HOSPITAL BARU PEREMPUAN DAN KANAK-KANAK,
KG. KIULAP Page 1 of 6
(FASA 1 )
M & E CONTRACTOR
METHOD STATEMENT
FOR
INSTALLATION OF SWITCHBOARDS
AUTO ENGINEERING SDN BHD P299
Date: 04.04.2013
TABLE OF CONTENTS
1) Purpose
2) Scope of Works
3) Storage
4) Pre-installation
5) Installation
6) Reference Documents
7) Checklist
AUTO ENGINEERING SDN BHD P299
Date: 04.04.2013
1) PURPOSE
2) SCOPE OF WORKS
The procedure will define the method to be used to ensure that the Electrical
Panel Installation on site Assembly, connection and workmanship are
acceptable, correct, as per the Authorities requirements and specifications.
3) STORAGE
* Make sure the storage area is safe and protect with tarpaulin
4) PRE - INSTALLATION
* Ensure that the location where the panel is installed is accessible, clean and
free of debris
AUTO ENGINEERING SDN BHD P299
Date: 04.04.2013
5) INSTALLATIONS
All switchboards are approved type and as per the approved shop drawings.
The switchboards comply local authorities requirements.
Please make sure the floor standby switchboards sit on proper location
above the opening where all the cable can enter properly.
A name plate will be provided with manufacturer name, panel name, type
rating etc.
After terminating all cables arrange inspection with authority to test the
switchboards.
Test complete function test of MSB, insulation test, high voltage injection
test , earth fault and over current test, earth test will carried out in the
presence of Consultant / Authority's representative
After approval energy meter can be procured and installed to the switchboards
Mounting arrangements for the wall mounted switchboards are showing in the
shop drawings
No glanding work for pvc 1C cables. The opening knockout is protected with
rubber gaskets to avoid damage of cables.
Due to space constrains the DB are installed in layer top bottom arrangements
Trunking works will be provided in between the DBs to avoid many conduits
entering to the DBs.
All unwanted opening will be sealed after termination of cable to the DB.
All termination work using proper gland and lay with necessary earth tag
Before energisation make sure all connecting cables and terminations are
checked and tested.
6) REFERENCE DOCUMENTS
7) CHECKLIST
DBs are terminated properly during all cables with cable ties and separated
each phase and keep proper order in the switchboards