Академический Документы
Профессиональный Документы
Культура Документы
0.0 Introduction
Beginning in 1992, a total of 16 PVP systems have been installed (under the international PVP
programme) in remote settlements in four provinces of Zimbabwe and they provide clean
drinking water to an estimated 20 000 people as well as their livestock. The current PVP
project is targeted at providing clean drinking water to remote rural settlements which are far
away from the electricity grid. These include rural health centres, schools, business centres,
police posts, villages and so on. Quite often these settlements are difficult to approach due to
poor roads as well as long distances, hence the logistics of running diesel powered systems are
very difficult and costly. The PVP programme therefore has well laid down criteria for
selecting a site for equipping with PVP. The PVP systems under the current programme have
performed very well and the right technological environment has been established for the
further dissemination of PVP. Table 1 in appendix A1 summarises the characteristics of the
PVP systems in Zimbabwe.
1.0 History of PV Pumping
PV pumping systems, mainly financed by various donors were introduced into the country as
early as 1982. These were characterised by a whole plethora of system design, configuration
and component type. The most dominant system configuration however consisted of a PV
module generator, a large wet cell battery bank, control electronics such as a time switch or
charge regulator and a mono pump driven by a surface DC motor.
A survey carried out in the first half of 1994 to determine the status of these early PVP pumps
established that of 23 sites visited less than half of the systems were found to be defunct due to
system component failure, lack of proper maintenance, poor management and theft of modules.
The highest percentage of component failure resulted from (i) the storage batteries which in
most cases were inappropriate for the deep discharge cycles associated with solar energy
applications and (ii) the electronic control components which were untested and of poor
quality. Coupled to this inappropriate as well as immature technology, the PV technological
environment of this period was fraught with inadequacies in terms of local expertise,
equipment and spares to match the variety of system components on the field. It is interesting
to note that even at this early stage, the market did offer tested and mature system
configurations such as the one which was installed at Bengale in 1984 and is still in operation
to this day.
Ownership and operational responsibility for the majority of the early PVP systems was
unclear. Although after the installation was completed the donor did hand over the system to
the benefiting community, no prior preparation or training of these communities was offered.
Hence structures such as water committees which are vital for the local management and
operation of the PV pump were lacking and this often led to conflicts between various
categories of the community, such as between the clinic nurses and the people from the village.
Moreover, the target communities were ill equipped to perform some of the management tasks
such as specialised repair and maintenance of their PV system. They also lacked the financial
resources to secure the services of the private sector. Rural District Councils were often the
only recourse for the communities that found themselves facing problems with their PV
pumping systems, but unfortunately RDCs' limited budgets and weak manpower base rendered
them ineffective to help. Systems that remained defunct and idle became targets of theft and
vandalism.
With the realisation that PVPs are a niche technology, sites were chosen following clearly laid
down criteria. Firstly a site would be chosen if there was a demonstrated need for drinking
water for humans.
2
WATER UNIT COST(Z$/m^3) FOR
PUMPING SYSTEMS (20m head; 13
10
8
6
4
2
0
Grid
Grid
Diesel
ic
(5km)
(0km)
Pho
Fig.1
Remote sites where fuel deliveries would pose serious logistical problems due to poor roads
and long distances received preference. As a rule of thumb, sites at least 15km away from the
electricity grid were chosen.
3
sector decision makers, academics, and water supply authorities is another key function of
DOE and GTZ in the project. The project partners jointly provide financial sponsorship
4
4.1 The PV Module
The photovoltaic (PV) module consists of 40 cells of crystalline silicon encapsulated in
tempered glass. As each module cannot produce sufficient power for the pump, the modules
are connected together both in parallel and in series to produce the required current and
voltage. The interface requirements of the inverter are taken into consideration during the
design of the PV generator.
The modules are mounted on a support structure which is firmly secured to a concrete
foundation, fixed at a tilt angle, oriented to the north and allows maximum ventilation of the
modules.
The use of temper-proof bolts for mounting the modules onto the support is a measure
towards theft prevention. Much more work is required in this area.
Cables are sized adequately to reduce energy losses and switches that are rated for DC
operation are used.
Using 1994 prices, a system designed to pump 35m3 per day through a head of 28m cost
Z$210 000. Compared to a diesel pumping system, this is a very high investment cost. A study
commissioned by the PVP project however shows that for such a system size, the PVP option
works out to be the least cost in the long term if economic consideration are taken into
account.
The project emphasises the concept of quality of both the equipment supplied as well as
workmanship during installation. To this end the modules used undergo rigorous tests and
confirm to the German TÜV standard. A warranty period of 10 years for the modules and two
years for maintenance forms part of the contract with the supplier. After installation, an
acceptance test is performed to determine to what extent the system performance agrees with
5
specifications jointly laid down by the project sponsors and the equipment supplier.
Performance characteristics are summarised in the H-Q-f, P-Q-f and P-Q-H curves provided by
the supplier where:
f is the inverter frequency
H is the pumping head
P is the DC power generated and
Q is the water flow rate per hour
The diagram below summarises the input-output analysis of the system which is performed
during the acceptance testing procedure.
Besides the input-output analysis, the physical layout of the whole system is also examined for
quality, that is the suitability of the module mounting frame in terms of tilt angle, orientation
and protection against corrosion, generator wiring, lightning protection measures and piping.
unwilling to pa
24.24%
willing to pay 62.63
Fig.4
6
The majority of potential consumers appreciated the convenience of a clean water supply close
to their homes, hence they were willing to pay for the service. About 13% of those interviewed
indicated that they would be prepared to pay, if the water point was brought to within half a
kilometer or so from their homes. The post-installation monitoring exercise has shown that in
fact the majority of consumers are paying for their consumption.
A number of measures were taken to ensure the sustainability of the project both at present as
well as in the long term.
Mounting (10%)
PV Modules (39.4%)
Fig.5
7
The first four PVP systems installed in Zaka District in 1992 comprised about 87% foreign
content. Subsequent systems were installed using riser main piping, well head fittings, module
mounting structures which were sourced locally. Combined with local transport and labour,
this substitution constituted 36.3% of the total system cost. Locally assembled modules have
been used at one installation but it is too early to make performance comparisons with the
imported product.
8
CHANGES IN HOUSEHOLD WATER CONSUM
BEFORE PVP (
per day)
Fig.6
The existence of a favourable environment, in terms of the capacity within industry, for the
further dissemination of PVP should see the expanded adoption of this option by the water
authorities to equip their new water supply stations. DWD develops an average of 50 borehole
water supply stations country wide per year and up to 80% of these fall in the range where
PVP is more attractive compared to other pumping options as shown in figure 7 below. If PV
pumps are also used to upgrade old water supply stations, then the potential is even greater.
The major constraint that the water authority faces is the high investment cost that is required
upfront. One funding mechanism which is worth considering is where the DWD puts forward
what it would cost to equip a borehole with a diesel pumping system and a donor tops up the
difference of what an equivalent PVP system costs.
9
Cost Comparison of Pumping Systems
20/13
0.50
30/18
0.40 40/20
50/21 Break even point
0.30 60/22
0.20 40/40 40/58
60/66 90/61
0.10 50/46
0.00
0 1,000 2,000 3,000 4,000 5,000 6,000
System Size-Hydraulic Energy Equivalent [m^4/d]
Fig.7
APPENDIX A1
SYSTEM CHARACTERISTICS
ZAKA DISTRICT
PVP station Chiredzana Chinyabako Zinguwo Veza
Date of October October October 1992 October
commissioning 1992 1992 1992
PV generator 1.4 1.4 1.8 1.8
capacity/kWp
Number of 28 28 36 36
modules
Discharge head/m 50 40 70 36
Water pumped per 16.6 19.8 14.2 28.8
day/m3
Water storage/m3 69 48 60 148
Total volume 9767 9200 8057 13632
delivered 12/94
GOKWE DISTRICT
PVP station Mateta II Mutange Nyarupakwe Lutope Sengwa Chirisa
Date of commissioning March 1994 March 1994 March 1994 March May 1994 August 1994
1994
PV generator 1.6 1.6 1.6 1.6 1.6 3.5
capacity/kWp
Number of modules 32 32 32 32 70
Module Type PQ40D PQ40D PQ40D PQ40D SP47 PQ40D
Inverter Type SA1500 SA1500 SA1500 SA1500 SA1500 Solarveter 3
Pump Type SP 3A-10 SP 3A-10 SP 3A-10 SP 3A-10 SP 3A-10 KSB UPA
100-4/19
Discharge head/m 26 52 35 35 28 68
Water pumped per 20 21 30 21 35 30
day/m3
Water storage/m3 90 70 90 45 90 90
Total volume 5976 4671 5500 5991 3203 3932
delivered 12/94
11