Project Name : White Nile

Project No : E3979
Engineer : Jafta Blennis
Date :
Client Order No :
Contract No :
DOC NO. Draft
CONSOLIDATED POWER PROJECTS
PROTECTION & AUTOMATION

DOC NO. Draft REV 0 DATE 19/07/2006

SUBJECT WRITTEN D MEYER

REVIEWED A.RICHELMANN
FACTORY ACCEPTANCE TESTING
CHECK SHEET
APPROVED

Project Name : White Nile Project No : E3979

Client Order No : Contract No :

Engineer : Jafta Blennis Date :

Factory Acceptance Secondary Testing


Description Yes No N/A
1 Continuity testing of schemes

2 Relay specific logics uploaded on to the Relays as per designs

3 Relay specific logics tested to be correct as per designs

4 Functional testing of schemes as per design

5 Settings received and implemented

6 Secondary injection of Relays

7 SCADA - Gateway tested

8 SCADA - HMI set up and tested

9 GOOSE connections functional

Scheme Specific Deviations


Description

Project Engineer Signature FAT Engineer Signature

10/18/2018 Page 3 of 4
CONSOLIDATED POWER PROJECTS
PROTECTION & AUTOMATION

DOC NO. Draft REV 0 DATE 19/07/2006

SUBJECT WRITTEN D MEYER

REVIEWED A.RICHELMANN
FACTORY ACCEPTANCE TESTING
CHECK SHEET
APPROVED

Project Name : White Nile Project No : E3979

Client Order No : Contract No :

Engineer : Jafta Blennis Date :

Scheme Specific Deviations


Description PM / DE FE

Project Engineer Signature FAT Engineer Signature

10/18/2018 Page 4 of 4