FR42 8015-0151-ENTR-41-411-EL-PP-41205 A0
LUKOIL MID-EAST LIMITED Doc. 8015-0151-ENTR-41-411-EL-PP-41205
TUBA TANK FARM EXTENSION Rev. A0
West Qurna (Phase 2) Contract Area Page 2 of 9
REVISION RECORD
TABLE OF CONTENTS
1 SCOPE ......................................................................................................................................................... 4
2 DEFINITIONS ............................................................................................................................................... 4
2.1 Project Parties ............................................................................................................................ 4
2.2 Acronyms & Abbreviations .......................................................................................................... 4
4 Responsibilities ............................................................................................................................................. 5
6 INTERFACES ............................................................................................................................................... 5
7 RESOURCES ............................................................................................................................................... 5
7.1 Personnel ................................................................................................................................... 5
7.2 Equipment .................................................................................................................................. 5
9 QUALITY ....................................................................................................................................................... 8
10 HSE ............................................................................................................................................................... 8
10.1 General ...................................................................................................................................... 8
1 SCOPE
This Method of Statement specifies the detailed requirements for the process installation the cathodic
protection system, all safety measures, and precautions are taken into consideration during the execution
of the work.
.
2 DEFINITIONS
4 REFERENCE DOCUMENTS
5 Project documents
• General plot plan N°1540 R203-00101 Rev. 3
7 Responsibilities
Project Manager
It is the responsibility of Project Manager to support all the project site, provide all the resources
which required at the site and execution of the project in compliance to project specification in
particular and engineering practices in general with quality, safety and schedule commitments.
Site Engineer
SE will ensure that all the works are performed as per latest Issued For Construction
(IFC) drawings & specifications.
Safety·
Construction activities to be carried out with safe working environment & in accordance
with approved project specific HSE plan.
9 INTERFACES
• Project site, is devoid from interfaces; anyhow permit will be obtained from Tuba Tank Farm
authority prior to the execution of any works.
• Coordinate with Tuba Tank Farm Managements the interface with their day to day internal activities
if any and the interference with the other progressing activities as per the Project Schedule.
• Coordinate the excavation with the existing services (piping, roads.... ..) including the tie in points.
10 RESOURCES
10.1 Personnel
Works will be carried out by well experienced personnel as below:
• Electricall engineers with 5 to 10 years of experience.
• QC Engineers 5--10 years Experience
• Surveyor with 3 to 5 years experience.
• Electrical Forman with 3 to 5 years experience.
• Labours.
10.2 Equipment
In accordance to work requirements, the following machineries and equipments will be used in general:
11 PROGRAM OF WORK
11.1 Mobilization
Mobilization will be carried out within 2 days from the date of receiving the acceptance to commence the
works and approval of work permit from Tuba Tank Farm authorities for each task.
11.2.1.2 DC Cables
• Cable connections to the pipe should be made.
• Buried cables should lie at a depth that will protect them from disturbance by
• Ploughing or other excavations. Cable tiles or cable warning tape should be used to
• Warn of the presence of the cable during any subsequent excavation.
• Cables should be color coded or marked to identify them.
• Excavate to the required depth, and excavate trench for cable as required.
• Ensure that any plastic covering is removed from the anode. The muslin bag should
be left intact.
• Place the anode in the required position and water thoroughly. (A bucket of water is
ideal)
• Terminate cables as required.
• Backfill the excavation and re-instate the ground.
• Excess spoil to be removed from site. Client: Method Statement
11.2.2.2 DC Cables
• The specification may call for above ground installation of cables. In this case, the
Cable should be installed as required in the specification.
11.2.2.3 AC Cables
• Generally AC mains voltage cables will be provided by the electricity supplier and
Terminated by them or by a qualified electrician. If it is necessary to install mains
Voltage cables then the requirements of BS7671 should be observed and advice
Sought from a qualified person.
• Ensure that all relevant site conditions and working practices are observed. If
necessary obtain a work permit as required by the site.
• Locate the transformer rectifier at the planned point of installation. This may be on a
prepared concrete plinth, on a wall, or on a pole.
• Fix the unit in place using appropriate fixings.
• Test the unit according to the specification.
• Terminate DC cables to the appropriate connections. Take particular care to observe
the polarity of the pipe and ground bed cables.
• Energize the system and carry out any testing procedures.
• Commission the system.
Cleaning
After completion of installation, remove burrs, dirt, and construction debris and repair any damages,
scratches and abrasion.
11.3 Demobilization
As soon as the construction works are completed, machinery and equipments which are not necessary
for the successor activity will be demobilized from work site.
12 QUALITY
• The works shall be executed in accordance with 8015-0151-ENTR-00-000-QC-PN-00001,
Consortium Project Quality Plan.
• The works shall be executed in accordance with approved Inspection Test Plan (ITP) Document
• The contractor QA/QC engineer will be monitoring the entire activities and as per the inspection
level in the aforementioned ITP.
• Quality Control department shall retain all Material Certificates, tests, and inspection records.
13 HSE
General
• Work is to be carried out in a safe manner and in accordance with the H.S.E Program and Safety
Policy. Site operatives shall be well inducted for the safe operation of the machineries, equipment
& tools to be used.
• Personnel Protective Equipments will be used by all staff & labours. The minimum personal
protective equipment is as follows:
• Safety helmet
• Safety footwear
• Eye protection
• Gloves
• Overalls
• Any other equipment required by the site operator or deemed necessary by the task.
• Before carrying out the field works, work permit will be obtained from Tuba depot authority, daily
or as per the regulation implemented.
• All regulation implemented by Tuba depot authority at site will be respected.
• Proper barricades and traffic signs shall be placed around the work site location whenever
required.
• Trained people with banner to regulate the traffic passages of vehicles and machineries.
• "Tool Box" talk or "Safety Talk" shall be conducted prior to the commencement of each activity.
• If weather will be dusty in some times during the work periods, then water will be sprayed
whenever required on dusty areas to prevent blowing and spread of dust.