50

D4 2 2.5 0.50 2.50

S.Total: 24.50 sft

204.50 sft
Total (21):
19.01 m2

22. Single Layers of tiles 10"x5"x1.25" laid over 4" earth and 1" mud plaster on roof

Length (ft) Width (ft) Quantity (sft)

3487

3487
Total (22):
324.07 m2

23. P/L of polythene sheet on roof

Length (ft) Width (ft) Quantity (sft)

Roof 3487

3487.00 sft
Total (23):
324.07 m2

21
24. PCC 1:2:4 on roof

Length (ft) Width (ft) Quantity (cft)

Roof 3487 0.17 581.17

581.17 cft
Total (24):
16.46 m3
25. P/L of Jumbolon on roof

Length (ft) Width (ft) Quantity (sft)

Roof 3487

3487.00 sft
Total (25):
324.07 m2
26. Making Khurras on roof 2' x 2' x 6"

Total (26): 7 Nos


27. Bottom Khurass of brick masonry in Cement Mortar (1:6) 4' x 2' x 4.5"

Total (27): 7 Nos


28. Wire mesh

No Area (sft) Quantity (sft)

1 1462.00 sft 1462

1462.00 sft
Total (28):
135.87 m2
29. Providing and applying Graiato on exterior walls

External walls Sides No. Length (ft) Height (ft) Quantity (sft)

External walls 9" thick 1 1 205 10 2050.00

S.Total: 2050.00 sft

Deduction Sides No. Length (ft) Height (ft) Quantity (sft)

Windows 1 16 6 6 576.00

Ventilators 1 2 3 2 12.00

S.Total: 588.00 sft

1462.00 sft
Total (29):

22
Total (29):
135.87 m2

30. 2" thick DPC of PCC (1:2:4)

No. Length (ft) Width (ft) Quantity (sft)

Wall footing section - A 1 64 0.75 48.00

Wall footing section - B 1 20 0.375 7.50

55.50 sft
Total (30):
5.16 m2

31. Providing Pre-cast slab

No. Length (ft) Width (ft) Quantity (sft)

1 3487 3487.00

3487.00 sft
Total (31):
324.07 m2

32. Providing and fixing gypsum board false ceiling

No. Length (ft) Width (ft) Quantity (sft)

False ceiling 1 3487 3487.00

3487.00 sft
Total (32):
324.07 m2

33. Providing tuff tiles for plinth protection

No. Length (ft) Width (ft) Quantity (sft)

Tuff tiles 1 210 3 630.00

630.00 sft
Total (33):
58.55 m2

34. Providing ceramic tiles

No. Length (ft) Height (ft) Quantity (sft)

Toilet walls 1 57 5 285.00

Toilet floors 1 93 93.00

378.00 sft
Total (34):
35.13 m2

23
35. Spraying Anti-termite liquid in foundation.

No. Length (ft) Perimeter (ft) Quantity (sft)

Wall-A 1 64 9.5 608.00

Wall-B 1 20 5.5 110.00

Column footing -F1 11 4 20 880.00

Column footing -F2 7 4 24 672.00

Column footing -F3 7 4 28 784.00

Column footing -F4 4 4 32 512.00

Column footing -F5 3 4 20 240.00

3806.00 sft
Total (35):
353.72 m2

24
S. Amount
Description Unit Qty Rate (Rs.)
No. (Rs.)

Septic Tank (10 ft x 4 ft)


1 Filling, watering and ramming earth under m3 0.398 109.80 43.65
floor with surplus earth from foundation, etc

2 Excavation in foundation of building, bridges m3 22.688 557.69 12,652.97


etc complete :

3 Plain Cement Concrete incl. placing, m3 1.161 5,385.03 6,252.79


compacting, finishing & curing (Ratio 1:4:8)

4 Plain Cement Concrete incl. placing, m3 0.247 7,398.32 1,827.61


compacting, finishing & curing (Ratio 1:2:4)

5 RCC in roof slab, beam, column & other m3 0.733 11,187.12 8,197.87
structural members, insitu or precast

6 Supply & fabricate M.S. reinforcement for tonne 0.0396 120,459.13 4,767.65
cement concrete (Deformed bars)

7 Pacca brick work in foundation and plinth in m3 4.869 7,352.89 35,803.96


Cement, sand mortar 1:6

8 Supplying and filling sand under floor or m3 0.284 2,664.37 756.14


plugging in wells

9 Cement plaster 1:4 upto 20' height 1/2" thick m2 96.190 201.25 19,358.20

10 P&L RCC pipe, moulded with cement m 9.144 787.52 7,200.73


concrete 1:1.5:3, incl. cost of reinfcnt, testing
etc : 6"
11 Providing and fitting CI soil pipe with : Cement m 1.000 577.57 577.39
caulked joint : 2" dia

12 Providing 2" coping (1:2:4) m2 2.440 602.59 1,470.08

Total: 98,909

8
Estimation for Septic Tank (10 ft x 4 ft)
1. Excavation for Septic Tank

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Size: Internal (10 ft x 4 ft) 1 14.5 6.5 8.5 801.13

801.13 cft
Total (1):
22.69 m3

2. PCC (1:4:8) in foundation

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Long wall 2 12.75 0.5 2 25.5

Short wall 2 2.75 0.5 2 5.5

Base 1 10 0.25 4 10

41.00 cft
Total (2):
1.16 m3

3. Back filling of earth in base

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Base 1 8.75 0.583 2.75 14.04

14.04 cft
Total (3):
0.40 m3

4. Sand Filling under base

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Base 1 9.25 0.333 3.25 10.021

10.02 cft
Total (4):
0.28 m3

5. PCC (1:2:4) in base

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Base 1 9.625 0.25 3.625 8.723

8.72 cft
Total (5):
0.25 m3

24
6. RCC (1:2:4)

No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Top slab 12 0.333 6 24

Baffle wall 5 1.500 0.25 1.875

25.88 cft
Total (6):
0.73 m3

7. Steel in slab
Quantity
Spacing No. Length(ft) Wt. (lb/ft) (lbs)

Main steel #3@8"c/c 19 6 0.376 42.86

Distribution steel #3@12"c/c 7 12 0.376 31.58

Baffle wall 34 0.376 12.78

87.23 lbs
Total (7):
0.0396 tonne

8. BB work in CSM (1:6)

18 " thick wall No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Long wall 2 12.25 0.5 1.5 18.375

Short wall 2 3.25 0.5 1.5 4.875

S.Total: 23.25 cft

13.5 " thick wall No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Long wall 2 11.875 0.5 1.125 13.359

Short wall 2 3.625 0.5 1.125 4.078

S.Total: 17.44 cft

9 " thick wall No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Long wall 2 11.5 5 0.75 86.25

Short wall 2 4 5 0.75 30.00

S.Total: 116.25 cft

25
4.5" thick No Length (ft) Depth (ft) Width (ft) Quantity (cft)

Internal baffel walls 2 4 5 0.375 15.00

S.Total: 15.00 cft

171.94 cft
Total (8):
4.87 m3

9. 2" Coping (1:2:4)

No Length (ft) Depth (ft) Width (Ft) Quantity (sft)

Long wall 2 11.5 0.75 17.25

Short wall 2 4 0.75 6

Baffle wall 2 4 0.375 3

26.3 sft
Total (9):
2.44 m2

10. Plaster in CS mortar (1:4) 1/2 " thick

Sides No Length(ft) Height(ft) Quantity (sft)

Long wall 2 8 10.75 5 860.00

Short wall 2 2 4.75 5 95.00

Baffle walls 2 2 4 5 80.00

1035.0 sft
Total (10):
96.19 m2

11. Providing and laying CI soil Pipe 2 " dia with cement caulked joint

3.3 ft
Total (11):
1.00 m

12. Providing and laying RCC 4" dia in septic tank

30.0 ft
Total (12):
9.14 m

26
S. No. Description Unit Qty Rate (Rs.) Amount (Rs.)

Soakage Pit (5 ft internal dia)


1 Excavate well in dry & dispose of soil within 50m In m3 4.622 411.52 1,902.26
hard strata like shingle : Upto 1.5 m depth

2 Excavate well in dry & dispose of soil within 50m In m3 2.735 426.28 1,165.95
hard strata like shingle :1.5 to 3 m depth

3 Excavate well in dry & dispose of soil within 50m In m3 6.577 444.41 2,922.99
hard strata like shingle : 3 to 4.5 m depth

4 Plain Cement Concrete incl. placing, compacting, m3 0.096 5,385.03 516.28


finishing & curing (Ratio 1:4:8)

5 Plain Cement Concrete incl. placing, compacting, m3 0.096 6,018.51 577.02


finishing & curing (Ratio 1:3:6)

6 RCC in roof slab, beam, column & other structural m3 0.313 11,187.12 3,502.64
members, insitu or precast. Type C (1:2:4)

7 Supply & fabricate M.S. reinforcement for cement tonne 0.016 120,459.13 1,927.35
concrete (Deformed bars)

8 Pacca brick work in foundation and plinth in m3 2.173 7,352.89 15,979.84


Cement, sand mortar 1:6

9 P&L RCC pipe, moulded with cement concrete m 4.572 787.52 3,600.37
1:1.5:3, incl. cost of reinfcnt, testing etc : 6"

10 P/L of bricks bats in Soakage pit m3 11.116 510.74 5,677.34

Total: 37,772

9
Estimate for Soakage pit (5 ft internal dia, 22 ft deep)
1. Excavation (Sinking) for Soakage pit
Dry Sinking ( up to 1.5 m) No Area (sft) Depth (ft) Quantity (cft)
6.5' dia 33.166 4.921 163.22
163.22 cft
Total:
4.62 m3
Dry Sinking (1.5 m - 3 m) No Area (sft) Depth (ft) Quantity (cft)
5' dia 19.625 4.921 96.58
96.58 cft
Total:
2.74 m3
Dry Sinking (3 m - 6.607 m) No Area (sft) Depth (ft) Quantity (cft)
5' dia 19.625 11.834 232.24
232.24 cft
Total:
6.58 m3
2. PCC (1:4:8)
No Length (ft) Depth (ft) Width (ft) Quantity (cft)
13.541 0.2500 3.385
3.39 cft
Total (2):
0.10 m3
3. RCC (1:2:4)
No Length (ft) Depth (ft) Width (ft) Quantity (cft)
Top slab 33.17 0.333 11.055
11.06 cft
Total (3):
0.31 m3
4. Steel in cover slab
Spacing No. Length Wt lb/ft
Steel #3@8"c/c B/W 0.376
35.26 lbs
Total (4):
0.016 tonne
5. BB work in CSM (1:6)
Height
(ft) Area (sft) Quantity (cft)
Walls 5.667 13.541 76.738
76.74 cft
Total (5):
2.17 m3
6. Coping 3" thick (1:3:6) over brickwork
Height
(ft) Area (sft) Quantity (cft)
0.25 13.541 3.385
3.39 cft
Total (6):

27
Total (6):
0.10 m3
7. P/L Brick bats filling in soakage pit (5 ft dia)
Height
(ft) Area (sft) Quantity (cft)
Walls 20 19.625 392.500
392.50 cft
Total (7):
11.12 m3
8. Providing and laying RCC 4" dia in Soakage pit
15.0 ft
Total (8):
4.57 m