Академический Документы
Профессиональный Документы
Культура Документы
Project Management
Center of Excellence
Practice Exam 1
Answers are shown in blue on the slide following the question slide.
Most answer slides also contain a PMBOK edition 5 reference.
To get the most out of the practice questions, record your answer
before checking it.
2
© International Business Machines 2012
Question 1
3
© International Business Machines 2012
Question 1 Answer
4
© International Business Machines 2012
Question 2
Which of the following is NOT TRUE about project life cycles and
project phases?
5
© International Business Machines 2012
Question 2 Answer
Which of the following is NOT TRUE about project life cycles and
project phases?
6
© International Business Machines 2012
Question 3
7
© International Business Machines 2012
Question 3 Answer
8
© International Business Machines 2012
Question 4
9
© International Business Machines 2012
Question 4 Answer
Ref: Ch 4, Pg 71
Project Integration Management: includes the processes and
activities needed to identify, define, combine, unify, and coordinate
the various processes and project management activities within
the Project Management Process Groups.
10
© International Business Machines 2012
Question 5
A. work package
B. project plan
C. project charter
11
© International Business Machines 2012
Question 5 Answer
A. work package
B. project plan
C. project charter
Which of the following are tools and techniques which can be used
during the Direct and Manage Project Execution Process?
13
© International Business Machines 2012
Question 6 Answer
Which of the following are tools and techniques which can be used
during the Direct and Manage Project Execution Process?
14
© International Business Machines 2012
Question 7
C. Strategic Plan
15
© International Business Machines 2012
Question 7 Answer
C. Strategic Plan
17
© International Business Machines 2012
Question 8 Answer
18
© International Business Machines 2012
Question 9
A. Define Activities
B. Sequence Activities
19
© International Business Machines 2012
Question 9 Answer
A. Define Activities
B. Sequence Activities
20
© International Business Machines 2012
Question 10
C. Fragment Network
D. Activity-On-Node [AON]
21
© International Business Machines 2012
Question 10 Answer
C. Fragment Network
D. Activity-On-Node [AON]
22
© International Business Machines 2012
Question 11
B. Control Schedule
D. Sequence Activities
23
© International Business Machines 2012
Question 11 Answer
B. Control Schedule
D. Sequence Activities
24
© International Business Machines 2012
Question 12
A. Project Charter
B. Requirements Document
25
© International Business Machines 2012
Question 12 Answer
A. Project Charter
B. Requirements Document
26
© International Business Machines 2012
Question 13
27
© International Business Machines 2012
Question 13 Answer
28
© International Business Machines 2012
Question 14
B. Can be scheduled
29
© International Business Machines 2012
Question 14 Answer
B. Can be scheduled
Work Package is the lowest level in the WBS, and is the point, at
which it can be reliably scheduled, cost estimated, monitored and
controlled.
30
© International Business Machines 2012
Question 15
A. Collect Requirements
B. Define Scope
C. Create WBS
D. Validate Scope
31
© International Business Machines 2012
Question 15 Answer
A. Collect Requirements
B. Define Scope
C. Create WBS
D. Validate Scope
32
© International Business Machines 2012
Question 16
A. Disinterested in
B. Affected by
C. Financially invested in
D. Working on
33
© International Business Machines 2012
Question 16 Answer
A. Disinterested in
B. Affected by
C. Financially invested in
D. Working on
Ref: PMBOK Section 4.1.3.1
Although both choices B and D could be correct answers, the project
charter may not be detailed enough to identify those who would be
working on the project, however, the charter should always include
those stakeholders who will be affected by the project
34
© International Business Machines 2012
Question 17
A. Contract
B. email
D. Status meeting
35
© International Business Machines 2012
Question 17 Answer
A. Contract
B. email
D. Status meeting
36
© International Business Machines 2012
Question 18
The project you are managing has nine stakeholders. How many
channels of communication are there between these stakeholders?
A. 9
B. 8
C. 45
D. 36
37
© International Business Machines 2012
Question 18 Answer
The project you are managing has nine stakeholders. How many
channels of communication are there between these stakeholders?
A. 9
B. 8
C. 45
D. 36
38
© International Business Machines 2012
Question 19
39
© International Business Machines 2012
Question 19 Answer
40
© International Business Machines 2012
Question 20
41
© International Business Machines 2012
Question 20 Answer
42
© International Business Machines 2012
Question 21
43
© International Business Machines 2012
Question 21 Answer
45
© International Business Machines 2012
Question 22 Answer
46
© International Business Machines 2012
Question 23
A. Quality Assurance
B. Quality Control
C. Quality Planning
D. Quality Review
47
© International Business Machines 2012
Question 23 Answer
A. Quality Assurance
B. Quality Control
C. Quality Planning
D. Quality Review
48
© International Business Machines 2012
Question 24
A. Edward Deming
B. Philip Crosby
C. Juran
D. Pareto
49
© International Business Machines 2012
Question 24 Answer
A. Edward Deming
B. Philip Crosby
C. Juran
D. Pareto
50
© International Business Machines 2012
Question 25
51
© International Business Machines 2012
Question 25 Answer
52
© International Business Machines 2012
Question 26
53
© International Business Machines 2012
Question 26 Answer
54
© International Business Machines 2012
Question 27
B. Cost baseline
C. WBS
D. Project schedule
55
© International Business Machines 2012
Question 27 Answer
B. Cost baseline
C. WBS
D. Project schedule
56
© International Business Machines 2012
Question 28
D.Budget at completion
57
© International Business Machines 2012
Question 28 Answer
D.Budget at completion
58
© International Business Machines 2012
Question 29
For a project with original assumptions that are no longer relevant due
to a change in conditions, Estimated at Completion (EAC) is most likely
determined by which technique?
A.ETC + AC
B.AC + BAC – EV
D.ETC + EV
59
© International Business Machines 2012
Question 29 Answer
For a project with original assumptions that are no longer relevant due
to a change in conditions, Estimated at Completion (EAC) is most likely
determined by which technique?
A.ETC + AC
B.AC + BAC – EV
D.ETC + EV
EAC uses a new estimate: Equals the actual costs to date plus a new ETC.
EACs are typically based on the actual costs incurred for work completed,
plus an estimate to complete (ETC) the remaining work.
61
© International Business Machines 2012
Question 30 Answer
62
© International Business Machines 2012
Question 31
D.Identify Risks
63
© International Business Machines 2012
Question 31 Answer
D.Identify Risks
64
© International Business Machines 2012
Question 32
All of the following are always INPUTS to the risk management process
except?
A. Historical information
B. Lessons Learned
65
© International Business Machines 2012
Question 32 Answer
All of the following are always INPUTS to the risk management process
except?
A. Historical information
B. Lessons Learned
There will not be project status reports when we first compile the
risks. So it is not always input to the risk management process.
66
© International Business Machines 2012
Question 33
A. Mitigation
B. Transfer
C. Acceptance
D. Avoidance
67
© International Business Machines 2012
Question 33 Answer
A. Mitigation
B. Transfer
C. Acceptance
D. Avoidance
68
© International Business Machines 2012
Question 34
While preparing your risk responses you identify additional risks. What
should you do?
A.Add reserves to the Project to accommodate the new risks and notify
management.
B.Document the risk items, and calculate the expected monetary value
based on probability and impact that result from the occurrences.
C.Determine the risk events and the associated cost, then add the cost
to the project budget as a reserve.
69
© International Business Machines 2012
Question 34 Answer
While preparing your risk responses you identify additional risks. What
should you do?
A.Add reserves to the Project to accommodate the new risks and notify
management.
B.Document the risk items and calculate the expected monetary value
based on probability and impact that result from the occurrences.
C.Determine the risk events and the associated cost, then add the cost
to the project budget as a reserve.
D.Add 10 percent to the project budget and notify the customer
When a new risk is identified, it should go through the risk management process.
A is incorrect as we need to first determine the probability of the risk and its impact and try
to diminish the impact.
C is incorrect as it may not be cost impact alone. It could be schedule impact.
D is incorrect as we cannot add the budget without determining
70
© International Business Machines 2012
Question 35
71
© International Business Machines 2012
Question 35 Answer
72
© International Business Machines 2012
Question 36
A.Interest
B.Influence
C.Skills
D.Involvement
73
© International Business Machines 2012
Question 36 Answer
A.Interest
B.Influence
C.Skills
D.Involvement
74
© International Business Machines 2012