Production Fluid Pipelines and Station Works for ABH Phase 1

ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
1 Overall Project Duration 154 daysFri 07-07-17 Thu 07-12-17
2 LOI Date 1 day Fri 07-07-17 Fri 07-07-17 LOI Date
3 Kick of Meeting 1 day Wed 12-07-17 Wed 12-07-17 Kick of Meeting
4 Project Milestone 122 daysTue 08-08-17 Thu 07-12-17
5 Start in Mainline Welding 74 days Tue 08-08-17 Fri 20-10-17
6 Completion of Mainline Welding - 51 days Tue 08-08-17 Wed 27-09-17 Completion of Mainline Welding - AWP-05 to AWP-
AWP-05 to AWP-02
7 Completion of Mainline Welding - 69 days Sun 13-08-17 Fri 20-10-17 Completion of Mainline Welding - AWP-03 to
AWP-03 to AWP-06
8 Hydrotesting of Mainline for AWP - 05 15 days Wed 18-10-17 Wed 01-11-17 Hydrotesting of Mainline for AWP - 05 to A
to AWP - 02
9 Hydrotesting of Mainline for AWP - 03 18 days Thu 02-11-17 Sun 19-11-17 Hydrotesting of Mainline for AWP - 03
to AWP - 06
10 RFSU Completion 17 days Mon 20-11-17 Wed 06-12-17 RFSU Completion
11 Overall Commissioning and Handover 1 day Thu 07-12-17 Thu 07-12-17 Overall Commissioning and Hando

12 Approval Of Procedures & ITP's 52 days Fri 07-07-17 Sun 27-08-17


13 Submission of WPS 2 days Sun 23-07-17 Mon 24-07-17 Submission of WPS
14 Submission of QAP 2 days Wed 09-08-17 Thu 10-08-17 Submission of QAP
15 Submission of Job Procedures 31 days Fri 28-07-17 Sun 27-08-17
33 HSE Plan 5 days Wed 02-08-17 Sun 06-08-17 HSE Plan
34 Job Safety Analisys 5 days Wed 02-08-17 Sun 06-08-17 Job Safety Analisys
35 Method Statement 10 days Wed 02-08-17 Fri 11-08-17 Method Statement
36 Submission of Manpower & 2 days Fri 07-07-17 Sat 08-07-17 Submission of Manpower & Machineries Mobilization Plan
Machineries Mobilization Plan

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
37 Submission of Project Schedule for 5 days Fri 07-07-17 Tue 11-07-17 Submission of Project Schedule for Approval
Approval
38 Submission of As Built Drawings 15 days Fri 07-07-17 Fri 21-07-17 Submission of As Built Drawings
39 Submission of Project Close out report 10 days Fri 07-07-17 Sun 16-07-17 Submission of Project Close out report

40 Mobilization 35 days Tue 18-07-17 Mon 21-08-17


41 Office, Camp, Storage Yard setup 15 days Tue 18-07-17 Tue 01-08-17 Office, Camp, Storage Yard setup
42 Manpower Mobilization 20 days Wed 02-08-17 Mon 21-08-17
43 Worker Camp setup 10 days Wed 02-08-17 Fri 11-08-17 Worker Camp setup
44 CSR & HR Verification 3 days Sat 12-08-17 Mon 14-08-17 CSR & HR Verification
45 Medical & HSE Induction 3 days Tue 15-08-17 Thu 17-08-17 Medical & HSE Induction
46 Security signature/Access card 2 days Fri 18-08-17 Sat 19-08-17 Security signature/Access card
47 Issueing of gate pass 2 days Sun 20-08-17 Mon 21-08-17 Issueing of gate pass
48 Machinaries Mobilization 18 days Wed 02-08-17 Sat 19-08-17
49 Mobilization of Machineries 15 days Wed 02-08-17 Wed 16-08-17 Mobilization of Machineries
50 Inspection & Tagging of Machineries 5 days Tue 15-08-17 Sat 19-08-17 Inspection & Tagging of Machineries

51 Procurement 117 daysTue 18-07-17 Sat 11-11-17


52 Pipeline Materials 117 daysTue 18-07-17 Sat 11-11-17
53 LR Bends 56 days Tue 18-07-17 Mon 11-09-17
54 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
55 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
56 Delivery at site/ Store 26 days Thu 17-08-17 Mon 11-09-17 Delivery at site/ Store
57 Anchor Flange 68 days Tue 18-07-17 Sat 23-09-17
58 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
59 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
60 Delivery at site/ Store 38 days Thu 17-08-17 Sat 23-09-17 Delivery at site/ Store
61 Monolithic Insulation Joint 117 daysTue 18-07-17 Sat 11-11-17
62 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
63 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
64 Delivery at site/ Store 87 days Thu 17-08-17 Sat 11-11-17 Delivery at site/ Store
65 Barred Tee 103 daysTue 18-07-17 Sat 28-10-17
66 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
67 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
68 Delivery at site/ Store 73 days Thu 17-08-17 Sat 28-10-17 Delivery at site/ Store
69 Pipeline Isolation Valve 117 daysTue 18-07-17 Sat 11-11-17
70 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
71 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
72 Delivery at site/ Store 87 days Thu 17-08-17 Sat 11-11-17 Delivery at site/ Store
73 Pipeline Markers 69 days Tue 18-07-17 Sun 24-09-17
74 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
75 PO Placement 10 days Sat 12-08-17 Mon 21-08-17 PO Placement
76 Delivery at site/ Store 34 days Tue 22-08-17 Sun 24-09-17 Delivery at site/ Store
77 Warning Signs 69 days Tue 18-07-17 Sun 24-09-17
78 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
79 PO Placement 10 days Sat 12-08-17 Mon 21-08-17 PO Placement
80 Delivery at site/ Store 34 days Tue 22-08-17 Sun 24-09-17 Delivery at site/ Store
81 Piping Materials 116 daysTue 18-07-17 Fri 10-11-17
82 Painting Material 73 days Tue 18-07-17 Thu 28-09-17
83 Selection of Vendors 20 days Tue 18-07-17 Sun 06-08-17 Selection of Vendors

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
84 PO Placement 8 days Mon 07-08-17 Mon 14-08-17 PO Placement
85 Delivery at site/ Store 45 days Tue 15-08-17 Thu 28-09-17 Delivery at site/ Store
86 Insulation and Cladding Items 60 days Tue 18-07-17 Fri 15-09-17
87 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
88 PO Placement 10 days Sat 12-08-17 Mon 21-08-17 PO Placement
89 Delivery at site/ Store 25 days Tue 22-08-17 Fri 15-09-17 Delivery at site/ Store
90 Pressure Safety Valves 116 daysTue 18-07-17 Fri 10-11-17
91 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
92 PO Placement 5 days Sat 12-08-17 Wed 16-08-17 PO Placement
93 Delivery at site/ Store 86 days Thu 17-08-17 Fri 10-11-17 Delivery at site/ Store
94 Flanges & Fittings 52 days Tue 18-07-17 Thu 07-09-17
95 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
96 PO Placement 3 days Sat 12-08-17 Mon 14-08-17 PO Placement
97 Delivery at site/ Store 24 days Tue 15-08-17 Thu 07-09-17 Delivery at site/ Store
98 Bolts & Studs 52 days Tue 18-07-17 Thu 07-09-17
99 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
100 PO Placement 3 days Sat 12-08-17 Mon 14-08-17 PO Placement
101 Delivery at site/ Store 24 days Tue 15-08-17 Thu 07-09-17 Delivery at site/ Store
102 Gaskets 73 days Tue 18-07-17 Thu 28-09-17
103 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
104 PO Placement 3 days Sat 12-08-17 Mon 14-08-17 PO Placement
105 Delivery at site/ Store 45 days Tue 15-08-17 Thu 28-09-17 Delivery at site/ Store
106 Electrical & Instrumentation Materials 53 days Tue 18-07-17 Fri 08-09-17

107 Instrumentation Fitting 53 days Tue 18-07-17 Fri 08-09-17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
108 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
109 PO Placement 4 days Sat 12-08-17 Tue 15-08-17 PO Placement
110 Delivery at site/ Store 24 days Wed 16-08-17 Fri 08-09-17 Delivery at site/ Store
111 Pressure Instruments 53 days Tue 18-07-17 Fri 08-09-17
112 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
113 PO Placement 4 days Sat 12-08-17 Tue 15-08-17 PO Placement
114 Delivery at site/ Store 24 days Wed 16-08-17 Fri 08-09-17 Delivery at site/ Store
115 Temperature Instruments 53 days Tue 18-07-17 Fri 08-09-17
116 Selection of Vendors 25 days Tue 18-07-17 Fri 11-08-17 Selection of Vendors
117 PO Placement 4 days Sat 12-08-17 Tue 15-08-17 PO Placement
118 Delivery at site/ Store 24 days Wed 16-08-17 Fri 08-09-17 Delivery at site/ Store
119 Tools n Tackles & Consumables 23 days Wed 02-08-17 Thu 24-08-17
120 Selection of Local Vendor 5 days Wed 02-08-17 Sun 06-08-17 Selection of Local Vendor
121 Procuring of Tools n Tackles & 18 days Mon 07-08-17 Thu 24-08-17 Procuring of Tools n Tackles & Consumables
Consumables
122 Welding Consumables 21 days Wed 02-08-17 Tue 22-08-17
123 Selection of Vendors 5 days Wed 02-08-17 Sun 06-08-17 Selection of Vendors
124 PO Placement 2 days Mon 07-08-17 Tue 08-08-17 PO Placement
125 Delivery at site / store 14 days Wed 09-08-17 Tue 22-08-17 Delivery at site / store
126 Joint Coating Materials 28 days Wed 02-08-17 Tue 29-08-17
127 Selection of Vendors 5 days Wed 02-08-17 Sun 06-08-17 Selection of Vendors
128 PO Placement 5 days Mon 07-08-17 Fri 11-08-17 PO Placement
129 Delivery at site/ Store 18 days Sat 12-08-17 Tue 29-08-17 Delivery at site/ Store
130 Issuence of All Drawings from CIL 2 days Wed 02-08-17 Thu 03-08-17
131 Alignment Sheet 2 days Wed 02-08-17 Thu 03-08-17 Alignment Sheet

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
132 GAD and P&ID's for all Well Pads 2 days Wed 02-08-17 Thu 03-08-17 GAD and P&ID's for all Well Pads
133 Isometric Drawings (IFC) for all well 2 days Wed 02-08-17 Thu 03-08-17 Isometric Drawings (IFC) for all well pads
pads
134 Issuence of Free Issue Materials 75 days Sun 06-08-17 Thu 19-10-17
135 Piping Materials 24 days Sun 13-08-17 Tue 05-09-17
136 Submission of MIV 2 days Sun 13-08-17 Mon 14-08-17 Submission of MIV
137 Issuence of Materials 10 days Sun 20-08-17 Tue 29-08-17 Issuence of Materials
138 Shortages as per drawing/FIM list (If 5 days Wed 30-08-17 Sun 03-09-17 Shortages as per drawing/FIM list (If any)
any)
139 Status of Shortage materials (If any) 2 days Mon 04-09-17 Tue 05-09-17 Status of Shortage materials (If any)

140 Pipeline Materials 70 days Sun 06-08-17 Sat 14-10-17


141 Handing Over of Pipes (FIM) for 20 days Sun 06-08-17 Fri 25-08-17 Handing Over of Pipes (FIM) for AWP-05 to AWP-02
AWP-05 to AWP-02
142 Handing Over of Pipes (FIM) for 20 days Mon 25-09-17 Sat 14-10-17 Handing Over of Pipes (FIM) for AWP-03 to AW
AWP-03 to AWP-06
143 Instrumentation and Electrical 43 days Thu 07-09-17 Thu 19-10-17
Materials
144 Submission of MIV 2 days Tue 03-10-17 Wed 04-10-17 Submission of MIV
145 Issuence of Materials 10 days Tue 10-10-17 Thu 19-10-17 Issuence of Materials
146 Shortages as per FIM list (If any) 2 days Thu 07-09-17 Fri 08-09-17 Shortages as per FIM list (If any)
147 Status of Shortages of FIM's (If any) 2 days Sat 09-09-17 Sun 10-09-17 Status of Shortages of FIM's (If any)

148 WPS, PQR / Welder Qualification 32 days Sun 13-08-17 Wed 13-09-17
149 Issueing of Free Issue Materials 5 days Wed 16-08-17 Sun 20-08-17 Issueing of Free Issue Materials

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
150 Using of Existing qualified welders for 5 days Sun 13-08-17 Thu 17-08-17 Using of Existing qualified welders for Piping Works
Piping Works
151 Preperation for WQT (Test Piece) 1 day Fri 18-08-17 Fri 18-08-17 Preperation for WQT (Test Piece)
152 Perform / Qualification for Pipeline 5 days Sat 19-08-17 Wed 23-08-17 Perform / Qualification for Pipeline Welders
Welders
153 Destructive Test 10 days Fri 25-08-17 Sun 03-09-17 Destructive Test
154 Submission of Destructive Test reports 5 days Sat 09-09-17 Wed 13-09-17 Submission of Destructive Test reports

155 Mainline Construction 74 days Tue 08-08-17 Fri 20-10-17


156 Mainline Construction for AWP - 05 51 days Tue 08-08-17 Wed 27-09-17
to AWP - 02
157 Route Survey 5 days Tue 08-08-17 Sat 12-08-17 Route Survey
158 ROW Clearing and Grading 5 days Tue 15-08-17 Sat 19-08-17 ROW Clearing and Grading
159 Stringing 8 days Sun 20-08-17 Sun 27-08-17 Stringing
160 Mainline Welding 15 days Wed 23-08-17 Wed 06-09-17 Mainline Welding
161 Radiography Test 10 days Tue 29-08-17 Thu 07-09-17 Radiography Test
162 Field Joint Coating 10 days Fri 01-09-17 Sun 10-09-17 Field Joint Coating
163 Trenching 10 days Sat 02-09-17 Mon 11-09-17 Trenching
164 Lowering 5 days Sun 10-09-17 Thu 14-09-17 Lowering
165 Backfilling 7 days Thu 14-09-17 Wed 20-09-17 Backfilling
166 Tie-In Welding for AWP - 05 to AWP 13 days Fri 15-09-17 Wed 27-09-17
- 02
167 Tie-In Welding 8 days Fri 15-09-17 Fri 22-09-17 Tie-In Welding
168 Ultrasonic Testing 7 days Sun 17-09-17 Sat 23-09-17 Ultrasonic Testing
169 Field Joint Coating 6 days Tue 19-09-17 Sun 24-09-17 Field Joint Coating
170 Backfilling & Restoration 3 days Mon 25-09-17 Wed 27-09-17 Backfilling & Restoration

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
171 Mainline Construction for AWP - 03 69 days Sun 13-08-17 Fri 20-10-17
to AWP - 06
172 Route Survey 5 days Sun 13-08-17 Thu 17-08-17 Route Survey
173 ROW Clearing and Grading 10 days Sun 20-08-17 Tue 29-08-17 ROW Clearing and Grading
174 Stringing 12 days Tue 29-08-17 Sat 09-09-17 Stringing
175 Mainline Welding 25 days Fri 08-09-17 Mon 02-10-17 Mainline Welding
176 Radiography Test 24 days Sun 10-09-17 Tue 03-10-17 Radiography Test
177 Field Joint Coating 25 days Mon 11-09-17 Thu 05-10-17 Field Joint Coating
178 Trenching 20 days Thu 14-09-17 Tue 03-10-17 Trenching
179 Lowering 18 days Wed 20-09-17 Sat 07-10-17 Lowering
180 Backfilling 15 days Sat 30-09-17 Sat 14-10-17 Backfilling
181 Tie-In Welding for AWP - 03 to AWP 18 days Tue 03-10-17 Fri 20-10-17
- 06
182 Tie-In Welding 12 days Tue 03-10-17 Sat 14-10-17 Tie-In Welding
183 Ultrasonic Testing 9 days Sun 08-10-17 Mon 16-10-17 Ultrasonic Testing
184 Field Joint Coating 10 days Mon 09-10-17 Wed 18-10-17 Field Joint Coating
185 Backfilling & Restoration 8 days Fri 13-10-17 Fri 20-10-17 Backfilling & Restoration
186 Marker Installation 53 days Fri 15-09-17 Mon 06-11-17
187 Procurment of Materials 10 days Fri 15-09-17 Sun 24-09-17 Procurment of Materials
188 Fabrication of Markers 20 days Wed 27-09-17 Mon 16-10-17 Fabrication of Markers
189 Installation of Markers 20 days Wed 18-10-17 Mon 06-11-17 Installation of Markers
190 Hydrotesting 33 days Wed 18-10-17 Sun 19-11-17
191 Hydrotesting of Mainline from AWP - 15 days Wed 18-10-17 Wed 01-11-17
05 to AWP - 02
192 Cleaning / Flushing 3 days Wed 18-10-17 Fri 20-10-17 Cleaning / Flushing

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
193 Gauging 2 days Sat 21-10-17 Sun 22-10-17 Gauging
194 Pigging 2 days Mon 23-10-17 Tue 24-10-17 Pigging
195 Filling / Hydrotesting 4 days Wed 25-10-17 Sat 28-10-17 Filling / Hydrotesting
196 Dewatering 2 days Sun 29-10-17 Mon 30-10-17 Dewatering
197 Air Drying 2 days Tue 31-10-17 Wed 01-11-17 Air Drying
198 Hydrotesting of Mainline from AWP - 18 days Thu 02-11-17 Sun 19-11-17
05 to AWP - 02
199 Cleaning / Flushing 3 days Thu 02-11-17 Sat 04-11-17 Cleaning / Flushing
200 Gauging 2 days Sun 05-11-17 Mon 06-11-17 Gauging
201 Pigging 2 days Tue 07-11-17 Wed 08-11-17 Pigging
202 Filling / Hydrotesting 4 days Thu 09-11-17 Sun 12-11-17 Filling / Hydrotesting
203 Dewatering 2 days Mon 13-11-17 Tue 14-11-17 Dewatering
204 Air Drying 2 days Wed 15-11-17 Thu 16-11-17 Air Drying
205 Submission of Hydrotest Completion 3 days Fri 17-11-17 Sun 19-11-17 Submission of Hydrotest Completion d
documents for CIL approval

206 Civil Activities 49 days Mon 04-09-17 Sun 22-10-17


207 Civil Activities for AWP - 05 25 days Mon 04-09-17 Thu 28-09-17
208 PLR Foundation 12 days Mon 04-09-17 Fri 15-09-17 PLR Foundation
209 Support Foundation 5 days Sat 16-09-17 Wed 20-09-17 Support Foundation
210 Anchor Blocks 8 days Thu 21-09-17 Thu 28-09-17 Anchor Blocks
211 Civil Activities for AWP - 02 21 days Sat 16-09-17 Fri 06-10-17
212 PLR Foundation 12 days Sat 16-09-17 Wed 27-09-17 PLR Foundation
213 Support Foundation 5 days Thu 21-09-17 Mon 25-09-17 Support Foundation
214 Anchor Blocks 8 days Fri 29-09-17 Fri 06-10-17 Anchor Blocks

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
215 Civil Activities for AWP - 03 19 days Tue 26-09-17 Sat 14-10-17
216 PLR Foundation 12 days Thu 28-09-17 Mon 09-10-17 PLR Foundation
217 Support Foundation 5 days Tue 26-09-17 Sat 30-09-17 Support Foundation
218 Anchor Blocks 8 days Sat 07-10-17 Sat 14-10-17 Anchor Blocks
219 Civil Activities for AWP - 06 22 days Sun 01-10-17 Sun 22-10-17
220 PLR Foundation 12 days Tue 10-10-17 Sat 21-10-17 PLR Foundation
221 Support Foundation 5 days Sun 01-10-17 Thu 05-10-17 Support Foundation
222 Anchor Blocks 8 days Sun 15-10-17 Sun 22-10-17 Anchor Blocks
223 Piping Construction 68 days Fri 18-08-17 Tue 24-10-17 Piping Construction
224 Piping Works for AWP - 05 42 days Fri 18-08-17 Thu 28-09-17
225 Fabrication of Piping Spools 12 days Fri 18-08-17 Tue 29-08-17 Fabrication of Piping Spools
226 PLR Installation 5 days Wed 23-08-17 Sun 27-08-17 PLR Installation
227 Piping Erection 10 days Mon 28-08-17 Wed 06-09-17 Piping Erection
228 Supports / Structure fabrication 10 days Wed 23-08-17 Fri 01-09-17 Supports / Structure fabrication
229 Supports / Structure Erection 5 days Sat 02-09-17 Wed 06-09-17 Supports / Structure Erection
230 Radiography 5 days Thu 07-09-17 Mon 11-09-17 Radiography
231 Hydrotesting 5 days Tue 12-09-17 Sat 16-09-17 Hydrotesting
232 Reinstatement 3 days Sun 17-09-17 Tue 19-09-17 Reinstatement
233 Insulation 12 days Sun 17-09-17 Thu 28-09-17 Insulation
234 Piping Works for AWP - 02 42 days Fri 18-08-17 Thu 28-09-17
235 Fabrication of Piping Spools 15 days Fri 18-08-17 Fri 01-09-17 Fabrication of Piping Spools
236 PLR Installation 5 days Wed 23-08-17 Sun 27-08-17 PLR Installation
237 Piping Erection 10 days Mon 28-08-17 Wed 06-09-17 Piping Erection
238 Supports / Structure fabrication 10 days Wed 23-08-17 Fri 01-09-17 Supports / Structure fabrication
239 Supports / Structure Erection 5 days Sat 02-09-17 Wed 06-09-17 Supports / Structure Erection

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
240 Radiography 5 days Thu 07-09-17 Mon 11-09-17 Radiography
241 Hydrotesting 5 days Tue 12-09-17 Sat 16-09-17 Hydrotesting
242 Reinstatement 3 days Sun 17-09-17 Tue 19-09-17 Reinstatement
243 Insulation 12 days Sun 17-09-17 Thu 28-09-17 Insulation
244 Piping Works for AWP - 03 42 days Tue 12-09-17 Mon 23-10-17
245 Fabrication of Piping Spools 15 days Tue 12-09-17 Tue 26-09-17 Fabrication of Piping Spools
246 PLR Installation 5 days Sun 17-09-17 Thu 21-09-17 PLR Installation
247 Piping Erection 10 days Fri 22-09-17 Sun 01-10-17 Piping Erection
248 Supports / Structure fabrication 10 days Sun 17-09-17 Tue 26-09-17 Supports / Structure fabrication
249 Supports / Structure Erection 5 days Wed 27-09-17 Sun 01-10-17 Supports / Structure Erection
250 Radiography 5 days Mon 02-10-17 Fri 06-10-17 Radiography
251 Hydrotesting 5 days Sat 07-10-17 Wed 11-10-17 Hydrotesting
252 Reinstatement 3 days Thu 12-10-17 Sat 14-10-17 Reinstatement
253 Insulation 12 days Thu 12-10-17 Mon 23-10-17 Insulation
254 Piping Works for AWP - 06 42 days Wed 13-09-17 Tue 24-10-17
255 Fabrication of Piping Spools 15 days Wed 13-09-17 Wed 27-09-17 Fabrication of Piping Spools
256 PLR Installation 5 days Mon 18-09-17 Fri 22-09-17 PLR Installation
257 Piping Erection 10 days Sat 23-09-17 Mon 02-10-17 Piping Erection
258 Supports / Structure fabrication 10 days Mon 18-09-17 Wed 27-09-17 Supports / Structure fabrication
259 Supports / Structure Erection 5 days Thu 28-09-17 Mon 02-10-17 Supports / Structure Erection
260 Radiography 5 days Tue 03-10-17 Sat 07-10-17 Radiography
261 Hydrotesting 5 days Sun 08-10-17 Thu 12-10-17 Hydrotesting
262 Reinstatement 3 days Fri 13-10-17 Sun 15-10-17 Reinstatement
263 Insulation 12 days Fri 13-10-17 Tue 24-10-17 Insulation
264 Electrical & Instrumentation Work 29 days Wed 18-10-17 Wed 15-11-17
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
265 Electrical & Instrumentation work at 14 days Wed 18-10-17 Tue 31-10-17
AWP - 05
266 Earthing 3 days Wed 18-10-17 Fri 20-10-17 Earthing
267 Lighting Fixture Installation 5 days Sat 21-10-17 Wed 25-10-17 Lighting Fixture Installation
268 Lighting Cable Laying 4 days Mon 23-10-17 Thu 26-10-17 Lighting Cable Laying
269 Instrument Installation 4 days Fri 27-10-17 Mon 30-10-17 Instrument Installation
270 Instrument Cable Laying 4 days Sat 28-10-17 Tue 31-10-17 Instrument Cable Laying
271 Electrical & Instrumentation work at 14 days Wed 18-10-17 Tue 31-10-17
AWP - 02
272 Earthing 3 days Wed 18-10-17 Fri 20-10-17 Earthing
273 Lighting Fixture Installation 5 days Sat 21-10-17 Wed 25-10-17 Lighting Fixture Installation
274 Lighting Cable Laying 4 days Mon 23-10-17 Thu 26-10-17 Lighting Cable Laying
275 Instrument Installation 4 days Fri 27-10-17 Mon 30-10-17 Instrument Installation
276 Instrument Cable Laying 4 days Sat 28-10-17 Tue 31-10-17 Instrument Cable Laying
277 Electrical & Instrumentation work at 15 days Wed 01-11-17 Wed 15-11-17
AWP - 03
278 Earthing 3 days Wed 01-11-17 Fri 03-11-17 Earthing
279 Lighting Fixture Installation 5 days Sat 04-11-17 Wed 08-11-17 Lighting Fixture Installation
280 Lighting Cable Laying 4 days Mon 06-11-17 Thu 09-11-17 Lighting Cable Laying
281 Instrument Installation 4 days Fri 10-11-17 Mon 13-11-17 Instrument Installation
282 Instrument Cable Laying 4 days Sun 12-11-17 Wed 15-11-17 Instrument Cable Laying
283 Electrical & Instrumentation work at 15 days Wed 01-11-17 Wed 15-11-17
AWP - 06
284 Earthing 3 days Wed 01-11-17 Fri 03-11-17 Earthing
285 Lighting Fixture Installation 5 days Sat 04-11-17 Wed 08-11-17 Lighting Fixture Installation

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only


Production Fluid Pipelines and Station Works for ABH Phase 1
ID Task Name Duration Start Finish 08 May '17 19 Jun '17 31 Jul '17 11 Sep '17 23 Oct '17 04 Dec '17 15 Jan '18 26 Feb '18 09 Ap
T M F T S W S T M F T S W S T M F T
286 Lighting Cable Laying 4 days Mon 06-11-17 Thu 09-11-17 Lighting Cable Laying
287 Instrument Installation 4 days Fri 10-11-17 Mon 13-11-17 Instrument Installation
288 Instrument Cable Laying 4 days Sun 12-11-17 Wed 15-11-17 Instrument Cable Laying
289 Interface by Client 5 days Thu 16-11-17 Mon 20-11-17
290 EHT Installation 5 days Thu 16-11-17 Mon 20-11-17 EHT Installation
291 Pre-Commissioning & Commissioning 17 days Tue 21-11-17 Thu 07-12-17
292 CCC 2 days Tue 21-11-17 Wed 22-11-17 CCC
293 System walkdown & Punch list 5 days Thu 23-11-17 Mon 27-11-17 System walkdown & Punch list Clear
Clearance
294 Cold loop Checks 2 days Tue 28-11-17 Wed 29-11-17 Cold loop Checks
295 Hot Loop checks 2 days Thu 30-11-17 Fri 01-12-17 Hot Loop checks
296 MCC 1 day Sat 02-12-17 Sat 02-12-17 MCC
297 Leak Test 2 days Sun 03-12-17 Mon 04-12-17 Leak Test
298 C & E Checks 1 day Tue 05-12-17 Tue 05-12-17 C & E Checks
299 RFSU 1 day Wed 06-12-17 Wed 06-12-17 RFSU
300 SAC 1 day Thu 07-12-17 Thu 07-12-17 SAC

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: Production Fluid Pipelines and Station Milestone Duration-only Deadline


Works for ABH Phase 1 Summary Manual Summary Rollup Progress
Contrator: OVAL Projects Enigineering Pvt Ltd
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only