Академический Документы
Профессиональный Документы
Культура Документы
References ......................................................................................................................... 28
1|Page
Chapter 1 - Executive Summary
The Volta River Authority (VRA) was established on April 26, 1961 under the Volta
River Development Act, Act 46 of the Republic of Ghana, as a body corporate with the
According to the 2014 annual report of the VRA, due to a major amendment to the VRA
Act in 2005, the operations of the VRA has largely been restricted to generation of
electricity. Transmission has therefore being separated into an entity, designated Ghana
Grid Company (GRIDCo) while the VRA’s distribution agency, the Northern Electricity
Department (NED), has been transformed into the Northern Electricity Distribution
power is currently the largest producer of renewable energy in Ghana. Hydro generation
currently accounts for 60 percent of the total system supply, and this is the largest share
of the ramping capacity. The VRA, the major generation plant in the country, thus offers
the best environment for practical exposure to the operations of a hydro generation
internship is a very good learning opportunity for the renewable energy engineer.
Upon receipt of the letter of attachment proposal from the University, the VRA/ Nedco
sections of electrical, lines, eGIS and fault Department from 23rd June to 11th August
2|Page
2017 which I accepted. The offer was made prior to an agreement that the authority
would not provide an attaché with transportation to and from the work place. Also, no
form of allowance, accommodation or meals will be provided. Work begins from 8:00
The Technical Maintenance section as the name suggests, is in charge of maintaining all
electrical apparatus and equipment that are involved in both electricity and fault
processes. The section comprises of electrical engineers and electrical technicians, and is
3|Page
Chapter 2 - Introduction
NEDCo was formed out of the Northern Electricity Department (NED) of the Volta River
Authority (VRA). NED itself was established in April 1987 when the northern electricity
distribution operations of the then Electricity Corporation of Ghana were ceded to the
VRA. The Authority, at that time, was in the process of extending the national grid
beyond Kumasi to the northern parts of Ghana. The Volta River Development
(Amendment) Law, 1987 (PNDCL 171) was passed to enable VRA to enter the
At the time of the inception of NED, some major towns were served by diesel generators.
Some of these towns with diesel generation included Sunyani, Techiman, Berekum,
Wenchi, Dormaa Ahenkro, Tamale, Yendi, Salaga, Bolgatanga, Navrongo, Bawku and
Wa. New diesel plants were also installed in Wa through the support of DANIDA in
NED was originally started as three operational Areas namely Upper Area, Northern
Area and Brong-Ahafo Area. In 1995, however, the Upper Area was divided into upper
East and Upper West Areas. In 2003, the Brong-Ahafo area was also further divided into
In June 1994, the Government of Ghana (GoG) initiated the Power Sector Reform (PSR)
Sector in order to improve services delivery to all consumers. In pursuance of the Power
4|Page
Sector Reforms, VRA Management registered NEDCo as a wholly-owned VRA
subsidiary with a Board of Directors since 1997 to take over the operations of NED.
Phone: +233-03-5202204-13
Email: corporatecomms@nedco.com.gh3
Website: www.nedco.gh.com3
2.2 Structure
owned enterprise and is overseen by the Volta River Authority board. This board is made
up of the Managing Director, the Head audit, Head legal, Secretary, Manager of network
and customer and five other members. There is also a Director of services. The NEDCo
management is further sectionalized into principal offices. These include, the office of the
Director Finance, the Director Network and Operation, Director Engineering and Director
Under the office of the Director services are the Manager of transports and security,
The Director Finance and Director Network and Operation is also made up of the
5|Page
The Director Engineering Branch consists of the Manager of engineering, Manager of
project, Manager Network and Planning and Development, the Director of Finance, the
Last but not least, the Director of Commercial and Operation is made up of the Manager
Organogram of NEDCo
Source: nedco.com.gh/organizational_chart
6|Page
2.3 Field of Business
NedCo’s current operations extend into the northern parts of Volta, Ashanti and Western
regions. Although NEDCo’s operations cover about 64% of the geographical area of
Ghana, the customer density of the operating area is low with access to electricity in the
NEDCo operating area put at about 36% as at the end of 2011. The Ghana Government,
in line with its vision of making electricity available to all by year 2020, has undertaken
power extensions over the years to new towns and communities that were hitherto not
served by NEDCo1. Customer population has thus grown from less than 20,000 in 1987
7|Page
Chapter 3 - Description of attachment
Week: 1
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
27- 06- 17 Air Conditioning Maintenance work was done There is a proper way 8
Maintenance on the air conditioner. This of handling electrical
included cleaning the dirty equipment and
and clogged filters. electric wires. Also,
cleaning is a very
critical aspect of
electrical maintenance
and should be viewed
as such.
8|Page
28- 06- 17 Patrol and Walking through to check When any object such 8
inspection on various electrical spans. as tree lies overhead
LV/ HT lines. Growing tress can cause the electrical poles.
issues on electrical lines For us not to
which can leads low voltage experience and low
in certain areas. voltage then we need
to trim some portion
of the tree to allow
the electrical pole not
to experience any
fault.
29- 06- 17 Prepare Complains from various Spans can be brought 8
document for areas where bought, and down, if the electrical
rotten LV poles. that has to do with their poles is rotton.
poles which is getting rotten
Feeder end and needs to replace.
voltage
measurement Measuring the voltages at
at various each substation to know the
substations. level of voltage at each area.
9|Page
Week: 2
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
10 | P a g e
to the great amount of
heat. During the
expansion, air is
pushed out of the
conservator tank
through the breather.
After the oil cools
down, it contracts,
thus sucking in air
through the breather.
But to prevent the
transformer oil from
coming into contact
with moisture, the
breather is fitted with
stacks of silica gel.
These mop up any
moisture in the
atmospheric air before
it gets to the
conservator tank.
07- 07- 17 Attend At the safety meeting, a Most electrical hazards 8
mandatory lecture was presented on are caused by unsafe
weekly Safety what electric hazards are, equipment and
Meeting what may lead to such installation, unsafe
hazards, and how to environment and
prevent them. unsafe work practices.
Thus these must be
given critical attention
whenever working.
11 | P a g e
Week: 3
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
12 | P a g e
shroud. test measures the
resistance of the
insulation, thus one of
the multimeter leads
is grounded. The usual
vibration of the
transformer could
cause the shroud to
loosen, if not
tightened, it could
lead to a fatal
accident.
14- 07- 17 Attend A lecture was given In a situation where 7
mandatory concerning protection from one wants to admit
Safety injuries in the case of first aid to an injured
meeting administering first aid. person, care should be
Unit 4 Continue with test from taken that neither the
Transformer previous day as pertaining injured person nor the
Maintenance to the transformer of unit one administering the
. 4. This is winding resistance first aid is further
test and power factor test exposed to
on transformer 4. unnecessary risk. Thus
it is advised that in the
course of
administering first aid,
cover open wounds,
use protective barrier
and avoid touching
mouth eye and ear.
13 | P a g e
Week: 4
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
14 | P a g e
and optimize network transformer we can
planning, design, module to direct the technicians
perform network analysis. to go and work on it.
20- 07- 17 UNIT 4 Blow and clean the radiator During transformer 8
Transformer and fans of the transformer. operation, the
Maintenance transformer windings
gets hot. The
transformer oil in
which the windings are
immersed expand due
to the great amount of
heat. During the
expansion, air is
pushed out of the
conservator tank
through the breather.
After the oil cools
down, it contracts,
thus sucking in air
through the breather.
But to prevent the
transformer oil from
coming into contact
with moisture, the
breather is fitted with
stacks of silica gel.
These mop up any
moisture in the
atmospheric air before
it gets to the
conservator tank.
21- 07- 17 Attend At the safety meeting, a Most electrical hazards 8
mandatory lecture was presented on are caused by unsafe
weekly Safety what electric hazards are, equipment and
Meeting what may lead to such installation, unsafe
hazards, and how to environment and
prevent them. unsafe work practices.
Thus these must be
given critical attention
whenever working.
15 | P a g e
Week: 5
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
16 | P a g e
down, it contracts,
thus sucking in air
through the breather.
But to prevent the
transformer oil from
coming into contact
with moisture, the
breather is fitted with
stacks of silica gel.
These mop up any
moisture in the
atmospheric air before
it gets to the
conservator tank.
28- 07- 17 Attend At the safety meeting, a Most electrical 8
mandatory lecture was presented on hazards are caused by
weekly Safety what electric hazards are, unsafe equipment and
Meeting what may lead to such installation, unsafe
hazards, and how to environment and
prevent them. unsafe work practices.
Thus these must be
given critical attention
whenever working.
17 | P a g e
Week: 6
Department/ Section: Technical Maintenance (Electrical, Lines, eGIS and Fault Maintenance)
18 | P a g e
During the expansion,
air is pushed out of
the conservator tank
through the breather.
After the oil cools
down, it contracts,
thus sucking in air
through the breather.
But to prevent the
transformer oil from
coming into contact
with moisture, the
breather is fitted with
stacks of silica gel.
These mop up any
moisture in the
atmospheric air before
it gets to the
conservator tank.
04- 08- 17 Attend At the safety meeting, a Most electrical 8
mandatory lecture was presented on hazards are caused by
weekly Safety what electric hazards are, unsafe equipment and
Meeting what may lead to such installation, unsafe
hazards, and how to environment and
prevent them. unsafe work practices.
Thus these must be
given critical attention
whenever working.
19 | P a g e
3.2 Description of workstation
senior electrical technician and an electrical engineer. The section is headed by the
district supervisor manager. With cooperation from the commercial maintenance section,
the technicians from the technical maintenance section run routine as well as emergency
maintenance on the units. Also any electrical equipment or appliance that is used in the
site is maintained by the technical maintenance section. The section has an office, a store
room and a workshop within which can be found, lockers for storage of personal items.
Upon arrival in the morning, the staff holds a tailboard meeting to discuss the work for
the day and how best to accomplish them safely and on time, while the attachés wait in
the workshop. Upon completion of the tailboard meeting, the tasks for the day would
have been divided into groups and each group assigned a supervisor for the day. The
attachés are also divided into groups and each group assigned to a staff group for the
day’s work. Therefore, upon completion of the tailboard meeting, we go into the office,
to see which group we belong to and who the supervisor is. After that is done, you have
to change into the PPEs which include an overall, a safety boot, a helmet and a pair of
gloves when necessary, then we move out in our respective groups to our respective work
stations.
There is a lunch break at 12:00 pm till 1:00 pm after which we resume to our respective
Whiles on the job, we are encouraged to ask questions so as to get clarification on certain
things. There are also times when the supervisor may see it fit to teach us. This ensures
20 | P a g e
On every Friday, however, there is a mandatory safety meeting that is attended by all
staff. These meetings seek to educate and remind the staff of why safety should be of
prime concern to everyone and measures that should be taken to stay safe on the job.
The staff also shows great interest in what we are learning, and thus whenever a question
Similarly the excitation transformer is also opened so that tests can be run on them.
The routine maintenance also involved the preparation of document for rotten poles. Thus
there were many times during routine maintenance that we will go to inspect HV and LV
lines to check if there is a growing object such as trees not to have any effect on the lines
and transformer. I also worked with a team that maintained the battery bank of the plant
which is used for field flashing of the generator and for supplying power to the
During my attachment period I have had the opportunity to not only learn so much
academically, but also experienced and learned how essential teamwork is on the field. I
say this because, no one under any circumstance is allowed to work alone. Rather all
tasks are assigned on a group basis. For that matter, there is the need for open
systems in the first semester of level 300. This course sought to introduce us to the power
generation methods of various energy sources as well as the transmission and distribution
systems of the grid. Protection and control of power systems were also considered. Being
attached at the technical maintenance section of the hydrogenation department not only
21 | P a g e
made me get a better understanding of the various concepts by physically appreciating
them but also I learned many other things that were not covered in the lectures.
The mandatory safety meetings that we also had to attend were ones that always
enlightened and exposed to all of us very common workplace hazards and how to avoid
administered. The training I have received from these and many other lectures has also
22 | P a g e
Chapter 4 - Impact of attachment
Upon arrival at the technical maintenance section, it was evident that all of the staff are
very friendly and approachable, for this reason, it takes no time for one to start
feeling comfortable at the workplace. I thus took the advantage of the situation to
ask many questions while on the job. There were some of the staff who will
periodically quiz us on what we have learned. There were also some staff who
took personal interest in me and were very interested in what I had been able to
learn so far. They thus helped me whenever I did not understand anything.
maintenance of all the components of a unit. This maintenance has to do with the
electric power transmitting, that is the overhead and underground system. This
gave me the chance to observe and know how to fix bare conductor of copper or
distances along a route. The bare copper wire is fixed to an insulator, which is
itself fixed onto a cross-arm on the pole. The number of cross-arms carried by
pole depends on the number of wires it has to carry. Lines supports consist of:
(ii) towers
Poles that are made of wood, reinforced concrete or steel are used up to 66KV, whereas
steel towers are used for high voltages. The underground system employs
23 | P a g e
Lines insulation are installed on line supports to support anchor and insulate conductors
from ground. This help in avoiding direct contact of the conductors with poles.
Thus, any leakage through the support to the earth is stopped, and the risk of
electric shock from poles is also minimized. They are made of porcelain, glass
i. Pin insulators
Pin insulators are mounted on the poles with the help of a pin, hence, the name. They
have a groove at their top and the conductor is tied in the groove by a binding wire going
When we are using for higher voltages, the pins insulators have limitation as they
becomes bulky (due to more numbers of petticoats) and also costly. For higher voltages
Shackles insulators are used on low tension (L.T) lines. They are fixed with the poles
through nuts and bolts, with the help of cramp D-strap. They can also be used in
24 | P a g e
Lastly, the suspension insulators, these insulators are hang down from the cross arm of
poles. Most at times for each 11KV, one suspension insulators or disc is generally, used
and, they can be joined with each other for any working voltage through ball and socket
joints. In case there is a fault, the whole string need not to be replaces; only the faulty
piece is replaced.
I was able to discern that line insulators must be mechanically strong, their dielectric
strength should be high, and they should be free from internal cracks or faults.
I was introduce to know the basic types of faults in electrical system and these include
phase-to-ground and phase-to-phase faults. The phase-to-ground fault means that one or
more conductors makes electrical contact with the ground, or point of zero-volt potential,
such as a line coming in contact with a tree (which, owning to its moisture, will conduct a
current to ground). The phase-to-phase fault means that two different phases come into
direct or indirect contact with each other, for instance, if a bird with large wingspans
avoided, not only because it implies a wasteful flow of electric current, but because there
is a risk of fire or electrocution when current flows where it was not intended to go. The
object of circuit protection is to reliably detect a fault when it happens and interrupt the
power flow to it, clearing the fault. The simple protection device that can detect an
overcurrent and interrupt a circuit is the fuse. It consists of thin wire that simply melts
when the current is too high. When there is a fault on the line the fuse need to be remove
the reading on the line. If the reading is above then there is a fault on the line.
25 | P a g e
Again during my attachment I had the chance to work with the eGIS, this department as
part of its efforts to ensure data integrity, consistency and security, improve revenue
collection, reduce illegal connections, and optimize network planning, design, module to
perform network analysis. I was able to discover that in the near future we can used this
software to analyze what one is using energy for at a particular period of time.
Lastly, the size of the pole depends on the line current and the voltage drops. Electrical
cables are routed overhead on utility poles as an inexpensive way keep it insulated from
the ground and out of the way of people and vehicles. Utility poles can be made of wood,
metals, concrete. The rotten poles have effect on our lines and if care is not taken, it can
measures were put in place and also the community alert us when there is a poles that is
In future, I would like to use the software to optimize the energy used for all tasks and
this includes checking where transformers have to be placed and the fault on each line. In
that, one can use the required power needed to work on a particular time interval.
26 | P a g e
Chapter 5 Conclusion
During the first semester of the fourth year, we will be taking a course in Power Control
and Analysis. It is very much obvious that I go in with a lot more advantage since I
already have a good appreciation of the how this devices works. It is therefore safe to say
that this attachment has really had a great impact on me academically, since not only was
it able to help me understand more clearly already learnt lessons, but has also prepared
I have also observed that, the energy sector of the country is facing major challenges even
with the introduction of some major IPPs such as Sunon Asogli Power Station and
CENIT Power Station. A renewable energy development programme is one of the most
constructive, cost effective ways to address the challenges of high energy prices, energy
security, air pollution, and global climate change. Hydroelectric power, currently the
largest producer of renewable energy in Ghana has over the years proved to be a reliable
source of power. But then when one considers the fact that the plant can only operate
when the water level is within certain agreeable limits, it is encouraging to learn that the
VRA/ NEDCo is making major strides in other renewable energy sources such as wind
and solar.
27 | P a g e
References
1.
Northern Electricity Distribution Company. (2013). NEDCO- Business Plan 2013- 2017. Accra.
2. Volta River Authority,Fifty Third Annual Report & Accounts 2014, Accra, 2014.
3. www.nedco.gh.com.
28 | P a g e