Вы находитесь на странице: 1из 3

Date: Day:

16-Oct-18 T

DAILY ACTIVITY REPORT


Project LBL Warehouse Demolition
Owner: LBL Contract No: 002531
Contractor: R.S.Dugeña Demolition Svs DAR No. 000023

Weather Condition
LEGENDS: 12AM
Sunny Windy Max temp: 31*C
recorded at: 11AM
6PM 6AM
Rainy/ Cloudy Stormy Min. Temp: 24*C
recorded at: 5AM
12PM

Work Performed
Accomplishment
Item Activity ID Description & Location Unit Remarks
Today To Date
1 Warehouse 1: Roof Level
R10002 C-Purlins Cutting % 0% 98%
2 Warehouse 2: Roof Level
R20001 Corrugated Roof Stripping % 2% 100% Done
To be Completed by Contractor

R20002 C Purlins Cutting % 0% 98%


3 Warehouse-Parking Partition
PS0001 C-Purlins Cutting % 0% 75%
Dismantling of G.I. Sheet
PS0002 % 0% 75%
Partition
4 Hauling/Clearing
H0001 Lumber/wood/plywood % 0% 75% On-Going
H0002 Clearing % - - On-Going
H0003 Hauling of I-Beams % - - On-Going
5 Demolition of Concrete/CHB
D0001 Interior Partition Demolition % 15% 90% On-Going

Manpower
Trades Engineer Foreman Safety Leadman Welder Cutter Driver/Operator Total
1 1 1 1 0 6 2 12

Total
Equipment
Description

Backhoe - 1 unit

Total

Material/Tools Delivered to Site

Description Unit Quantity CITEM no. Remarks

Materials:
None
To be Completed by Contractor

Tools
None

Issues/Problems/Incidents

Item Actvity ID Description Comments Action by Date

Prepared by: Signature: Date:


ENGR. PAUL S. MACHON 10/16/2018

Visitors
Name Position Company
ACCOMPLISHMENT PHOTOS

Hauling of Garbages Segragation of Materials