Вы находитесь на странице: 1из 3

Date: Day:

12-Oct-18 F

DAILY ACTIVITY REPORT


Project LBL Warehouse Demolition
Owner: LBL Contract No: 002531
Contractor: R.S.Dugeña Demolition Svs DAR No. 000020

Weather Condition
LEGENDS: 12AM
Sunny Windy Max temp: 33*C
recorded at: 2PM
6PM 6AM
Rainy/ Cloudy Stormy Min. Temp: 24*C
recorded at: 5AM
12PM

Work Performed
Accomplishment
Item Activity ID Description & Location Unit Remarks
Today To Date
1 Warehouse 1: Roof Level
R10001 Corrugated Roof Stripping % 5% 95%
R10002 C-Purlins Cutting % 5% 95%
2 Warehouse 2: Roof Level
To be Completed by Contractor

R20001 Corrugated Roof Stripping % 3% 98%

R20002 C Purlins Cutting % 3% 98%


3 Parking: 2nd Floor
PS0001 Steel Plate/Flooring Stripping % 5% 95%
PS0002 C-Purlins Cutting % 10% 95%
PS0003 I-Beams Cutting % 10% 95%
3 Warehouse-Parking Partition
PS0001 C-Purlins Cutting % 0% 75%
Dismantling of G.I. Sheet
PS0002 % 0% 75%
Partition
4 Hauling/Clearing
H0001 Lumber/wood/plywood % 0% 50% On-Going
H0002 Clearing % - - On-Going
H0003 Hauling of I-Beams % - - On-Going

Manpower
Trades Engineer Foreman Safety Leadman Welder Cutter Driver/Operator Total
1 1 1 2 1 7 1 14

Total
Equipment
Description

Backhoe - 1 unit

Total

Material/Tools Delivered to Site

Description Unit Quantity CITEM no. Remarks

Materials:
None
To be Completed by Contractor

Tools
None

Issues/Problems/Incidents

Item Actvity ID Description Comments Action by Date

Prepared by: Signature: Date:


ENGR. PAUL S. MACHON 10/12/2018

Visitors
Name Position Company
ACCOMPLISHMENT PHOTOS

Clearing using Backhoe Clearing using Backhoe

Warehouse Roof Stripping Floor Stripping at Parking