EXAMINATION, INSPECTION AND TEST PLAN

(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

PAGE (Página) 1 OF 7
DATE (FECHA): 9/16/2015 JOB (OT): 685-1
EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV: 0
(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)

PROCEDURE QC RESULTS AI Client


ACTIVITY FORM IP QC SIGN/DATE IP AI SIGN/DATE IP Client SIGN/DATE
No. (ACTIVIDAD) (PROCEDIMIENTO) (FORMATO) (RESULTADOS) (FIRMA FECHA) (FIRMA FECHA) (FIRMA FECHA)
ENGNEERING DOCUMENTS
1 CALCULATIONS REVIEW ASME SECC VIII R
2 DRAWINGS REVIEW ASME SECC VIII R
3 MATERIAL REQUISITION REVIEW PROC. INTERNO R
MATERIAL PROCUREMENT
1 PURCHASE ORDER REVIEW R
2 RECEIVING INSPECTION AND MTR REVIEW
2.1 PLATES ASME SECC II R
2.2 HEADS ASME SEC. VIII R
2.3 PIPE AND TUBES ASME SECC II R
2.4 FLANGES ASME B16.5 R
2.5 FITTINGS ASME B16.9 R
2.6 BOLTING ASME SECC II R
MATERIAL CONTROL
1 MARKING TRANSFER PROC. INTERNO
1.1 PLATES HP
1.2 PIPE HP

R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

PAGE (Página) 2 OF 7
DATE (FECHA): 9/16/2015 JOB (OT): 685-1

EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV: 0


(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)

PROCEDURE QC RESULTS AI Client


ACTIVITY FORM IP
No. (ACTIVIDAD) (PROCEDIMIENTO) (FORMATO) IP (RESULTADOS)
QC SIGN/DATE
(FIRMA FECHA)
IP AI SIGN/DATE
(FIRMA FECHA)
Client SIGN/DATE
(FIRMA FECHA)
FABRICATION CONTROL
1 DIMENSIONAL HEADS ASME B16.9 HP
2 FIT UP LEGS DRAWINGS HP

WELDING CONTROL
1 WPS AND PQR REVIEW ASME secc IX R
WELDERS/W.OPERATORS
2 ASME secc IX R
QUALIFICATION REVIEW
3 FITUP MAIN JOINTS (SEE PAGE 4) DRAWINGS HP
4 FITUP NOZZLES (SEE PAGE 5) DRAWINGS HP

R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

PAGE (Página) 3 OF 7
DATE (FECHA): 9/16/2015 JOB (OT): 685-1

EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV: 0


(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)
PROCEDURE QC RESULTS AI Client
ACTIVITY FORM IP
No. (ACTIVIDAD) (PROCEDIMIENTO) (FORMATO) IP (RESULTADOS)
QC SIGN/DATE
(FIRMA FECHA)
IP AI SIGN/DATE
(FIRMA FECHA)
Client SIGN/DATE
(FIRMA FECHA)
NDE
1 RT SPOT UW 11(b) VRCC-RT003 R2.6-F09 R

FINAL INSPECTION
1 INTERNAL INSPECTION ASME secc. VIII R2.6-F29 HP
2 EXTERNAL INSPECTION ASME secc. VIII R2.6-F29 HP
TEST
1 HYDROSTATIC TEST 65 PSI R2.6-I08 R2.6-F39 HP
CERTIFICATION
1 NCR CLOSED QUALITY MANUAL R2.6-F11 R
2 "US BUILT DIMENSION" DRAWINGS R
3 DOSSIER QUALITY MANUAL R

R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

PAGE (P
DATE (FECHA): 9/16/2015 JOB (OT

EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01


(EQUIPO) (PLANOS)

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)

Bevel Prepair Examination Fit up & Tack welds VE NDE ✘ RT

JOINT
I.P. QC

I.P. QC
I.P. AI

I.P. AI
Examination Inspection Inspection Examination Inspection Inspection Examination
Results Results Results Results Results Results Results

C1
cuerpo a H H
cabeza

C2 tapa H H
a cuerpo

MAIN JOINT CHECK LIST


STEP DESCRIPTION
1 VE BORDES PARA SOLDAR S/UG-93 (d)(1), UG-95
2 GRADOS DE LOS BISELES S/PLANO & TOLERANCIAS
3 LUZ DE PENETRACION S/PLANO & TOLERANCIAS
4 CHEQUEAR ALINEAMIENTO S/UW-33
5 VE PUNTOS DE ARMADO S/UW-31( c )
6 CHEQUEO DE LIMPIEZA ZONAS A SOLDAR UW-32(a)

R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUA
PAGE (Página) 4 OF 7
JOB (OT): 685-1

T-041-0685-01-01 REV: 0
REV:

EDICION 2013

RT
✘ RT FULL
SPOT
I.P. QC Inspect. Inspect. Report

I.P. AI
Results Results No.

H
R= REVIEW (REVISIÓN)

H.P.=HOLD POINT (PUNTO DE ESPERA)

W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)


EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

PAGE (Página) 5 OF 7
DATE (FECHA): 9/16/2015 JOB (OT): 685-1
EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV: 0
(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)
RT
Fit up & Tack welds VE Flange to neck Fit up & Tack welds VE Nozzle to shell/head NDE/TEST UT ✘ PT MT ✘ PLT
Examinat. Inspect. Inspect. Report
NOZZLE Examination
I.P. QC

I.P. QC

I.P. QC

I.P. AI
I.P. AI

I.P. AI
Inspection Inspection Examination Inspection Inspection
Results Results Results Results Results Results
Results Results Results No.
A HP HP
B HP HP
C HP
D HP
E HP
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)
EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

WELDING MAP (MAPA DE SOLDADURAS) PAGE (Página)


DATE (FECHA): 9/16/2015 JOB (OT):

EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV:


(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO
PAGE (Página) 6 OF 7
685-1

0
R= REVIEW (REVISIÓN)

H.P.=HOLD POINT (PUNTO DE ESPERA)

W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)


EXAMINATION, INSPECTION AND TEST PLAN
(PLAN DE EXAMINACIONES , INSPECCIONES Y PRUEBAS)

MATERIAL MAP (MAPA DE MATERIALES) PAGE (Página)


DATE (FECHA): 9/16/2015 JOB (OT):

EQUIPMENT: FILTRO DE GAS DRAWINGS: T-041-0685-01-01 REV:


(EQUIPO) (PLANOS) REV:

REVIEW BY A.I. N.A. Date


(Revisado por I.A.) (Fecha)
ED./ ADD.
CODE: ASME SEC. VIII DIVISION 1 (ED. / ADD.) EDICION 2013
(CODIGO)
R= REVIEW (REVISIÓN)
PREPARED BY: DATE: APPROVED BY: DATE:
H.P.=HOLD POINT (PUNTO DE ESPERA)
(PREPARADO POR:) (FECHA) (APROBADO POR:) (FECHA)
W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO
PAGE (Página) 7 OF 7
685-1

0
R= REVIEW (REVISIÓN)

H.P.=HOLD POINT (PUNTO DE ESPERA)

W= WITNESS POINT (PUNTO DE ATESTIGUAMIIENTO)