PROJECT DESCRIPTION :
Scope of Work : Construction
I. ESTIMATED COST
A. DIRECT COST
Prepared: Submitted:
CAYAMOMBAO D. DIA
OIC- Assistant Regional Director
Approved:
MARK-UPS IN
ESTIMATED DIRECT TOTAL MARK-UPS TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT TOTAL COST UNIT COST
COST COST
OCM PROFIT % VALUE
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5) + (9] (9) + (10) (5) + (11) (12) / (3)
101 Removal of Existing Structure 1.00 L.S 11,727.58 12.00 10.00 22.00 2,580.07 715.38 3,295.45 15,023.04 15,023.04
401 Railings (Including Sun Breaker) 1.00 L.S 219,496.60 12.00 10.00 22.00 48,289.25 13,389.29 61,678.54 281,175.14 281,175.14
403 (a) Steel Trusses 2,620.00 kgs. 285,719.57 12.00 10.00 22.00 62,858.31 17,428.89 80,287.20 366,006.77 139.70
404 Reinforcing Steel 13,190.00 kgs. 775,126.00 12.00 10.00 22.00 170,527.72 47,282.69 217,810.41 992,936.41 75.28
405 Structural Concrete (Class "A") 21 Mpa 82.00 cu. m. 376,648.38 12.00 10.00 22.00 82,862.64 22,975.55 105,838.19 482,486.57 5,883.98
414 Forms and Falsework 1.00 L.S 291,073.40 12.00 10.00 22.00 64,036.15 17,755.48 81,791.63 372,865.03 372,865.03
506(1) Masonry Works (Concrete Hollow Blocks) 250.00 cu. m. 135,664.82 12.00 10.00 22.00 29,846.26 8,275.55 38,121.82 173,786.64 695.15
803 Excavation of Footing 77.00 cu. m. 37,626.00 12.00 10.00 22.00 8,277.72 2,295.19 10,572.91 48,198.90 625.96
804(a) Backfilling of Excavated Materials 60.00 cu. m. 3,523.91 12.00 10.00 22.00 775.26 214.96 990.22 4,514.13 75.24
1003 Carpentry and Joinery Works 1.00 L.S 180,000.00 12.00 10.00 22.00 39,600.00 10,980.00 50,580.00 230,580.00 230,580.00
1003(d) Ceiling Works 169.00 sq. m. 118,228.93 12.00 10.00 22.00 26,010.36 7,211.96 33,222.33 151,451.26 896.16
1007 Aluminum Glass Doors 1.00 L.S 139,408.12 12.00 10.00 22.00 30,669.79 8,503.90 39,173.68 178,581.80 178,581.80
1008 Aluminum Glass Window 1.00 L.S 86,336.24 12.00 10.00 22.00 18,993.97 5,266.51 24,260.48 110,596.72 110,596.72
1010 Doors 1.00 L.S 31,059.12 12.00 10.00 22.00 6,833.01 1,894.61 8,727.61 39,786.73 39,786.73
1012 Plumbing Works 1.00 L.S 140,325.62 12.00 10.00 22.00 30,871.64 8,559.86 39,431.50 179,757.11 179,757.11
1014 Pre-painted Metal Roofing 138.00 sq. m. 98,527.96 12.00 10.00 22.00 21,676.15 6,010.21 27,686.36 126,214.32 914.60
1016 Waterproofing 14.00 sq. m. 8,460.84 12.00 10.00 22.00 1,861.39 516.11 2,377.50 10,838.34 774.17
1027 Cement Plaster Finish 800.00 sq.m. 107,589.60 12.00 10.00 22.00 23,669.71 6,562.97 30,232.68 137,822.27 172.28
1100 Conduit, Boxes, and Fittings 90.00 ln. m. 7,050.58 12.00 10.00 22.00 1,551.13 430.09 1,981.21 9,031.79 100.35
1018(a) Tile Works (Glazed Tiles) 75.00 sq. m. 47,132.81 12.00 10.00 22.00 10,369.22 2,875.10 13,244.32 60,377.13 805.03
1018(b) Tile Works (Unglazed Tiles) 96.00 sq. m. 77,643.77 12.00 10.00 22.00 17,081.63 4,736.27 21,817.90 99,461.67 1,036.06
1032 (a-1) Masonry Painting 1600.00 sq. m. 155,044.95 12.00 10.00 22.00 34,109.89 9,457.74 43,567.63 198,612.58 124.13
1032 (a-2) Wooden Painting 202.00 sq. m. 17,875.37 12.00 10.00 22.00 3,932.58 1,090.40 5,022.98 22,898.35 113.36
1101 Wires and Wiring Devices 597.00 ln. m. 30,025.32 12.00 10.00 22.00 6,605.57 1,831.54 8,437.11 38,462.43 64.43
1102 (A) Lighting Fixtures 34.00 set 47,552.69 12.00 10.00 22.00 10,461.59 2,900.71 13,362.30 60,914.99 1,791.62
1102 (B) Panel Boards and Cabinets 1.00 set 7,390.16 12.00 10.00 22.00 1,625.83 450.80 2,076.63 9,466.79 9,466.79
1200 Air Conditioning and Refrigeration System 2.00 set 76,384.27 12.00 10.00 22.00 16,804.54 4,659.44 21,463.98 97,848.25 48,924.13
F.E.A.1.4 Project Billboard 1.00 L.S 6,297.36 12.00 10.00 22.00 1,385.42 384.14 1,769.56 8,066.92 8,066.92
F.E.A.1.5 Construction Safety and Health Program 1.00 L.S 74,579.12 0.00 10.00 10.00 7,457.91 4,101.85 11,559.76 86,138.88 86,138.88
SPL-1 Mobilization/Demobilization 1.00 L.S 34,884.00 0.00 0.00 0.00 - 1,744.20 1,744.20 36,628.20 36,628.20
T O T A L 3,628,403.09 781,624.71 220,501.39 4,630,529.19