ID Task Name Duration Start Finish July August September October November December January
6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
1 Construction of transitional bus terminal 180 days Mon 6/25/18 Sat 1/5/19
for Kandy Multimodal transpotation
terminal project at Bogambara in Kandy
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Thu 9/13/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
35 Dence graded aggregate base (Approx 12 days Wed 10/17/18 Sun 10/28/18
100mm )(Aggregate base course)
40 Construction of transitional bus terminal 166 days Mon 7/9/18 Sat 1/5/19
64 Structural work ground floor to first 14 days Fri 10/5/18 Thu 10/18/18
floor level
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Thu 9/13/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
67 piping for water supply and 10 days Thu 11/1/18 Sat 11/10/18
sewerage inside of the building
68 Conduiting and wiring electrical 10 days Thu 11/1/18 Sat 11/10/18
work
69 Conduiting and wiring for fire alarm 10 days Thu 11/1/18 Sat 11/10/18
and fire detection system
installation
70 Conduiting and wiring for CCTV 10 days Thu 11/1/18 Sat 11/10/18
system
71 Conduiting and wiring for public 10 days Thu 11/1/18 Sat 11/10/18
address system
72 Water supply,sewerage and waste 15 days Wed 12/12/18 Wed 12/26/18
water external works
73 Construction of septic tank,sockage 10 days Wed 12/12/18 Fri 12/21/18
pit and sump
74 Installation of sanitory fittings and 12 days Wed 12/12/18 Sun 12/23/18
accesaries
75 Installation of electrical fittings and 15 days Wed 12/12/18 Wed 12/26/18
D board
76 Installation of fire potection and 14 days Wed 12/12/18 Tue 12/25/18
detection system
77 Installation and fixing public address 13 days Wed 12/12/18 Mon 12/24/18
system and CCTV system
80 Water proofing bath room and roof 7 days Fri 11/23/18 Thu 11/29/18
slab
81 Plastering (external wall) 6 days Sat 12/8/18 Thu 12/13/18
82 Plinth plater 7 days Fri 12/14/18 Thu 12/20/18
83 Aluminium works 20 days Fri 12/14/18 Wed 1/2/19
84 Wall tiling bathroom area 12 days Sat 11/17/18 Wed 11/28/18
85 Floor tiling 13 days Thu 11/29/18 Tue 12/11/18
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Thu 9/13/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress