Академический Документы
Профессиональный Документы
Культура Документы
City of Rye v Public Serv. Mut. Ins. Co., 34 N.Y.2d 470 (1974)
315 N.E.2d 458, 358 N.Y.S.2d 391
grant summary judgment to them. Therefore, the Court of
Appeals has no power to grant the developers, respondents on
34 N.Y.2d 470, 315 N.E.2d 458, 358 N.Y.S.2d 391
the appeal, affirmative relief.
City of Rye, Appellant,
v.
Public Service Mutual Insurance City of Rye v. Public Serv. Mut. Ins. Co., 42 A D 2d 749,
Company et al., Respondents. affirmed.
City of Rye v Public Serv. Mut. Ins. Co., 34 N.Y.2d 470 (1974)
315 N.E.2d 458, 358 N.Y.S.2d 391
Frank H. Connelly for remaining respondents. I. The city has The developers, under a plan approved by the City
sustained no actual damage. Therefore unless the common- Planning Commission, had constructed six luxury co-
law bond can be enforced as an agreement to pay “liquidated operative apartment buildings and were to construct six
damages”, it cannot be enforced at all. (Weinstein & Sons more. In order to obtain certificates of occupancy for the six
v. City of New York, 264 App. Div. 398; Winkelman v. completed buildings the developers were required to post a
Winkelman, 208 App. Div. 68.) II. A bond, exacted by a bond with the city to ensure completion of the remaining six
municipality to enforce compliance with the law is a penalty buildings. By letter agreement with the city in the fall of 1967,
bond, and it is ultra vires unless some statute sanctions it. they agreed to post a $100,000 bond and to pay $200 per
Penalties cannot be recovered through private agreement. day for each day after April 1, 1971 that the six remaining
(Priebe & Sons v. United States, 332 U. S. 407; Lyman v. buildings were not completed, up to the aggregate amount
Perlmutter, 166 N. Y. 410.) III. Actual fiscal damage, if any, of the bond. More than 500 days have passed without the
can be recovered under a penalty bond. (City of New York additional buildings having been completed within the time
v. Brooklyn & Manhattan Ferry Co., 238 N. Y. 52; Gitlin v. limit. The city seeks to recover the entire $100,000 amount
Schneider, 42 Misc 2d 230; Weinstein & Sons v. City of New of the bond.
York, 264 App. Div. 398; Perma-Stone Bi County Corp. v.
Ackerman, 15 Misc 2d 640.) Concededly, no statute authorizes the city to exact a penalty
or forfeiture from the developers. If there were such a statute,
OPINION OF THE COURT the statutory penalty would undoubtedly be upheld (see,
e.g., Lyman v. Perlmutter, 166 N. Y. 410, 413-415; Clark
Chief Judge Breitel.
v. Barnard, 108 U. S. 436, 461; see, also, United States v.
In this action to recover on a surety bond given to secure Zerbey, 271 U. S. 332, 340, and cases cited). Hence, general
timely completion of some six buildings, the City of Rye, principles of contract law governing the enforceability of
as obligee under the bond, seeks to recover the face amount liquidated damage clauses should apply (cf. Priebe & Sons v.
of $100,000. The surety and the developers are defendants. United States, 332 U. S. 407, 411; see 5 Williston, Contracts
Special Term denied the city's motion for summary judgment, [3d ed.], § 775B, at p. 664). The sole issue, then, becomes
and a divided Appellate Division affirmed the denial. In whether the agreement exacted from the developers and the
his concurring opinion at the Appellate Division, *472 conditional bond supplied provide for a *473 penalty or for
Mr. Justice Shapiro reasoned that the bond was penal in liquidated damages. If the agreement provides for a penalty
nature and therefore not enforceable. The dissenters, in an or forfeiture without statutory authority, it is unenforceable.
opinion by Mr. Justice Hopkins, would have sustained the Where, however, damages flowing from a breach are difficult
city's contention that, as a governmental entity pursuing to ascertain, a provision fixing the damages in advance will
its governmental responsibilities, it had the power, without be upheld if the amount is a reasonable measure of the
violating any public policy, to exact a substantial bond to anticipated probable harm (Ward v. Hudson Riv. Bldg. Co.,
secure performance of obligations imposed on a developer by 125 N. Y. 230, 235; Restatement, Contracts, § 339; 5 Corbin,
the zoning ordinance and action taken under it. Contracts, §§ 1059, 1063). If, on the other hand, the amount
fixed is grossly disproportionate to the anticipated probable
The order of the Appellate Division denying plaintiff city's harm or if there were no anticipatable harm, the provision will
motion for summary judgment should be affirmed. The bond not be enforced.
of $100,000 posted by the developers with the city to ensure
completion of the remaining six “peripheral” buildings by a The harm which the city contends it would suffer by
date certain did not reflect a reasonable estimate of probable delay in construction is minimal, speculative, or simply not
monetary harm or damages to the city, but a penalty, and, in cognizable. The city urges that its inspectors and employees
the absence of statutory authority for the penal bond, may not will be required to devote more time to the project than
be recovered upon. anticipated because it has taken extra years to complete. It also
urges that it will lose tax revenues for the years the buildings
are not completed. It contends, too, that it is harmed by a
continuing violation of the height restrictions of its zoning
City of Rye v Public Serv. Mut. Ins. Co., 34 N.Y.2d 470 (1974)
315 N.E.2d 458, 358 N.Y.S.2d 391
There is no suggestion in this case that the developers' delay
ordinance. This is entailed because the 12 buildings in the
was purposeful. Apparently, the mortgage market “dried up”
entire complex vary in height between two and four stories;
the ordinance sets a maximum average height of 30 feet and the developers could not obtain additional financing for
the remaining six buildings in the time planned. (The court
for the complex; and the taller buildings, those higher than
is informed by the developers in their brief that, while this
the allowable average, were built first. Only after all of the
litigation has been pending, the remaining six buildings have
structures in the complex are built will the project comply
almost been completed.)
with the average height requirement of the ordinance.
End of Document © 2015 Thomson Reuters. No claim to original U.S. Government Works.