4. (a) Diagram for timing of tasks, showing type and number of staff needed to cover them.
(Monday to Thursday shown only.)
(b) Rostering pattern - 4 days on/2 days off. 3 shifts are required.
E = Early shift, L = Late shift, - = day off
Day M T W T F S S M T W T F
Shift 1 E E E E - - L L L L - -
2 - - L L L L - - E E E E
3 L L - - E E E E - - L L
5. Silver-Meal heuristic
Week Requirement Trial reple- Incremental Total Average Best run Stock
nishment Cost Cost Cost size on hand
1 17 17 500 500 500 37 20
2 8 25 16 516 258 12
3 12 37 48 564 188 lowest 0
4 4 41 24 588 196
6. Silver-Meal heuristic
Week Requirement Trial Incremental Total Average Best run Stock
Replenishment Cost Cost Cost size on hand
1 Decision implemented
2 Decision implemented 2
3 15 13 500 500 500 71 58
4 10 23 20 520 260 48
5 20 43 80 600 200 28
6 4 47 24 624 156 24
7 15 62 120 744 148.8 9
8 3 65 30 774 129 6
9 6 71 72 746 120.86 lowest 0
10 9 80 126 972 121.5