Sistema de Tuberías Enmalladas - Método de Hardy Cross - Darcy - Weisbach

Ѵ 1.01E-06

Primera Iteración

Malla Tubería L (m) D (m) e (m) K A (m2) Q (m3/s) V (m/s) Re f Rf RL R H H/Q ∆Q Q (m3/s)
1 500 0.300 0.00015 0 0.070686 0.030 0.4244 1.26E+05 0.020 3.38E+02 0.00E+00 3.38E+02 0.304 10.1429 0.0384
3 50 0.150 0.00015 10 0.0176715 0.0100 0.5659 8.43E+04 0.023 1.25E+03 1.63E+03 2.88E+03 0.288 28.8042 0.0120
I 0.00845
2 600 0.250 0.00015 0 0.0490875 -0.0450 0.9167 2.28E+05 0.019 9.88E+02 0.00E+00 9.88E+02 -2.001 44.4769 -0.0366
Ficticia
Suma -1.409 83.424
4 200 0.250 0.00015 2 0.0490875 0.0200 0.4074 1.01E+05 0.021 3.53E+02 4.23E+01 3.96E+02 0.158 7.91312 0.0265
II 5 200 0.300 0.00015 2 0.070686 -0.0550 0.7781 2.32E+05 0.019 1.28E+02 2.04E+01 1.49E+02 -0.450 8.17404 0.00645 -0.0485
3 50 0.150 0.00015 10 0.0176715 -0.0100 0.5659 8.43E+04 0.023 1.25E+03 1.63E+03 2.88E+03 -0.288 28.8042 -0.0120
Suma -0.579 44.891
Iteración Final
Malla Tubería L (m) D (m) e (m) K A (m )
2
Q (m /s) V (m/s)
3
Re f Rf RL R H H/Q ∆Q Q (m3/s)
1 500 0.300 0.00015 0 0.070686 0.045 0.6379 1.90E+05 0.019 3.25E+02 0.00E+00 3.25E+02 0.662 14.6726 0.0451
3 50 0.150 0.00015 10 0.0176715 0.0093 0.5260 7.84E+04 0.023 1.26E+03 1.63E+03 2.89E+03 0.250 26.8558 0.0093
I 3E-06
2 600 0.250 0.00015 0 0.0490875 -0.0299 0.6093 1.51E+05 0.020 1.02E+03 0.00E+00 1.02E+03 -0.912 30.4783 -0.0299
Ficticia
Suma 0.000 72.007
4 200 0.250 0.00015 2 0.0490875 0.0358 0.7292 1.81E+05 0.020 3.35E+02 4.23E+01 3.77E+02 0.483 13.4974 0.0358
II 5 200 0.300 0.00015 2 0.070686 -0.0392 0.5547 1.65E+05 0.019 1.32E+02 2.04E+01 1.52E+02 -0.234 5.96525 4E-06 -0.0392
3 50 0.150 0.00015 10 0.0176715 -0.0093 0.5260 7.84E+04 0.023 1.26E+03 1.63E+03 2.89E+03 -0.250 26.8558 -0.0093
Suma 0.000 46.319