CASE STUDY 5

POTENTIAL ANSWER

a) What is the major problem here and what do you think is the root cause?
o Lack of communication by Social Sub Committee
o No passing information by the Social Sub Committee to Ngo (The Project In
charge)
o Delayed work (Promotional Materials not coming rapidly)
o Physical and Logistics activities were behind schedule
o Ngo did not take responsibility of completion of work by Social Sub Committee
o No authority (Felt it interference)
o Ngo sent brief report to project team and Association of Social Sub Committee

b) How could it have been avoided?


‐ Ngo should have worked out a detailed working schedule with the project team;
‐ Ngo should have developed project’s work break down structure
‐ Should have mentioned tasks due at specified time with detailed milestones
‐ Ngo should have developed proper progress reporting schedule and arranged meetings
for updates
‐ Social Sub Committee should have communicated well with each accomplishment of
their own activities to Ngo and Project Manager