Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.

BANYAN GROVE PROGRAMME OF WORKS


ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
1 Programme of Work Banyan Grove 410.51 days Mon 03/08/15 Mon 22/05/17
2 Mobilization 15 days Mon 07/09/15 Tue 29/09/15
3 Client to handover site 0 days Mon 07/09/15 Mon 07/09/15
4 Mobilization & Site Establishment 15 days Mon 07/09/15 Tue 29/09/15
5 Clear site 10 days Wed 09/09/15 Thu 24/09/15
6 Construction Works 394 days Mon 03/08/15 Wed 26/04/17
7 Bulk Earthworks 30 days Wed 16/09/15 Fri 30/10/15
8 Basement excavation 30 days Wed 16/09/15 Fri 30/10/15
9 Completion of basement excavation 0 days Fri 30/10/15 Fri 30/10/15
10 Common Basement (AB, CD, GH) 134 days Mon 03/08/15 Mon 14/03/16
11 Setting out 10 days Thu 01/10/15 Fri 16/10/15
12 Excavate for footing/bases/lift pits/sumps 10 days Thu 01/10/15 Fri 16/10/15
13 Lay c/run layer and compact 15 days Mon 12/10/15 Wed 04/11/15
14 Blinding 1st layer 12 days Fri 16/10/15 Wed 04/11/15
15 Appointment of Waterproofing contractor 0 days Mon 03/08/15 Mon 03/08/15
16 Tanking membrane 12 days Tue 20/10/15 Fri 06/11/15
17 Blinding 2nd layer 12 days Thu 22/10/15 Tue 10/11/15
18 Appointment of MEPD Subcontractor 0 days Fri 28/08/15 Fri 28/08/15
19 Appointment of Lift Supplier 0 days Mon 14/09/15 Mon 14/09/15
20 FRC basement floor slab inc MEPD sleeves 30 days Wed 28/10/15 Mon 14/12/15
21 Completion of basement floor slab (Milestone 4 Months 31/12/15) 0 days Mon 14/12/15 Mon 14/12/15
22 FRC columns 30 days Fri 13/11/15 Fri 15/01/16
23 FRC walls (common basement) 40 days Fri 13/11/15 Tue 02/02/16
24 Completion of basement retaining walls 0 days Tue 02/02/16 Tue 02/02/16
25 Tanking membrane to wall and protective blockwork 25 days Tue 02/02/16 Mon 14/03/16
26 Completion of common basement 0 days Mon 14/03/16 Mon 14/03/16
27 Block AB 356.86 days Tue 01/09/15 Mon 03/04/17
28 Structure 190 days Wed 18/11/15 Fri 16/09/16
29 Ground Floor Slab 47 days Wed 25/11/15 Fri 26/02/16
30 FRC beams 20 days Wed 25/11/15 Wed 13/01/16
31 FRC basement slab(GF) inc MEPD conduits 25 days Thu 03/12/15 Thu 28/01/16
32 Completion of basement slab AB (GF) 0 days Thu 28/01/16 Thu 28/01/16
33 Deformwork 5 days Thu 18/02/16 Fri 26/02/16
34 Superstructure 190 days Wed 18/11/15 Fri 16/09/16
35 Ground to 1st 59 days Tue 19/01/16 Thu 21/04/16
36 Setting out 7 days Tue 19/01/16 Fri 29/01/16
37 Blockwork 25 days Wed 20/01/16 Wed 02/03/16
38 Commencement of AB Blockwork 0 days Wed 20/01/16 Wed 20/01/16
39 Erect tower crane 0 days Thu 28/01/16 Thu 28/01/16
40 FRC columns 15 days Mon 08/02/16 Wed 02/03/16
41 FRC beams 20 days Thu 11/02/16 Tue 15/03/16
42 FRC 1st Floor slab inc MEPD conduits 25 days Mon 22/02/16 Wed 30/03/16
43 Completion of AB 1st floor slab 0 days Wed 30/03/16 Wed 30/03/16
44 Deformwork 5 days Wed 13/04/16 Thu 21/04/16
45 1st to 2nd 140 days Wed 18/11/15 Wed 06/07/16
46 Setting out 5 days Fri 15/04/16 Mon 25/04/16
47 Blockwork 25 days Fri 15/04/16 Mon 23/05/16
48 FRC columns 15 days Mon 02/05/16 Mon 23/05/16
49 FRC beams 20 days Wed 04/05/16 Thu 02/06/16
50 Appointment of Pool & Water Feature Equipment Supplier 0 days Wed 18/11/15 Wed 18/11/15
51 FRC 2nd floor slab inc MEPD conduits 25 days Mon 09/05/16 Tue 14/06/16
52 Completion of AB SF slab 0 days Tue 14/06/16 Tue 14/06/16
53 Deformwork 5 days Tue 28/06/16 Wed 06/07/16
54 2nd to Roof 53 days Thu 30/06/16 Fri 16/09/16
55 Setting out 5 days Thu 30/06/16 Fri 08/07/16
56 Blockwork 18 days Fri 01/07/16 Fri 29/07/16
57 FRC columns 12 days Tue 12/07/16 Fri 29/07/16
58 FRC beams 20 days Thu 14/07/16 Mon 15/08/16
59 FRC roof slab inc MEPD conduits 24 days Fri 22/07/16 Fri 26/08/16
60 Completion of AB Roof slab (Milestone Structure complete 31/08/16)0 days Fri 26/08/16 Fri 26/08/16
61 Dismantle tower crane and remove from site 0 days Fri 26/08/16 Fri 26/08/16
62 Deformwork 5 days Fri 09/09/16 Fri 16/09/16
63 Parapet walls & 2nd floor pools Block AB 15 days Fri 19/08/16 Fri 09/09/16
64 Wet Trades 158 days Thu 21/04/16 Tue 13/12/16
65 Internally 154 days Thu 21/04/16 Tue 06/12/16
66 Basement 60 days Fri 26/08/16 Fri 25/11/16
67 Basement block and wet works 40 days Fri 26/08/16 Mon 24/10/16
68 Render common stairs 20 days Mon 24/10/16 Fri 25/11/16
69 Ground Floor 55 days Thu 21/04/16 Mon 11/07/16
70 Partition block wall & risers 12 days Thu 21/04/16 Mon 09/05/16
71 M&E 1st & 2nd fix 15 days Fri 22/04/16 Fri 13/05/16
72 Preplaster Check 10 days Tue 03/05/16 Tue 17/05/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

1
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
73 Render wall & ceilings internal 25 days Thu 05/05/16 Fri 10/06/16
74 Suspended ceiling grid work 10 days Wed 01/06/16 Wed 15/06/16
75 Floor & wall tiles 25 days Fri 03/06/16 Mon 11/07/16
76 Completion of GF Floor wet trades 0 days Mon 11/07/16 Mon 11/07/16
77 1st Floor 55 days Wed 06/07/16 Mon 26/09/16
78 Partition block wall & risers 12 days Wed 06/07/16 Mon 25/07/16
79 M&E 1st & 2nd fix 15 days Thu 07/07/16 Fri 29/07/16
80 Preplaster Check 10 days Tue 19/07/16 Tue 02/08/16
81 Render wall & ceilings internal 25 days Thu 21/07/16 Fri 26/08/16
82 Suspended ceiling grid work 10 days Wed 17/08/16 Wed 31/08/16
83 Floor & wall tiles 25 days Fri 19/08/16 Mon 26/09/16
84 Completion of 1st Floor wet trades 0 days Mon 26/09/16 Mon 26/09/16
85 2nd Floor 52 days Fri 16/09/16 Tue 06/12/16
86 Partition block wall & risers 12 days Fri 16/09/16 Wed 05/10/16
87 M&E 1st & 2nd fix 12 days Mon 19/09/16 Thu 06/10/16
88 Preplaster Check 10 days Mon 26/09/16 Mon 10/10/16
89 Render wall & ceilings internal 25 days Wed 28/09/16 Mon 07/11/16
90 Suspended ceiling grid work 10 days Mon 24/10/16 Thu 10/11/16
91 Floor & wall tiles 25 days Wed 26/10/16 Tue 06/12/16
92 Completion of 2nd Floor wet trades 0 days Tue 06/12/16 Tue 06/12/16
93 Externally (Block AB) 65 days Mon 05/09/16 Tue 13/12/16
94 Plaster parapet wall on roof 10 days Mon 05/09/16 Mon 19/09/16
95 Plaster front façade 25 days Tue 13/09/16 Wed 19/10/16
96 Plaster side façade 20 days Tue 11/10/16 Mon 14/11/16
97 Plaster rear facades 25 days Fri 04/11/16 Tue 13/12/16
98 Builders work in connection with services on roof & Screed 20 days Wed 07/09/16 Thu 06/10/16
99 Complete Plaster External facades 0 days Tue 13/12/16 Tue 13/12/16
100 Finishes 356.86 days Tue 01/09/15 Mon 03/04/17
101 Internally 356.86 days Tue 01/09/15 Mon 03/04/17
102 Basement 80 days Thu 10/11/16 Mon 03/04/17
103 Finishes 30 days Thu 10/11/16 Fri 13/01/17
104 Make good to basement floor 20 days Thu 02/03/17 Mon 03/04/17
105 Ground Floor 324.86 days Tue 01/09/15 Mon 13/02/17
106 Finishes Internal 261.86 days Tue 01/09/15 Mon 17/10/16
107 Commencement of Block AB GF Finishes 0 days Tue 01/09/15 Tue 01/09/15
108 Paint 1st coat 8 days Fri 24/06/16 Thu 07/07/16
109 Aluminium openings 12 days Wed 29/06/16 Tue 19/07/16
110 Suspended Ceilings 12 days Tue 12/07/16 Fri 29/07/16
111 Shopfitting installation incl all 15 days Fri 22/07/16 Mon 15/08/16
112 Kitchen fit outs 15 days Wed 10/08/16 Thu 01/09/16
113 Granite tops 12 days Thu 25/08/16 Mon 12/09/16
114 Sanitary wares & accessories 10 days Wed 07/09/16 Thu 22/09/16
115 Electrical accessories & light fittings 10 days Mon 12/09/16 Tue 27/09/16
116 TEL/DATA/MATV installation 7 days Mon 19/09/16 Thu 29/09/16
117 Shower screens 5 days Thu 22/09/16 Thu 29/09/16
118 Snag/De-snag 7 days Thu 29/09/16 Mon 10/10/16
119 Paint final coat 7 days Thu 06/10/16 Mon 17/10/16
120 Complete Block AB GF internal 0 days Mon 17/10/16 Mon 17/10/16
121 Terraces Ground Floor 35 days Wed 30/11/16 Mon 13/02/17
122 Paint 1st & 2nd coat 10 days Wed 30/11/16 Thu 15/12/16
123 Waterproofing to terraces 15 days Fri 02/12/16 Fri 13/01/17
124 Terrace tiling 15 days Wed 14/12/16 Tue 24/01/17
125 Timber screens & cladding 10 days Tue 10/01/17 Tue 24/01/17
126 Balustrades 10 days Thu 12/01/17 Thu 26/01/17
127 Paint final coat 7 days Thu 19/01/17 Mon 30/01/17
128 Snag/De-snag 7 days Mon 30/01/17 Mon 13/02/17
129 Complete Block AB Terraces GF 0 days Mon 13/02/17 Mon 13/02/17
130 First Floor 96 days Fri 09/09/16 Fri 24/02/17
131 Finishes Internal 77 days Fri 09/09/16 Tue 24/01/17
132 Commencement of Block AB FF Finishes 0 days Thu 22/09/16 Thu 22/09/16
133 Paint 1st coat 8 days Fri 09/09/16 Thu 22/09/16
134 Aluminium openings 12 days Wed 14/09/16 Mon 03/10/16
135 Suspended Ceilings 12 days Tue 27/09/16 Thu 13/10/16
136 Shopfitting installation incl all 15 days Thu 06/10/16 Thu 27/10/16
137 Kitchen fit outs 15 days Tue 25/10/16 Mon 21/11/16
138 Granite tops 12 days Mon 14/11/16 Wed 30/11/16
139 Sanitary wares & accessories 10 days Fri 25/11/16 Fri 09/12/16
140 Electrical accessories & light fittings 10 days Wed 30/11/16 Thu 15/12/16
141 TEL/DATA/MATV installation 7 days Wed 07/12/16 Fri 06/01/17
142 Shower screens 5 days Fri 09/12/16 Fri 06/01/17
143 Snag/De-snag 7 days Fri 06/01/17 Tue 17/01/17
144 Paint final coat 7 days Fri 13/01/17 Tue 24/01/17
145 Complete Block AB FF internal 0 days Tue 24/01/17 Tue 24/01/17

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

2
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
146 Terraces First Floor 35 days Tue 13/12/16 Fri 24/02/17
147 Paint 1st & 2nd coat 10 days Tue 13/12/16 Mon 16/01/17
148 Waterproofing to terraces 15 days Thu 15/12/16 Wed 25/01/17
149 Terrace tiling 15 days Fri 13/01/17 Tue 07/02/17
150 Timber screens & cladding 10 days Tue 24/01/17 Thu 09/02/17
151 Balustrades 10 days Tue 24/01/17 Thu 09/02/17
152 Paint final coat 7 days Tue 31/01/17 Tue 14/02/17
153 Snag/De-snag 7 days Tue 14/02/17 Fri 24/02/17
154 Complete Block AB Terraces FF 0 days Fri 24/02/17 Fri 24/02/17
155 Second Floor 71 days Tue 22/11/16 Thu 30/03/17
156 Finishes Internal 71 days Tue 22/11/16 Thu 30/03/17
157 Commencement of Block AB SF Finishes 0 days Fri 02/12/16 Fri 02/12/16
158 Paint 1st coat 8 days Tue 22/11/16 Fri 02/12/16
159 Aluminium openings 12 days Fri 25/11/16 Wed 14/12/16
160 Suspended Ceilings 10 days Wed 07/12/16 Wed 11/01/17
161 Shopfitting installation incl all 14 days Thu 15/12/16 Tue 24/01/17
162 Kitchen fit outs 12 days Fri 20/01/17 Thu 09/02/17
163 Granite tops 12 days Tue 31/01/17 Wed 22/02/17
164 Sanitary wares & accessories 10 days Thu 16/02/17 Fri 03/03/17
165 Electrical accessories & light fittings 10 days Wed 22/02/17 Wed 08/03/17
166 TEL/DATA/MATV installation 7 days Wed 01/03/17 Fri 10/03/17
167 Shower screens 5 days Fri 03/03/17 Fri 10/03/17
168 Snag/De-snag 7 days Fri 10/03/17 Wed 22/03/17
169 Paint final coat 7 days Fri 17/03/17 Thu 30/03/17
170 Complete Block AB SF internal 0 days Thu 30/03/17 Thu 30/03/17
171 Terraces Second Floor 35 days Wed 11/01/17 Tue 07/03/17
172 Paint 1st & 2nd coat 10 days Wed 11/01/17 Wed 25/01/17
173 Waterproofing to terraces 15 days Fri 13/01/17 Tue 07/02/17
174 Terrace tiling & Pool tiling 15 days Tue 24/01/17 Mon 20/02/17
175 Timber screens & cladding 10 days Mon 06/02/17 Wed 22/02/17
176 Balustrades 10 days Mon 06/02/17 Wed 22/02/17
177 Paint final coat 7 days Tue 14/02/17 Fri 24/02/17
178 Snag/De-snag 7 days Fri 24/02/17 Tue 07/03/17
179 Complete Block AB Terraces SF 0 days Tue 07/03/17 Tue 07/03/17
180 Externally & Common areas 125 days Fri 29/07/16 Fri 24/02/17
181 Commencement of Block A & B Externally & Common areas 0 days Thu 06/10/16 Thu 06/10/16
182 Waterproofing on roof 12 days Thu 06/10/16 Mon 24/10/16
183 M & E Equipments on roof 20 days Mon 17/10/16 Fri 18/11/16
184 Paint 1st & 2nd coat 15 days Mon 28/11/16 Mon 09/01/17
185 Lifts installation including finishes 40 days Mon 17/10/16 Fri 06/01/17
186 Stone cladding 35 days Tue 13/12/16 Fri 24/02/17
187 Appointment of External Joinery 0 days Fri 29/07/16 Fri 29/07/16
188 Composite timber cladding, pergolas & gates 35 days Tue 13/12/16 Fri 24/02/17
189 Appointment of Balustrade Subcontractor 0 days Mon 19/09/16 Mon 19/09/16
190 Balustrades 20 days Tue 13/12/16 Mon 30/01/17
191 Tiling to main staircases and common areas 20 days Fri 06/01/17 Tue 07/02/17
192 Paint final coat 10 days Mon 24/10/16 Thu 10/11/16
193 Snag/De-snag 10 days Mon 09/01/17 Mon 23/01/17
194 Complete Block AB External Finishes & Common areas 0 days Fri 24/02/17 Fri 24/02/17
195 Block CD 299 days Tue 08/12/15 Wed 12/04/17
196 Structure 184 days Tue 08/12/15 Wed 28/09/16
197 Ground Floor Slab 46 days Tue 08/12/15 Wed 09/03/16
198 FRC beams 20 days Tue 08/12/15 Tue 26/01/16
199 FRC basement slab(GF) inc MEPD conduits 24 days Tue 15/12/15 Wed 10/02/16
200 Completion of basement slab CD (GF) 0 days Wed 10/02/16 Wed 10/02/16
201 Deformwork 5 days Tue 01/03/16 Wed 09/03/16
202 Superstructure 161 days Fri 29/01/16 Wed 28/09/16
203 Ground to 1st 59 days Fri 29/01/16 Mon 02/05/16
204 Setting out 7 days Fri 29/01/16 Thu 11/02/16
205 Blockwork 25 days Tue 02/02/16 Mon 14/03/16
206 Commencement of CD Blockwork 0 days Tue 02/02/16 Tue 02/02/16
207 Erect tower crane 0 days Wed 10/02/16 Wed 10/02/16
208 FRC columns 15 days Thu 18/02/16 Mon 14/03/16
209 FRC beams 20 days Wed 24/02/16 Fri 25/03/16
210 FRC 1st Floor slab inc MEPD conduits 25 days Wed 02/03/16 Fri 08/04/16
211 Completion of CD 1st floor slab 0 days Fri 08/04/16 Fri 08/04/16
212 Deformwork 5 days Mon 25/04/16 Mon 02/05/16
213 1st to 2nd 55 days Wed 27/04/16 Fri 15/07/16
214 Setting out 5 days Wed 27/04/16 Wed 04/05/16
215 Blockwork 25 days Wed 27/04/16 Thu 02/06/16
216 FRC columns 15 days Wed 11/05/16 Thu 02/06/16
217 FRC beams 20 days Fri 13/05/16 Mon 13/06/16
218 FRC 2nd floor slab inc MEPD conduits 25 days Wed 18/05/16 Thu 23/06/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

3
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
219 Completion of CD SF slab 0 days Thu 23/06/16 Thu 23/06/16
220 Deformwork 5 days Fri 08/07/16 Fri 15/07/16
221 2nd to Roof 53 days Tue 12/07/16 Wed 28/09/16
222 Setting out 5 days Tue 12/07/16 Wed 20/07/16
223 Blockwork 18 days Wed 13/07/16 Tue 09/08/16
224 FRC columns 12 days Fri 22/07/16 Tue 09/08/16
225 FRC beams 20 days Tue 26/07/16 Wed 24/08/16
226 FRC roof slab inc MEPD conduits 24 days Tue 02/08/16 Tue 06/09/16
227 Completion of CD Roof slab (Milestone Structure complete 31/08/16)0 days Tue 06/09/16 Tue 06/09/16
228 Dismantle tower crane and remove from site 0 days Tue 06/09/16 Tue 06/09/16
229 Deformwork 5 days Wed 21/09/16 Wed 28/09/16
230 Parapet walls & 2nd floor pools Block AB 15 days Tue 30/08/16 Tue 20/09/16
231 Wet Trades 158 days Mon 02/05/16 Wed 11/01/17
232 Internally 154 days Mon 02/05/16 Thu 05/01/17
233 Basement 60 days Tue 06/09/16 Tue 06/12/16
234 Basement render works 40 days Tue 06/09/16 Mon 07/11/16
235 Render common stairs 20 days Mon 07/11/16 Tue 06/12/16
236 Ground Floor 55 days Mon 02/05/16 Thu 21/07/16
237 Partition block wall & risers 12 days Mon 02/05/16 Wed 18/05/16
238 M&E 1st & 2nd fix 15 days Tue 03/05/16 Tue 24/05/16
239 Preplaster Check 10 days Thu 12/05/16 Fri 27/05/16
240 Render wall & ceilings internal 25 days Mon 16/05/16 Tue 21/06/16
241 Suspended ceiling grid work 10 days Fri 10/06/16 Fri 24/06/16
242 Floor & wall tiles 25 days Tue 14/06/16 Thu 21/07/16
243 Completion of GF Floor wet trades 0 days Thu 21/07/16 Thu 21/07/16
244 1st Floor 55 days Fri 15/07/16 Wed 05/10/16
245 Partition block wall & risers 12 days Fri 15/07/16 Wed 03/08/16
246 M&E 1st & 2nd fix 15 days Tue 19/07/16 Tue 09/08/16
247 Preplaster Check 10 days Thu 28/07/16 Thu 11/08/16
248 Render wall & ceilings internal 25 days Mon 01/08/16 Tue 06/09/16
249 Suspended ceiling grid work 10 days Fri 26/08/16 Fri 09/09/16
250 Floor & wall tiles 25 days Tue 30/08/16 Wed 05/10/16
251 Completion of 1st Floor wet trades 0 days Wed 05/10/16 Wed 05/10/16
252 2nd Floor 52 days Wed 28/09/16 Thu 05/01/17
253 Partition block wall & risers 12 days Wed 28/09/16 Fri 14/10/16
254 M&E 1st & 2nd fix 12 days Thu 29/09/16 Mon 17/10/16
255 Preplaster Check 10 days Wed 05/10/16 Wed 19/10/16
256 Render wall & ceilings internal 25 days Fri 07/10/16 Thu 17/11/16
257 Suspended ceiling grid work 10 days Mon 07/11/16 Tue 22/11/16
258 Floor & wall tiles 25 days Wed 09/11/16 Thu 05/01/17
259 Completion of 2nd Floor wet trades 0 days Thu 05/01/17 Thu 05/01/17
260 Externally (Block CD) 65 days Wed 14/09/16 Wed 11/01/17
261 Plaster parapet wall on roof 10 days Wed 14/09/16 Thu 29/09/16
262 Plaster front façade 25 days Fri 23/09/16 Mon 31/10/16
263 Plaster side façade 20 days Thu 20/10/16 Wed 23/11/16
264 Plaster rear facades 25 days Wed 16/11/16 Wed 11/01/17
265 Builders work in connection with services on roof & Screed 20 days Fri 16/09/16 Mon 17/10/16
266 Complete Plaster External facades 0 days Wed 11/01/17 Wed 11/01/17
267 Finishes 172 days Wed 06/07/16 Wed 12/04/17
268 Internally 172 days Wed 06/07/16 Wed 12/04/17
269 Basement 80 days Tue 22/11/16 Wed 12/04/17
270 Finishes 30 days Tue 22/11/16 Tue 24/01/17
271 Make good to basement floor 20 days Mon 13/03/17 Wed 12/04/17
272 Ground Floor 140 days Wed 06/07/16 Thu 23/02/17
273 Finishes Internal 77 days Wed 06/07/16 Wed 26/10/16
274 Commencement of Block CD GF Finishes 0 days Tue 19/07/16 Tue 19/07/16
275 Paint 1st coat 8 days Wed 06/07/16 Tue 19/07/16
276 Aluminium openings 12 days Mon 11/07/16 Thu 28/07/16
277 Suspended Ceilings 12 days Fri 22/07/16 Tue 09/08/16
278 Shopfitting installation incl all 15 days Tue 02/08/16 Wed 24/08/16
279 Kitchen fit outs 15 days Mon 22/08/16 Mon 12/09/16
280 Granite tops 12 days Mon 05/09/16 Thu 22/09/16
281 Sanitary wares & accessories 10 days Fri 16/09/16 Mon 03/10/16
282 Electrical accessories & light fittings 10 days Thu 22/09/16 Thu 06/10/16
283 TEL/DATA/MATV installation 7 days Thu 29/09/16 Mon 10/10/16
284 Shower screens 5 days Mon 03/10/16 Mon 10/10/16
285 Snag/De-snag 7 days Mon 10/10/16 Wed 19/10/16
286 Paint final coat 7 days Mon 17/10/16 Wed 26/10/16
287 Complete Block CD GF internal 0 days Wed 26/10/16 Wed 26/10/16
288 Terraces Ground Floor 35 days Fri 09/12/16 Thu 23/02/17
289 Paint 1st & 2nd coat 10 days Fri 09/12/16 Fri 13/01/17
290 Waterproofing to terraces 15 days Wed 14/12/16 Tue 24/01/17
291 Terrace tiling 15 days Thu 12/01/17 Mon 06/02/17
Task Milestone Rolled Up Critical Task Split Group By Summary
STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

4
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
292 Timber screens & cladding 10 days Thu 19/01/17 Mon 06/02/17
293 Balustrades 10 days Mon 23/01/17 Wed 08/02/17
294 Paint final coat 7 days Mon 30/01/17 Mon 13/02/17
295 Snag/De-snag 7 days Mon 13/02/17 Thu 23/02/17
296 Complete Block CD Terraces GF 0 days Thu 23/02/17 Thu 23/02/17
297 First Floor 96 days Wed 21/09/16 Tue 07/03/17
298 Finishes Internal 77 days Wed 21/09/16 Mon 06/02/17
299 Commencement of Block CD FF Finishes 0 days Mon 03/10/16 Mon 03/10/16
300 Paint 1st coat 8 days Wed 21/09/16 Mon 03/10/16
301 Aluminium openings 12 days Mon 26/09/16 Wed 12/10/16
302 Suspended Ceilings 12 days Thu 06/10/16 Mon 24/10/16
303 Shopfitting installation incl all 15 days Mon 17/10/16 Thu 10/11/16
304 Kitchen fit outs 15 days Tue 08/11/16 Wed 30/11/16
305 Granite tops 12 days Wed 23/11/16 Fri 09/12/16
306 Sanitary wares & accessories 10 days Tue 06/12/16 Tue 10/01/17
307 Electrical accessories & light fittings 10 days Fri 09/12/16 Fri 13/01/17
308 TEL/DATA/MATV installation 7 days Fri 06/01/17 Tue 17/01/17
309 Shower screens 5 days Tue 10/01/17 Tue 17/01/17
310 Snag/De-snag 7 days Tue 17/01/17 Thu 26/01/17
311 Paint final coat 7 days Tue 24/01/17 Mon 06/02/17
312 Complete Block CD FF internal 0 days Mon 06/02/17 Mon 06/02/17
313 Terraces First Floor 35 days Wed 11/01/17 Tue 07/03/17
314 Paint 1st & 2nd coat 10 days Wed 11/01/17 Wed 25/01/17
315 Waterproofing to terraces 15 days Fri 13/01/17 Tue 07/02/17
316 Terrace tiling 15 days Tue 24/01/17 Mon 20/02/17
317 Timber screens & cladding 10 days Mon 06/02/17 Wed 22/02/17
318 Balustrades 10 days Mon 06/02/17 Wed 22/02/17
319 Paint final coat 7 days Tue 14/02/17 Fri 24/02/17
320 Snag/De-snag 7 days Fri 24/02/17 Tue 07/03/17
321 Complete Block CD Terraces FF 0 days Tue 07/03/17 Tue 07/03/17
322 Second Floor 71 days Thu 01/12/16 Mon 10/04/17
323 Finishes Internal 71 days Thu 01/12/16 Mon 10/04/17
324 Commencement of Block CD SF Finishes 0 days Wed 14/12/16 Wed 14/12/16
325 Paint 1st coat 8 days Thu 01/12/16 Wed 14/12/16
326 Aluminium openings 12 days Tue 06/12/16 Thu 12/01/17
327 Suspended Ceilings 10 days Fri 06/01/17 Fri 20/01/17
328 Shopfitting installation incl all 14 days Fri 13/01/17 Mon 06/02/17
329 Kitchen fit outs 12 days Tue 31/01/17 Wed 22/02/17
330 Granite tops 12 days Tue 14/02/17 Fri 03/03/17
331 Sanitary wares & accessories 10 days Tue 28/02/17 Tue 14/03/17
332 Electrical accessories & light fittings 10 days Fri 03/03/17 Fri 17/03/17
333 TEL/DATA/MATV installation 7 days Fri 10/03/17 Wed 22/03/17
334 Shower screens 5 days Tue 14/03/17 Wed 22/03/17
335 Snag/De-snag 7 days Wed 22/03/17 Mon 03/04/17
336 Paint final coat 7 days Thu 30/03/17 Mon 10/04/17
337 Complete Block CD SF internal 0 days Mon 10/04/17 Mon 10/04/17
338 Terraces Second Floor 35 days Fri 20/01/17 Thu 16/03/17
339 Paint 1st & 2nd coat 10 days Fri 20/01/17 Tue 07/02/17
340 Waterproofing to terraces 15 days Tue 24/01/17 Mon 20/02/17
341 Terrace tiling & Pool tiling 15 days Mon 06/02/17 Wed 01/03/17
342 Timber screens & cladding 10 days Thu 16/02/17 Fri 03/03/17
343 Balustrades 10 days Thu 16/02/17 Fri 03/03/17
344 Paint final coat 7 days Fri 24/02/17 Tue 07/03/17
345 Snag/De-snag 7 days Tue 07/03/17 Thu 16/03/17
346 Complete Block CD Terraces SF 0 days Thu 16/03/17 Thu 16/03/17
347 Externally & Common areas 78 days Mon 17/10/16 Tue 07/03/17
348 Commencement of Block C & D Externally & Common areas 0 days Mon 17/10/16 Mon 17/10/16
349 Waterproofing on roof 12 days Mon 17/10/16 Mon 07/11/16
350 M & E Equipments on roof 20 days Wed 26/10/16 Tue 29/11/16
351 Paint 1st & 2nd coat 15 days Wed 07/12/16 Wed 18/01/17
352 Lifts installation including finishes 40 days Wed 26/10/16 Tue 17/01/17
353 Stone cladding 35 days Wed 11/01/17 Tue 07/03/17
354 Composite timber cladding, pergolas & gates 35 days Wed 11/01/17 Tue 07/03/17
355 Balustrades 20 days Wed 11/01/17 Mon 13/02/17
356 Tiling to main staircases and common areas 20 days Tue 17/01/17 Mon 20/02/17
357 Paint final coat 10 days Mon 07/11/16 Tue 22/11/16
358 Snag/De-snag 10 days Wed 18/01/17 Thu 02/02/17
359 Complete Block CD External Finishes & Common areas 0 days Tue 07/03/17 Tue 07/03/17
360 Block GH 299 days Mon 11/01/16 Wed 26/04/17
361 Structure 184 days Mon 11/01/16 Wed 12/10/16
362 Ground Floor Slab 46 days Mon 11/01/16 Thu 24/03/16
363 FRC beams 20 days Mon 11/01/16 Thu 11/02/16
364 FRC basement slab(GF) inc MEPD conduits 24 days Mon 18/01/16 Fri 26/02/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

5
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
365 Completion of basement slab GH (GF) 0 days Fri 26/02/16 Fri 26/02/16
366 Deformwork 5 days Wed 16/03/16 Thu 24/03/16
367 Superstructure 161 days Tue 16/02/16 Wed 12/10/16
368 Ground to 1st 59 days Tue 16/02/16 Mon 16/05/16
369 Setting out 7 days Tue 16/02/16 Mon 29/02/16
370 Blockwork 25 days Thu 18/02/16 Tue 29/03/16
371 Commencement of GH Blockwork 0 days Thu 18/02/16 Thu 18/02/16
372 Erect tower crane 0 days Fri 26/02/16 Fri 26/02/16
373 FRC columns 15 days Fri 04/03/16 Tue 29/03/16
374 FRC beams 20 days Thu 10/03/16 Fri 08/04/16
375 FRC 1st Floor slab inc MEPD conduits 25 days Thu 17/03/16 Mon 25/04/16
376 Completion of GH 1st floor slab 0 days Mon 25/04/16 Mon 25/04/16
377 Deformwork 5 days Mon 09/05/16 Mon 16/05/16
378 1st to 2nd 55 days Wed 11/05/16 Mon 01/08/16
379 Setting out 5 days Wed 11/05/16 Wed 18/05/16
380 Blockwork 25 days Wed 11/05/16 Thu 16/06/16
381 FRC columns 15 days Thu 26/05/16 Thu 16/06/16
382 FRC beams 20 days Mon 30/05/16 Mon 27/06/16
383 FRC 2nd floor slab inc MEPD conduits 25 days Thu 02/06/16 Fri 08/07/16
384 Completion of GH SF slab 0 days Fri 08/07/16 Fri 08/07/16
385 Deformwork 5 days Mon 25/07/16 Mon 01/08/16
386 2nd to Roof 53 days Wed 27/07/16 Wed 12/10/16
387 Setting out 5 days Wed 27/07/16 Wed 03/08/16
388 Blockwork 18 days Thu 28/07/16 Wed 24/08/16
389 FRC columns 12 days Fri 05/08/16 Wed 24/08/16
390 FRC beams 20 days Tue 09/08/16 Wed 07/09/16
391 FRC roof slab inc MEPD conduits 24 days Wed 17/08/16 Tue 20/09/16
392 Completion of GH Roof slab 0 days Tue 20/09/16 Tue 20/09/16
393 Dismantle tower crane and remove from site 0 days Tue 20/09/16 Tue 20/09/16
394 Deformwork 5 days Wed 05/10/16 Wed 12/10/16
395 Parapet walls & 2nd floor pools Block GH 15 days Tue 13/09/16 Wed 05/10/16
396 Wet Trades 158 days Mon 16/05/16 Wed 25/01/17
397 Internally 154 days Mon 16/05/16 Thu 19/01/17
398 Basement 60 days Wed 21/09/16 Tue 10/01/17
399 Basement render works 40 days Wed 21/09/16 Tue 22/11/16
400 Render common stairs 20 days Tue 22/11/16 Tue 10/01/17
401 Ground Floor 55 days Mon 16/05/16 Thu 04/08/16
402 Partition block wall & risers 12 days Mon 16/05/16 Thu 02/06/16
403 M&E 1st & 2nd fix 15 days Tue 17/05/16 Wed 08/06/16
404 Preplaster Check 10 days Fri 27/05/16 Fri 10/06/16
405 Render wall & ceilings internal 25 days Tue 31/05/16 Wed 06/07/16
406 Suspended ceiling grid work 10 days Fri 24/06/16 Mon 11/07/16
407 Floor & wall tiles 25 days Tue 28/06/16 Thu 04/08/16
408 Completion of GF Floor wet trades 0 days Thu 04/08/16 Thu 04/08/16
409 1st Floor 55 days Mon 01/08/16 Wed 19/10/16
410 Partition block wall & risers 12 days Mon 01/08/16 Thu 18/08/16
411 M&E 1st & 2nd fix 15 days Tue 02/08/16 Wed 24/08/16
412 Preplaster Check 10 days Thu 11/08/16 Fri 26/08/16
413 Render wall & ceilings internal 25 days Tue 16/08/16 Tue 20/09/16
414 Suspended ceiling grid work 10 days Fri 09/09/16 Mon 26/09/16
415 Floor & wall tiles 25 days Tue 13/09/16 Wed 19/10/16
416 Completion of 1st Floor wet trades 0 days Wed 19/10/16 Wed 19/10/16
417 2nd Floor 52 days Wed 12/10/16 Thu 19/01/17
418 Partition block wall & risers 12 days Wed 12/10/16 Mon 31/10/16
419 M&E 1st & 2nd fix 12 days Thu 13/10/16 Thu 03/11/16
420 Preplaster Check 10 days Wed 19/10/16 Mon 07/11/16
421 Render wall & ceilings internal 25 days Fri 21/10/16 Thu 01/12/16
422 Suspended ceiling grid work 10 days Tue 22/11/16 Tue 06/12/16
423 Floor & wall tiles 25 days Thu 24/11/16 Thu 19/01/17
424 Completion of 2nd Floor wet trades 0 days Thu 19/01/17 Thu 19/01/17
425 Externally (Block GH) 65 days Thu 29/09/16 Wed 25/01/17
426 Plaster parapet wall on roof 10 days Thu 29/09/16 Thu 13/10/16
427 Plaster front façade 25 days Fri 07/10/16 Thu 17/11/16
428 Plaster side façade 20 days Tue 08/11/16 Wed 07/12/16
429 Plaster rear facades 25 days Wed 30/11/16 Wed 25/01/17
430 Builders work in connection with services on roof & Screed 20 days Mon 03/10/16 Thu 03/11/16
431 Complete Plaster External facades 0 days Wed 25/01/17 Wed 25/01/17
432 Finishes 172 days Thu 21/07/16 Wed 26/04/17
433 Internally 172 days Thu 21/07/16 Wed 26/04/17
434 Basement 80 days Tue 06/12/16 Wed 26/04/17
435 Finishes 30 days Tue 06/12/16 Thu 09/02/17
436 Make good to basement floor 20 days Wed 29/03/17 Wed 26/04/17
437 Ground Floor 140 days Thu 21/07/16 Thu 09/03/17
Task Milestone Rolled Up Critical Task Split Group By Summary
STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

6
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
438 Finishes Internal 77 days Thu 21/07/16 Tue 15/11/16
439 Commencement of Block GH GF Finishes 0 days Tue 02/08/16 Tue 02/08/16
440 Paint 1st coat 8 days Thu 21/07/16 Tue 02/08/16
441 Aluminium openings 12 days Tue 26/07/16 Thu 11/08/16
442 Suspended Ceilings 12 days Fri 05/08/16 Wed 24/08/16
443 Shopfitting installation incl all 15 days Wed 17/08/16 Wed 07/09/16
444 Kitchen fit outs 15 days Mon 05/09/16 Tue 27/09/16
445 Granite tops 12 days Mon 19/09/16 Thu 06/10/16
446 Sanitary wares & accessories 10 days Mon 03/10/16 Mon 17/10/16
447 Electrical accessories & light fittings 10 days Thu 06/10/16 Thu 20/10/16
448 TEL/DATA/MATV installation 7 days Thu 13/10/16 Mon 24/10/16
449 Shower screens 5 days Mon 17/10/16 Mon 24/10/16
450 Snag/De-snag 7 days Mon 24/10/16 Mon 07/11/16
451 Paint final coat 7 days Thu 03/11/16 Tue 15/11/16
452 Complete Block GH GF internal 0 days Tue 15/11/16 Tue 15/11/16
453 Terraces Ground Floor 35 days Fri 13/01/17 Thu 09/03/17
454 Paint 1st & 2nd coat 10 days Fri 13/01/17 Fri 27/01/17
455 Waterproofing to terraces 15 days Tue 17/01/17 Thu 09/02/17
456 Terrace tiling 15 days Thu 26/01/17 Wed 22/02/17
457 Timber screens & cladding 10 days Mon 06/02/17 Wed 22/02/17
458 Balustrades 10 days Wed 08/02/17 Fri 24/02/17
459 Paint final coat 7 days Thu 16/02/17 Tue 28/02/17
460 Snag/De-snag 7 days Tue 28/02/17 Thu 09/03/17
461 Complete Block GH Terraces GF 0 days Thu 09/03/17 Thu 09/03/17
462 First Floor 96 days Wed 05/10/16 Wed 22/03/17
463 Finishes Internal 77 days Wed 05/10/16 Wed 22/02/17
464 Commencement of Block GH FF Finishes 0 days Mon 17/10/16 Mon 17/10/16
465 Paint 1st coat 8 days Wed 05/10/16 Mon 17/10/16
466 Aluminium openings 12 days Mon 10/10/16 Wed 26/10/16
467 Suspended Ceilings 12 days Thu 20/10/16 Thu 10/11/16
468 Shopfitting installation incl all 15 days Thu 03/11/16 Fri 25/11/16
469 Kitchen fit outs 15 days Wed 23/11/16 Thu 15/12/16
470 Granite tops 12 days Wed 07/12/16 Fri 13/01/17
471 Sanitary wares & accessories 10 days Tue 10/01/17 Tue 24/01/17
472 Electrical accessories & light fittings 10 days Fri 13/01/17 Fri 27/01/17
473 TEL/DATA/MATV installation 7 days Fri 20/01/17 Tue 31/01/17
474 Shower screens 5 days Tue 24/01/17 Tue 31/01/17
475 Snag/De-snag 7 days Tue 31/01/17 Tue 14/02/17
476 Paint final coat 7 days Fri 10/02/17 Wed 22/02/17
477 Complete Block GH FF internal 0 days Wed 22/02/17 Wed 22/02/17
478 Terraces First Floor 35 days Wed 25/01/17 Wed 22/03/17
479 Paint 1st & 2nd coat 10 days Wed 25/01/17 Mon 13/02/17
480 Waterproofing to terraces 15 days Fri 27/01/17 Thu 23/02/17
481 Terrace tiling 15 days Fri 10/02/17 Mon 06/03/17
482 Timber screens & cladding 10 days Wed 22/02/17 Wed 08/03/17
483 Balustrades 10 days Wed 22/02/17 Wed 08/03/17
484 Paint final coat 7 days Wed 01/03/17 Fri 10/03/17
485 Snag/De-snag 7 days Fri 10/03/17 Wed 22/03/17
486 Complete Block GH Terraces FF 0 days Wed 22/03/17 Wed 22/03/17
487 Second Floor 70 days Thu 05/01/17 Fri 21/04/17
488 Finishes Internal 70 days Thu 05/01/17 Fri 21/04/17
489 Commencement of Block GH SF Finishes 0 days Tue 17/01/17 Tue 17/01/17
490 Paint 1st coat 8 days Thu 05/01/17 Tue 17/01/17
491 Aluminium openings 12 days Tue 10/01/17 Thu 26/01/17
492 Suspended Ceilings 10 days Fri 20/01/17 Tue 07/02/17
493 Shopfitting installation incl all 14 days Fri 27/01/17 Wed 22/02/17
494 Kitchen fit outs 12 days Mon 20/02/17 Wed 08/03/17
495 Granite tops 12 days Tue 28/02/17 Thu 16/03/17
496 Sanitary wares & accessories 10 days Mon 13/03/17 Wed 29/03/17
497 Electrical accessories & light fittings 10 days Thu 16/03/17 Mon 03/04/17
498 TEL/DATA/MATV installation 7 days Mon 27/03/17 Wed 05/04/17
499 Shower screens 5 days Wed 29/03/17 Wed 05/04/17
500 Snag/De-snag 7 days Wed 05/04/17 Fri 14/04/17
501 Paint final coat 7 days Wed 12/04/17 Fri 21/04/17
502 Complete Block GH SF internal 0 days Fri 21/04/17 Fri 21/04/17
503 Terraces Second Floor 35 days Tue 07/02/17 Mon 03/04/17
504 Paint 1st & 2nd coat 10 days Tue 07/02/17 Thu 23/02/17
505 Waterproofing to terraces 15 days Fri 10/02/17 Mon 06/03/17
506 Terrace tiling & Pool tiling 15 days Wed 22/02/17 Wed 15/03/17
507 Timber screens & cladding 10 days Fri 03/03/17 Fri 17/03/17
508 Balustrades 10 days Fri 03/03/17 Fri 17/03/17
509 Paint final coat 7 days Fri 10/03/17 Wed 22/03/17
510 Snag/De-snag 7 days Wed 22/03/17 Mon 03/04/17

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

7
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
511 Complete Block GH Terraces SF 0 days Mon 03/04/17 Mon 03/04/17
512 Externally & Common areas 78 days Thu 03/11/16 Wed 22/03/17
513 Commencement of Block G & H Externally & Common areas 0 days Thu 03/11/16 Thu 03/11/16
514 Waterproofing on roof 12 days Thu 03/11/16 Tue 22/11/16
515 M & E Equipments on roof 20 days Tue 15/11/16 Wed 14/12/16
516 Paint 1st & 2nd coat 15 days Wed 11/01/17 Thu 02/02/17
517 Lifts installation including finishes 40 days Tue 15/11/16 Tue 31/01/17
518 Stone cladding 35 days Wed 25/01/17 Wed 22/03/17
519 Composite timber cladding, pergolas & gates 35 days Wed 25/01/17 Wed 22/03/17
520 Balustrades 20 days Wed 25/01/17 Tue 28/02/17
521 Tiling to main staircases and common areas 20 days Tue 31/01/17 Mon 06/03/17
522 Paint final coat 10 days Tue 22/11/16 Tue 06/12/16
523 Snag/De-snag 10 days Thu 02/02/17 Tue 21/02/17
524 Complete Block GH External Finishes & Common areas 0 days Wed 22/03/17 Wed 22/03/17
525 Block EF 331 days Thu 08/10/15 Mon 03/04/17
526 Structure 218 days Thu 08/10/15 Tue 20/09/16
527 Substructure 57 days Thu 08/10/15 Thu 21/01/16
528 Setting out 5 days Thu 08/10/15 Fri 16/10/15
529 Excavate for footing and bases 10 days Mon 12/10/15 Tue 27/10/15
530 Trim & compact 4 days Thu 22/10/15 Wed 28/10/15
531 Blinding 7 days Thu 22/10/15 Tue 03/11/15
532 FRC footing & bases 12 days Mon 26/10/15 Fri 13/11/15
533 Completion of foundation 0 days Fri 13/11/15 Fri 13/11/15
534 Foundation blockwork 7 days Tue 10/11/15 Fri 20/11/15
535 FRC tie columns 7 days Tue 17/11/15 Fri 27/11/15
536 Completion foundations to underside surfacebed (Milestone 4 Months 31/12/15)
0 days Fri 27/11/15 Fri 27/11/15
537 Backfill & compact to u/side of surface bed 10 days Mon 23/11/15 Tue 08/12/15
538 MEPD sleeves/pipes under surface bed 10 days Mon 30/11/15 Mon 14/12/15
539 Appointment of Antitermite subcontractor 0 days Fri 09/10/15 Fri 09/10/15
540 Soil poisoning & DPM sheet 2 days Thu 10/12/15 Mon 14/12/15
541 FRC GF surface beds 14 days Mon 14/12/15 Thu 21/01/16
542 Completion of surface bed 0 days Thu 21/01/16 Thu 21/01/16
543 Superstructure 165 days Fri 15/01/16 Tue 20/09/16
544 Ground to 1st 58 days Fri 15/01/16 Fri 15/04/16
545 Setting out 5 days Fri 15/01/16 Fri 22/01/16
546 Blockwall 25 days Mon 18/01/16 Mon 29/02/16
547 Commencement of GF Blockwork 0 days Mon 18/01/16 Mon 18/01/16
548 FRC columns 15 days Thu 04/02/16 Mon 29/02/16
549 FRC beam 20 days Tue 09/02/16 Fri 11/03/16
550 FRC 1st Floor slab inc MEPD conduits 24 days Tue 16/02/16 Fri 25/03/16
551 Deformwork 5 days Fri 08/04/16 Fri 15/04/16
552 Completion of FF Slab 0 days Fri 25/03/16 Fri 25/03/16
553 1st to 2nd 59 days Wed 13/04/16 Fri 08/07/16
554 Setting out 5 days Wed 13/04/16 Thu 21/04/16
555 Blockwall 25 days Thu 14/04/16 Fri 20/05/16
556 Commencement of FF Blockwork 0 days Thu 14/04/16 Thu 14/04/16
557 FRC columns 15 days Fri 29/04/16 Fri 20/05/16
558 FRC beam 20 days Wed 04/05/16 Thu 02/06/16
559 FRC SF slab 25 days Wed 11/05/16 Thu 16/06/16
560 Deformwork 5 days Thu 30/06/16 Fri 08/07/16
561 Completion of SF Slab 0 days Thu 16/06/16 Thu 16/06/16
562 2nd to Roof 53 days Tue 05/07/16 Tue 20/09/16
563 Setting out 5 days Tue 05/07/16 Tue 12/07/16
564 Blockwall 18 days Wed 06/07/16 Tue 02/08/16
565 Commencement of SF Blockwork 0 days Wed 06/07/16 Wed 06/07/16
566 FRC columns 12 days Thu 14/07/16 Tue 02/08/16
567 FRC beam 20 days Tue 19/07/16 Wed 17/08/16
568 FRC Roof slab 24 days Tue 26/07/16 Tue 30/08/16
569 Deformwork 5 days Tue 13/09/16 Tue 20/09/16
570 Completion of Roof Slab (Milestone Structure complete 31/06/16) 0 days Tue 30/08/16 Tue 30/08/16
571 Parapet walls Block E & F 15 days Tue 23/08/16 Tue 13/09/16
572 Wet Trades 227 days Thu 07/01/16 Thu 15/12/16
573 Internally 223 days Thu 07/01/16 Thu 08/12/16
574 Ground Floor 119 days Thu 07/01/16 Wed 06/07/16
575 Partition block wall & risers 12 days Fri 15/04/16 Wed 04/05/16
576 Appointment of Conceal Mixer Supplier 0 days Thu 07/01/16 Thu 07/01/16
577 M&E 1st & 2nd fix 15 days Tue 19/04/16 Tue 10/05/16
578 Preplaster Check 10 days Thu 28/04/16 Thu 12/05/16
579 Render wall & ceilings internal 25 days Mon 02/05/16 Tue 07/06/16
580 Appointment of Suspended Ceiling Subcontractor 0 days Mon 22/02/16 Mon 22/02/16
581 Suspended ceiling grid work 10 days Fri 27/05/16 Fri 10/06/16
582 Appointment of Floor and Wall tile Supplier 0 days Wed 13/01/16 Wed 13/01/16
583 Floor & wall tiles 25 days Tue 31/05/16 Wed 06/07/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

8
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
584 Completion of GF wet works 0 days Wed 06/07/16 Wed 06/07/16
585 1st Floor 55 days Fri 08/07/16 Wed 28/09/16
586 Partition block wall & risers 12 days Fri 08/07/16 Wed 27/07/16
587 M&E 1st & 2nd fix 15 days Mon 11/07/16 Tue 02/08/16
588 Preplaster Check 10 days Thu 21/07/16 Thu 04/08/16
589 Render wall & ceilings internal 25 days Mon 25/07/16 Tue 30/08/16
590 Suspended ceiling grid work 10 days Fri 19/08/16 Fri 02/09/16
591 Floor & wall tiles 25 days Tue 23/08/16 Wed 28/09/16
592 Completion of 1st floor wet works 0 days Fri 02/09/16 Fri 02/09/16
593 2nd Floor 52 days Wed 21/09/16 Thu 08/12/16
594 Partition block wall & risers 12 days Wed 21/09/16 Fri 07/10/16
595 M&E 1st & 2nd fix 12 days Thu 22/09/16 Mon 10/10/16
596 Preplaster Check 10 days Wed 28/09/16 Wed 12/10/16
597 Render wall & ceilings internal 25 days Fri 30/09/16 Wed 09/11/16
598 Suspended ceiling grid work 10 days Wed 26/10/16 Tue 15/11/16
599 Floor & wall tiles 25 days Mon 31/10/16 Thu 08/12/16
600 Completion of 2nd floor wet works 0 days Thu 08/12/16 Thu 08/12/16
601 Externally (Block E & F) 65 days Wed 07/09/16 Thu 15/12/16
602 Plaster parapet wall on roof 10 days Wed 07/09/16 Thu 22/09/16
603 Plaster front façade 25 days Thu 15/09/16 Fri 21/10/16
604 Plaster side façade 20 days Thu 13/10/16 Wed 16/11/16
605 Plaster rear facades 25 days Tue 08/11/16 Thu 15/12/16
606 Builders work in connection with services on roof & Screed 20 days Fri 09/09/16 Mon 10/10/16
607 Completion of plaster to facades 0 days Thu 15/12/16 Thu 15/12/16
608 Finishes 272 days Tue 26/01/16 Mon 03/04/17
609 Internally 272 days Tue 26/01/16 Mon 03/04/17
610 Ground Floor 242 days Tue 26/01/16 Wed 15/02/17
611 Finishes Internal 174 days Tue 26/01/16 Wed 12/10/16
612 Commencement of Block E & F GF Finishes 0 days Mon 25/04/16 Mon 25/04/16
613 Appointment of Painting Subcontractor 0 days Mon 25/04/16 Mon 25/04/16
614 Paint 1st coat 8 days Tue 21/06/16 Fri 01/07/16
615 Appointment of Alumnium Opening Subcontractor 0 days Tue 26/01/16 Tue 26/01/16
616 Aluminium openings 12 days Fri 24/06/16 Wed 13/07/16
617 Suspended Ceilings 12 days Thu 07/07/16 Tue 26/07/16
618 Appointment of Shopfitting Subcontractor 0 days Mon 22/02/16 Mon 22/02/16
619 Shopfitting installation incl all 15 days Tue 19/07/16 Tue 09/08/16
620 Appointment of Kithcen Fit Out Subcontractor 0 days Fri 11/03/16 Fri 11/03/16
621 Kitchen fit outs 15 days Fri 05/08/16 Mon 29/08/16
622 Appointment of Granite Supplier 0 days Mon 11/04/16 Mon 11/04/16
623 Granite tops 12 days Mon 22/08/16 Wed 07/09/16
624 Appointment of Sanware & Toilet Accessories Supplier 0 days Mon 25/04/16 Mon 25/04/16
625 Sanitary wares & accessories 10 days Fri 02/09/16 Fri 16/09/16
626 Appointment of Light Fitting Supplier 0 days Thu 28/04/16 Thu 28/04/16
627 Electrical accessories & light fittings 10 days Wed 07/09/16 Thu 22/09/16
628 Appointment of Tel/Data/MATV Subcontractor 0 days Fri 17/06/16 Fri 17/06/16
629 TEL/DATA/MATV installation 7 days Wed 14/09/16 Mon 26/09/16
630 Appointment of Shower Door Supplier 0 days Tue 31/05/16 Tue 31/05/16
631 Shower screens 5 days Fri 16/09/16 Mon 26/09/16
632 Snag/De-snag 7 days Mon 26/09/16 Wed 05/10/16
633 Paint final coat 7 days Mon 03/10/16 Wed 12/10/16
634 Complete Block A & B GF internal 0 days Wed 12/10/16 Wed 12/10/16
635 Terraces Ground Floor 35 days Fri 02/12/16 Wed 15/02/17
636 Paint 1st & 2nd coat 10 days Fri 02/12/16 Fri 06/01/17
637 Waterproofing to terraces 15 days Tue 06/12/16 Tue 17/01/17
638 Terrace tiling 15 days Thu 05/01/17 Thu 26/01/17
639 Timber screens & cladding 10 days Thu 12/01/17 Thu 26/01/17
640 Balustrades 10 days Mon 16/01/17 Mon 30/01/17
641 Paint final coat 7 days Mon 23/01/17 Thu 02/02/17
642 Snag/De-snag 7 days Thu 02/02/17 Wed 15/02/17
643 Complete Block E & F Terraces GF 0 days Wed 15/02/17 Wed 15/02/17
644 First Floor 96 days Tue 13/09/16 Tue 28/02/17
645 Finishes Internal 77 days Tue 13/09/16 Thu 26/01/17
646 Commencement of Block E & F FF Finishes 0 days Mon 26/09/16 Mon 26/09/16
647 Paint 1st coat 8 days Tue 13/09/16 Mon 26/09/16
648 Aluminium openings 12 days Fri 16/09/16 Wed 05/10/16
649 Suspended Ceilings 12 days Thu 29/09/16 Mon 17/10/16
650 Shopfitting installation incl all 15 days Mon 10/10/16 Thu 03/11/16
651 Kitchen fit outs 15 days Thu 27/10/16 Wed 23/11/16
652 Granite tops 12 days Wed 16/11/16 Fri 02/12/16
653 Sanitary wares & accessories 10 days Tue 29/11/16 Wed 14/12/16
654 Electrical accessories & light fittings 10 days Fri 02/12/16 Fri 06/01/17
655 TEL/DATA/MATV installation 7 days Fri 09/12/16 Tue 10/01/17
656 Shower screens 5 days Wed 14/12/16 Tue 10/01/17

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

9
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
657 Snag/De-snag 7 days Tue 10/01/17 Thu 19/01/17
658 Paint final coat 7 days Tue 17/01/17 Thu 26/01/17
659 Complete Block E & F FF internal 0 days Thu 26/01/17 Thu 26/01/17
660 Terraces First Floor 35 days Thu 15/12/16 Tue 28/02/17
661 Paint 1st & 2nd coat 10 days Thu 15/12/16 Wed 18/01/17
662 Waterproofing to terraces 15 days Fri 06/01/17 Fri 27/01/17
663 Terrace tiling 15 days Tue 17/01/17 Thu 09/02/17
664 Timber screens & cladding 10 days Tue 24/01/17 Thu 09/02/17
665 Balustrades 10 days Thu 26/01/17 Tue 14/02/17
666 Paint final coat 7 days Mon 06/02/17 Thu 16/02/17
667 Snag/De-snag 7 days Thu 16/02/17 Tue 28/02/17
668 Complete Block E & F Terraces FF 0 days Tue 28/02/17 Tue 28/02/17
669 Second Floor 71 days Thu 24/11/16 Mon 03/04/17
670 Finishes Internal 71 days Thu 24/11/16 Mon 03/04/17
671 Commencement of Block E & F SF Finishes 0 days Tue 06/12/16 Tue 06/12/16
672 Paint 1st coat 8 days Thu 24/11/16 Tue 06/12/16
673 Aluminium openings 12 days Tue 29/11/16 Thu 05/01/17
674 Suspended Ceilings 10 days Fri 09/12/16 Fri 13/01/17
675 Shopfitting installation incl all 14 days Fri 06/01/17 Thu 26/01/17
676 Kitchen fit outs 12 days Tue 24/01/17 Tue 14/02/17
677 Granite tops 12 days Mon 06/02/17 Fri 24/02/17
678 Sanitary wares & accessories 10 days Tue 21/02/17 Tue 07/03/17
679 Electrical accessories & light fittings 10 days Fri 24/02/17 Fri 10/03/17
680 TEL/DATA/MATV installation 7 days Fri 03/03/17 Tue 14/03/17
681 Shower screens 5 days Tue 07/03/17 Tue 14/03/17
682 Snag/De-snag 7 days Tue 14/03/17 Mon 27/03/17
683 Paint final coat 7 days Wed 22/03/17 Mon 03/04/17
684 Complete Block E & F SF internal 0 days Mon 03/04/17 Mon 03/04/17
685 Terraces Second Floor 35 days Fri 13/01/17 Thu 09/03/17
686 Paint 1st & 2nd coat 10 days Fri 13/01/17 Fri 27/01/17
687 Waterproofing to terraces 15 days Tue 17/01/17 Thu 09/02/17
688 Terrace tiling & Pool tiling 15 days Thu 26/01/17 Wed 22/02/17
689 Timber screens & cladding 10 days Mon 06/02/17 Wed 22/02/17
690 Balustrades 10 days Wed 08/02/17 Fri 24/02/17
691 Paint final coat 7 days Thu 16/02/17 Tue 28/02/17
692 Snag/De-snag 7 days Tue 28/02/17 Thu 09/03/17
693 Complete Block E & F Terraces SF 0 days Thu 09/03/17 Thu 09/03/17
694 Externally & Common areas 78 days Mon 10/10/16 Tue 28/02/17
695 Commencement of Block E & F Externally & Common areas 0 days Mon 10/10/16 Mon 10/10/16
696 Waterproofing on roof 12 days Mon 10/10/16 Wed 26/10/16
697 M & E Equipments on roof 20 days Wed 19/10/16 Tue 22/11/16
698 Paint 1st & 2nd coat 15 days Wed 30/11/16 Wed 11/01/17
699 Lifts installation including finishes 40 days Wed 19/10/16 Tue 10/01/17
700 Stone cladding 35 days Thu 15/12/16 Tue 28/02/17
701 Composite timber cladding & gates 30 days Thu 15/12/16 Tue 21/02/17
702 Balustrades 20 days Thu 15/12/16 Thu 02/02/17
703 Tiling to main staircases and common areas 20 days Tue 10/01/17 Thu 09/02/17
704 Paint final coat 10 days Wed 26/10/16 Tue 15/11/16
705 Snag/De-snag 10 days Wed 11/01/17 Wed 25/01/17
706 Complete Block E & F External Finishes & Common areas 0 days Tue 28/02/17 Tue 28/02/17
707
708 External Works Blocks A, B, C & D 261 days Tue 23/02/16 Mon 10/04/17
709 Common Pools 148 days Tue 23/02/16 Wed 28/09/16
710 Structure 88 days Tue 23/02/16 Thu 30/06/16
711 Excavation and Formation 15 days Tue 23/02/16 Wed 16/03/16
712 Blinding 10 days Wed 09/03/16 Thu 24/03/16
713 MEP 1st Fix base 10 days Tue 22/03/16 Tue 05/04/16
714 FRC Base 20 days Tue 29/03/16 Wed 27/04/16
715 MEP 1st Fix walls 30 days Tue 12/04/16 Wed 25/05/16
716 FRC Wall 50 days Wed 20/04/16 Thu 30/06/16
717 Wet Trades 35 days Thu 23/06/16 Tue 16/08/16
718 MEP Second Fix 10 days Thu 23/06/16 Fri 08/07/16
719 water Test 10 days Fri 08/07/16 Mon 25/07/16
720 Plaster to pool 15 days Mon 25/07/16 Tue 16/08/16
721 Finishes 35 days Mon 08/08/16 Wed 28/09/16
722 Pool Tiling 35 days Mon 08/08/16 Wed 28/09/16
723 Complete common pool 0 days Wed 28/09/16 Wed 28/09/16
724 Daybeds & Planters 144 days Wed 16/03/16 Thu 13/10/16
725 Substructure 46 days Wed 16/03/16 Mon 23/05/16
726 Setting out 10 days Wed 16/03/16 Thu 31/03/16
727 Excavation for bases 15 days Thu 24/03/16 Thu 14/04/16
728 Blinding 7 days Thu 31/03/16 Mon 11/04/16
729 FRC bases 10 days Thu 07/04/16 Fri 22/04/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

10
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
730 MEP First Fix 5 days Wed 20/04/16 Wed 27/04/16
731 Columns 12 days Fri 22/04/16 Tue 10/05/16
732 Backfill 7 days Tue 03/05/16 Thu 12/05/16
733 Casting of Surface Bed 10 days Mon 09/05/16 Mon 23/05/16
734 Superstructure 38 days Mon 16/05/16 Mon 11/07/16
735 Ground to First 38 days Mon 16/05/16 Mon 11/07/16
736 Columns 15 days Mon 16/05/16 Tue 07/06/16
737 MEP 1st and 2nd fix 5 days Tue 31/05/16 Tue 07/06/16
738 FRC Beams 10 days Fri 03/06/16 Fri 17/06/16
739 FRC Slab with conduits 20 days Fri 10/06/16 Mon 11/07/16
740 Finishes (Internal + External) 55 days Tue 26/07/16 Thu 13/10/16
741 Plaster 25 days Tue 26/07/16 Wed 31/08/16
742 Stone Walls 30 days Wed 31/08/16 Thu 13/10/16
743 Paint 1st coat 10 days Wed 24/08/16 Wed 07/09/16
744 Complete daybeds & Planters 0 days Thu 13/10/16 Thu 13/10/16
745 Security Post 82 days Mon 03/10/16 Mon 27/02/17
746 Substructure 12 days Mon 03/10/16 Wed 19/10/16
747 Fixed start 0 days Mon 03/10/16 Mon 03/10/16
748 Setting out 2 days Mon 03/10/16 Wed 05/10/16
749 Excavate for footing and bases 2 days Tue 04/10/16 Thu 06/10/16
750 Trim & compact 1 day Wed 05/10/16 Thu 06/10/16
751 Blinding 1 day Wed 05/10/16 Thu 06/10/16
752 FRC footing & bases 3 days Wed 05/10/16 Mon 10/10/16
753 Foundation blockwork 3 days Fri 07/10/16 Wed 12/10/16
754 FRC tie columns 2 days Tue 11/10/16 Thu 13/10/16
755 Backfill & compact to u/side of surface bed 2 days Wed 12/10/16 Fri 14/10/16
756 MEPD sleeves/pipes under surface bed 3 days Wed 12/10/16 Mon 17/10/16
757 Soil poisoning & DPM sheet 1 day Fri 14/10/16 Mon 17/10/16
758 FRC GF surface beds 4 days Thu 13/10/16 Wed 19/10/16
759 Completion of surface bed 0 days Wed 19/10/16 Wed 19/10/16
760 Superstructure 30 days Wed 19/10/16 Tue 06/12/16
761 Blockwork 7 days Wed 19/10/16 Fri 28/10/16
762 FRC columns 7 days Tue 25/10/16 Mon 07/11/16
763 FRC beams 7 days Fri 28/10/16 Thu 10/11/16
764 FRC 1st Floor slab inc MEPD conduits 7 days Mon 07/11/16 Fri 18/11/16
765 Deformwork 2 days Fri 02/12/16 Tue 06/12/16
766 Finishes (Internal + External) 40 days Tue 06/12/16 Mon 27/02/17
767 Finishes & snag 40 days Tue 06/12/16 Mon 27/02/17
768 Complete Security Post 0 days Mon 27/02/17 Mon 27/02/17
769 Transformer Room 50 days Fri 01/07/16 Tue 13/09/16
770 Fixed start 0 days Fri 01/07/16 Fri 01/07/16
771 Structure 15 days Fri 01/07/16 Mon 25/07/16
772 Wet Trade 15 days Mon 25/07/16 Tue 16/08/16
773 Finishes 25 days Mon 08/08/16 Tue 13/09/16
774 Complete Transformer Room 0 days Tue 13/09/16 Tue 13/09/16
775 Ramps to basements 25 days Tue 13/09/16 Wed 19/10/16
776 Structure 10 days Tue 13/09/16 Wed 28/09/16
777 Wet Trade 5 days Wed 28/09/16 Wed 05/10/16
778 Finishes 10 days Wed 05/10/16 Wed 19/10/16
779 Complete Ramps to Basement 0 days Wed 19/10/16 Wed 19/10/16
780 Site Works 100 days Tue 21/06/16 Fri 18/11/16
781 External Services including stormwater 100 days Tue 21/06/16 Fri 18/11/16
782 Complete External Services Site Works 0 days Fri 18/11/16 Fri 18/11/16
783 Hard Landscape 80 days Mon 24/10/16 Thu 16/03/17
784 Paving slabs & Parking 70 days Mon 24/10/16 Thu 02/03/17
785 Other finishes 30 days Fri 27/01/17 Thu 16/03/17
786 Complete Hard Landscaping 0 days Thu 16/03/17 Thu 16/03/17
787 Soft Landscape 160 days Thu 21/07/16 Mon 10/04/17
788 Appointment of Landscape Subcontractor 0 days Thu 21/07/16 Thu 21/07/16
789 Top soil 15 days Fri 25/11/16 Fri 06/01/17
790 Irrigation 25 days Fri 09/12/16 Tue 07/02/17
791 External light 25 days Fri 27/01/17 Thu 09/03/17
792 Planting 25 days Thu 02/03/17 Mon 10/04/17
793 Complete Soft Landscaping 0 days Mon 10/04/17 Mon 10/04/17
794
795 Final Handover of Works 349.51 days Fri 30/10/15 Mon 22/05/17
796 Bulk Earthworks 0 days Fri 30/10/15 Fri 30/10/15
797 Completion of basement excavation 0 days Fri 30/10/15 Fri 30/10/15
798 Common Basement (AB, CD, GH) 45 days Mon 14/12/15 Mon 14/03/16
799 Completion of basement floor slab (Milestone 31/12/15) 0 days Mon 14/12/15 Mon 14/12/15
800 Completion of basement retaining walls 0 days Tue 02/02/16 Tue 02/02/16
801 Completion of basement incl waterproofing to retaining walls 0 days Mon 14/03/16 Mon 14/03/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

11
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
802 Block AB 268 days Thu 28/01/16 Thu 30/03/17
803 Structure 140 days Thu 28/01/16 Fri 26/08/16
804 Completion of basement slab (GF) 0 days Thu 28/01/16 Thu 28/01/16
805 Completion of FF slab 0 days Wed 30/03/16 Wed 30/03/16
806 Completion of SF slab 0 days Tue 14/06/16 Tue 14/06/16
807 Completion of Roof slab (Milestone Structure complete 31/08/16) 0 days Fri 26/08/16 Fri 26/08/16
808 Wet Trades 103 days Mon 11/07/16 Tue 13/12/16
809 Completion of GF Floor wet trades 0 days Mon 11/07/16 Mon 11/07/16
810 Completion of 1st Floor wet trades 0 days Mon 26/09/16 Mon 26/09/16
811 Completion of 2nd Floor wet trades 0 days Tue 06/12/16 Tue 06/12/16
812 Complete Plaster External facades 0 days Tue 13/12/16 Tue 13/12/16
813 Finishes 93 days Mon 17/10/16 Thu 30/03/17
814 Complete GF internal 0 days Mon 17/10/16 Mon 17/10/16
815 Complete Terraces GF 0 days Mon 13/02/17 Mon 13/02/17
816 Complete FF internal 0 days Tue 24/01/17 Tue 24/01/17
817 Complete Terraces FF 0 days Fri 24/02/17 Fri 24/02/17
818 Complete SF internal 0 days Thu 30/03/17 Thu 30/03/17
819 Complete Terraces SF 0 days Tue 07/03/17 Tue 07/03/17
820 Complete External Finishes & Common areas 0 days Fri 24/02/17 Fri 24/02/17
821 Block CD 268 days Wed 10/02/16 Mon 10/04/17
822 Structure 140 days Wed 10/02/16 Tue 06/09/16
823 Completion of basement slab (GF) 0 days Wed 10/02/16 Wed 10/02/16
824 Completion of FF slab 0 days Fri 08/04/16 Fri 08/04/16
825 Completion of SF slab 0 days Thu 23/06/16 Thu 23/06/16
826 Completion of Roof slab (Milestone Structure complete 31/08/16) 0 days Tue 06/09/16 Tue 06/09/16
827 Wet Trades 103 days Thu 21/07/16 Wed 11/01/17
828 Completion of GF Floor wet trades 0 days Thu 21/07/16 Thu 21/07/16
829 Completion of 1st Floor wet trades 0 days Wed 05/10/16 Wed 05/10/16
830 Completion of 2nd Floor wet trades 0 days Thu 05/01/17 Thu 05/01/17
831 Complete Plaster External facades 0 days Wed 11/01/17 Wed 11/01/17
832 Finishes 93 days Wed 26/10/16 Mon 10/04/17
833 Complete GF internal 0 days Wed 26/10/16 Wed 26/10/16
834 Complete Terraces GF 0 days Thu 23/02/17 Thu 23/02/17
835 Complete FF internal 0 days Mon 06/02/17 Mon 06/02/17
836 Complete Terraces FF 0 days Tue 07/03/17 Tue 07/03/17
837 Complete SF internal 0 days Mon 10/04/17 Mon 10/04/17
838 Complete Terraces SF 0 days Thu 16/03/17 Thu 16/03/17
839 Complete External Finishes & Common areas 0 days Tue 07/03/17 Tue 07/03/17
840 Block GH 267 days Fri 26/02/16 Fri 21/04/17
841 Structure 140 days Fri 26/02/16 Tue 20/09/16
842 Completion of basement slab (GF) 0 days Fri 26/02/16 Fri 26/02/16
843 Completion of FF slab 0 days Mon 25/04/16 Mon 25/04/16
844 Completion of SF slab 0 days Fri 08/07/16 Fri 08/07/16
845 Completion of AB Roof slab (Milestone later as agreed additional block) 0 days Tue 20/09/16 Tue 20/09/16
846 Wet Trades 103 days Thu 04/08/16 Wed 25/01/17
847 Completion of GF Floor wet trades 0 days Thu 04/08/16 Thu 04/08/16
848 Completion of 1st Floor wet trades 0 days Wed 19/10/16 Wed 19/10/16
849 Completion of 2nd Floor wet trades 0 days Thu 19/01/17 Thu 19/01/17
850 Complete Plaster External facades 0 days Wed 25/01/17 Wed 25/01/17
851 Finishes 92 days Tue 15/11/16 Fri 21/04/17
852 Complete GF internal 0 days Tue 15/11/16 Tue 15/11/16
853 Complete Terraces GF 0 days Thu 09/03/17 Thu 09/03/17
854 Complete FF internal 0 days Wed 22/02/17 Wed 22/02/17
855 Complete Terraces FF 0 days Wed 22/03/17 Wed 22/03/17
856 Complete SF internal 0 days Fri 21/04/17 Fri 21/04/17
857 Complete Terraces SF 0 days Mon 03/04/17 Mon 03/04/17
858 Complete External Finishes & Common areas 0 days Wed 22/03/17 Wed 22/03/17
859 Block EF 299 days Fri 27/11/15 Mon 03/04/17
860 Structure 171 days Fri 27/11/15 Tue 30/08/16
861 Completion foundations to underside surfacebed (Milestone 31/12/15) 0 days Fri 27/11/15 Fri 27/11/15
862 Completion of surface bed 0 days Thu 21/01/16 Thu 21/01/16
863 Completion of FF Slab 0 days Fri 25/03/16 Fri 25/03/16
864 Completion of SF Slab 0 days Thu 16/06/16 Thu 16/06/16
865 Completion of Roof Slab (Milestone Structure complete 31/08/16) 0 days Tue 30/08/16 Tue 30/08/16
866 Wet Works 108 days Wed 06/07/16 Thu 15/12/16
867 Completion of GF wet works 0 days Wed 06/07/16 Wed 06/07/16
868 Completion of 1st floor wet works 0 days Fri 02/09/16 Fri 02/09/16
869 Completion of 2nd floor wet works 0 days Thu 08/12/16 Thu 08/12/16
870 Completion of plaster to facades 0 days Thu 15/12/16 Thu 15/12/16
871 Finishes 98 days Wed 12/10/16 Mon 03/04/17
872 Complete Block E & F GF internal 0 days Wed 12/10/16 Wed 12/10/16
873 Complete Block E & F Terraces GF 0 days Wed 15/02/17 Wed 15/02/17

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary

12
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
874 Complete Block E & F FF internal 0 days Thu 26/01/17 Thu 26/01/17
875 Complete Block E & F Terraces FF 0 days Tue 28/02/17 Tue 28/02/17
876 Complete Block E & F SF internal 0 days Mon 03/04/17 Mon 03/04/17
877 Complete Block E & F Terraces SF 0 days Thu 09/03/17 Thu 09/03/17
878 Complete Block E & F External Finishes & Common areas 0 days Tue 28/02/17 Tue 28/02/17
879 External Works Blocks A, B, C & D 122.94 days Tue 13/09/16 Mon 10/04/17
880 Complete common pool 0 days Wed 28/09/16 Wed 28/09/16
881 Complete daybeds & Planters 0 days Thu 13/10/16 Thu 13/10/16
882 Complete Security Post 0 days Mon 27/02/17 Mon 27/02/17
883 Complete Transformer Room 0 days Tue 13/09/16 Tue 13/09/16
884 Complete Ramps to Basement 0 days Wed 19/10/16 Wed 19/10/16
885 Complete External Services Site Works 0 days Fri 18/11/16 Fri 18/11/16
886 Complete Hard Landscaping 0 days Thu 16/03/17 Thu 16/03/17
887 Complete Soft Landscaping 0 days Mon 10/04/17 Mon 10/04/17
888
889 Final Completion 35.42 days Thu 30/03/17 Mon 22/05/17
890 Final M & E T & C & Snag and Desnag AB 20 days Thu 30/03/17 Thu 27/04/17
891 Final M & E T & C & Snag and Desnag CD 20 days Tue 11/04/17 Wed 10/05/17
892 Final M & E T & C & Snag and Desnag GH 20 days Wed 19/04/17 Thu 18/05/17
893 Final M & E T & C & Snag and Desnag EF 20 days Mon 03/04/17 Tue 02/05/17
894 Final M & E T & C & Snag and Desnag Common Basement 15 days Wed 26/04/17 Thu 18/05/17
895 Final M & E T & C & Snag and Desnag External Works 20 days Tue 11/04/17 Wed 10/05/17
896
897 Final Completion 0 days Mon 22/05/17 Mon 22/05/17

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:15 September 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 1 Progress Rolled Up Task Rolled Up Progress Project Summary