INSPECTION AND TEST PLAN

Date:

Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1


Inspection
Parameter to be Inspection Control Method / Format/ Authority
Item Activity/Description Acceptance Criteria
verified Frequency Reference Records
SECL TA
Material
Reinforcement Bar Tensile Strength Every batch As per Structural Specification Mill Test Certificate MIR

Compressive strength Mix


A As per Each Grade
RCP
One Time during 2000 Coul. Lab Reports Design
Concrete Water Absorption
Trial Mix 2.5 %
Water Permeability Approval
0.30 Ml/M2/S
ISAT

Diameters & No. of Bars Each Section As per Structural Drawings Structural Drawings

Spacing Each Section ± 25mm Structural Drawings


B Reinforcement work IR
Lap Length / Anchorage
Each Section Min. 50 dia. Structural Drawings
Length

Cover Each Section Min. 2 no. Cover blocks per m2 Structural Specification

C Shuttering Material Surface Finish Each Section - Structural Specification -

MEP Fixtures Each Section - Approved Shop Drawings IR

Structural Drawings/
Dimensions Each Section ± 3mm
Specification
Structural Drawings/
D Shuttering Works Verticality Each Section ± 3mm IR
Specification

Level Each Section ± 3mm Structural Drawings

Stability Each Section Rigid Approved Shop Drawings


INSPECTION AND TEST PLAN
Date:

Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1


Inspection
Parameter to be Inspection Control Method / Format/ Authority
Item Activity/Description Acceptance Criteria
verified Frequency Reference Records
SECL TA
Surfaces Preparation
E Cleanliness Each Section Free from waste / foreign materials - -
before Concreting
Mix Proportion (Concrete Each truck on Delivery
As per Specification Structural Specification
Grade) Arrival Order

Each truck on
Workability (Slump test) As per Approved Mix Design Structural Specification -
Arrival
F Concrete
Each truck on
Temperature Max. 32°C Structural Specification -
Arrival
Compression Strength Cube test
Each location Not less than the specified values Structural Specification
(Cube test at 7 & 28 days) results
Delivery less than 2 hours from As per Approved Method Delivery
Concrete Duration Each truck
batching time Statement Tickets

Compaction Each Section Usage of vibrator in all areas Structural Specification -

Finish Level Each Section Uniform & ± 4mm Structural Specification -


G Placing
Protection from direct Fully covered with hessian cloth and
Each Section Structural Specification -
sunlight polythene

Watering for 7 days or use of


Curing Each Section Structural Specification -
approved curing compound

LEGEND : LA - LOCAL AUTHORITY H - HOLD W- WITNESS INSPECTION S - SURVEILLANCE INSPECTION R - REVIEW A - PPROVAL