ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
1 Overall Project Duration 154 daysFri 07-07-17 Thu 07-12-17
2 LOI Date 1 day Fri 07-07-17 Fri 07-07-17 LOI Date
3 Kick of Meeting 1 day Wed 12-07-17 Wed 12-07-17 Kick of Meeting
4 Project Milestone 122 daysTue 08-08-17 Thu 07-12-17
5 Start in Mainline Welding 74 days Tue 08-08-17 Fri 20-10-17
6 Completion of Mainline Welding - 51 days Tue 08-08-17 Wed 27-09-17 Completion of Mainline Welding - AWP-05 to AWP-
AWP-05 to AWP-02
7 Completion of Mainline Welding - 69 days Sun 13-08-17 Fri 20-10-17 Completion of Mainline Welding - AWP-03 to
AWP-03 to AWP-06
8 Hydrotesting of Mainline for AWP - 05 15 days Wed 18-10-17 Wed 01-11-17 Hydrotesting of Mainline for AWP - 05 to A
to AWP - 02
9 Hydrotesting of Mainline for AWP - 03 18 days Thu 02-11-17 Sun 19-11-17 Hydrotesting of Mainline for AWP - 03
to AWP - 06
10 RFSU Completion 17 days Mon 20-11-17 Wed 06-12-17 RFSU Completion
11 Overall Commissioning and Handover 1 day Thu 07-12-17 Thu 07-12-17 Overall Commissioning and Hando
148 WPS, PQR / Welder Qualification 32 days Sun 13-08-17 Wed 13-09-17
149 Issueing of Free Issue Materials 5 days Wed 16-08-17 Sun 20-08-17 Issueing of Free Issue Materials